1220-04-04-.46
Interruptions Of Service
Cite as Tenn. Comp. R. & Regs. 1220-04-04-.46
(1)
Each utility shall make reasonable efforts to avoid interruptions of service but when
interruptions occur, service shall be re-established within the shortest time practicable,
consistent with safety.
(a)
Each utility shall keep records of interruptions of service on its primary distribution
system and shall make an analysis of the records for the purpose of determining steps
to be taken to prevent recurrence of such interruptions. Such records should include
the following information concerning the interruptions:
1.
Cause.
2.
Date and time.
3.
Duration.
(b)
The log for each unattended substation must show interruptions that require attention
to restore service, with the estimated time of interruption.
(c)
Planned interruptions shall be made at a time that will not cause unreasonable
inconvenience to customers and shall be preceded, if feasible, by adequate notice to
those who will be affected.
(d)
Each utility shall notify the Commission by telephone or telegraph of any service
interruption to twenty-five percent (25%) or more of its distribution customers or loads
of twenty five thousand (25,000) kW or more when such interruptions last for more than
two (2) hours.