1220-04-04-.35
In-Service Performance Tests
Cite as Tenn. Comp. R. & Regs. 1220-04-04-.35
(1)
General In-Service performance tests must be made in accordance with Rules 1220-04-04-
.35(2), 1220-04-04-.35(3), or 1220-04-04-.35(4). These tests may be made on the customer’s
premises or in the utility’s meter shop. However, it is recommended that meters associated
with instrument transformers, or phase shifting transformers, or those having mechanical
contact devices, be tested on the customer’s premises. Tests made for other purposes, such
as request tests or referee tests, must not be counted as in-service performance tests. All
meters on a utility’s system must be tested in accordance with a single program, which must
be one of the following:
(a)
At a fixed periodic interval in accordance with 1220-04-04-.35(2).
(b)
At a variable interval in accordance with 1220-04-04-.35(3).
(c)
An acceptable statistical sampling program in accordance with 1220-04-04-.35(4).
REGULATIONS FOR ELECTRIC COMPANIES
CHAPTER 1220-04-04
(2)
Periodic Test Schedule
If this option is used, the basic periodic test interval for meters shall not be longer than
provided for in American National Standard for Electric Meters – ANSI C 12.1, latest edition,
and as follows for secondary standards:
(a)
Portable electronic watt-hour standards
..............................................................yearly
(b)
Indicating voltmeters
.........................................................................................yearly
(c)
Instrument transformer standards
...............................................................as required
(3)
Variable Interval Plan
(a)
If this option is used, the variable interval plan shall conform to American National
Standard for Electric Meters - ANSI C 12.1, latest edition, for all meters that do not
have an additional mechanical attachment such as a thermal or mechanical register.
(b)
The variable interval plan shall be accompanied by an adequate policy for testing
meters on request and a procedure whereby unusually high or low bills for service
would be detected and investigated.
(4)
Statistical Sampling
(a)
If this option is used, the statistical sampling plan shall conform to American National
Standard for Electric Meters - ANSI C 12.1, latest edition, and shall use American
Standard for Quality Control, ANSI, ASQCZ1.9, latest edition, to select sample
quantities and to analyze test results, for all meters that do not have an additional
mechanical attachment such as a thermal or mechanical register.
(b)
A statistical sampling program shall included an adequate policy for testing meters on
request and a procedure whereby unusually high or low bills for service would be
detected and investigated.
(c)
An acceptable sampling plan is one in which a sample will, ninety-five (95) times out of
one hundred (100), correctly identify a homogenous group of meters, which has at
least ninety-seven and one half percent (97.5%) of the group within the limits ninety-
eight percent to one hundred two percent (98% - 102%) registration on in-service
performance test. If a group of meters does not meet acceptable performance criteria,
then corrective action must be taken.
(d)
The corrective action may consist of an accelerated test program to raise the accuracy
performance of the group from service. An accelerated test program should provide for
testing at rates that vary in accordance with the calculated percentage of defective
meters in rejected groups. In its application to an individual group the rate of testing
should be such that the required corrective action is completed in four (4) years, but not
more than twenty-five percent (25%) of the meters in the group need to be tested in
any one (1) year. Accelerated testing may be discontinued when the test results
indicate that the rejected group is within acceptable limits.
(e)
Records shall be maintained and tabulated to indicate the number of meters in each
homogeneous group in service at the beginning of each year, the number of meters
making up the sample for each homogeneous group, the test results for each group,
and any necessary corrective action taken.
REGULATIONS FOR ELECTRIC COMPANIES
CHAPTER 1220-04-04