1220-04-03-.36
Referee Test
Cite as Tenn. Comp. R. & Regs. 1220-04-03-.36
(1)
Any customer, by written application to the Commission accompanied by payment of such
fee for the test as may be prescribed by statute or by the Commission from time to time, may
have a test conducted by the utility in the presence of a representative of the Commission.
Upon receipt of such request, the Commission will notify the utility to leave the customer’s
meter in place until arrangements are made for the test. If such test shows that the meter is
in error greater than two percent (2%) fast, the total cost of such test including the cost of
transportation of the Commission’s representative shall be borne by the utility, and the
amount of the fee paid by the customer shall be refunded.