1220-04-04-.30

Request Tests

Last amended: 2018Year: 2026Length: 115 wordsOfficial source

Cite as Tenn. Comp. R. & Regs. 1220-04-04-.30

(1) Upon request by a customer, and at no charge, the utility shall make a test of the meter serving the customer, provided that such tests need not be made more frequently than once in twelve (12) months. (a) The customer, or his/her representative, may be present when his/her meter is tested. REGULATIONS FOR ELECTRIC COMPANIES CHAPTER 1220-04-04 (b) A report of the results of the test together with a copy of Rule 1220-04-04-.31 shall be made to the customer within ten (10) workdays after the completion of the test, and a record of the report, together with a complete record of each test, shall be kept on file at the office of the utility.