1220-04-05-.28
Facilities And Equipment For Meter Testing
Cite as Tenn. Comp. R. & Regs. 1220-04-05-.28
(1)
Each utility shall maintain or have access to a meter shop for the purposes of inspecting,
testing, and repairing meters. The shop shall be open for inspection by authorized
representatives of the Commission at all reasonable times, and the facilities and equipment,
as well as the methods of measurements and testing employed, shall be subject to the
approval of the Commission.
(a)
The area within the meter shop used for the testing of meters shall be designed so that
the meters and meter testing equipment are protected from drafts and excessive
changes of temperature. The meters to be tested shall be stored in such manner that
the temperature of the meters is substantially the same as the temperature of the
prover.
(b)
Working Standards
Each utility shall own and maintain, or have access to, at least one (1) approved bell
type prover of five (5) cubic foot capacity, and all other equipment necessary to test
meters, which shall be installed in the meter room.
1.
Means shall be provided to maintain the temperature of the liquid in the meter
prover at substantially the same level as the ambient temperature in the prover
room.
2.
The meter prover shall be maintained in good condition and correct adjustment
so that it shall be capable of determining the accuracy of any service meter to
within one-half of one percent (.5%).
Each utility having meters which are too large for testing on a five (5) cubic foot
bell prover may use a properly designed flow prover for testing the large meters.
(c)
Working standards must be checked periodically (see Rule 1220-04-05-.26(e)) by
comparison with a secondary standard.
1.
Bell provers must be checked with a one (1) cubic foot bottle which has been
calibrated by the National Bureau of Standards.
2.
Rotary displacement test meters must be checked with a bell prover of adequate
capacity which has been calibrated by representatives of the National Bureau of
Standards.
(d)
Extreme care must be exercised in the use and handling of standards to assure that
their accuracy is not disturbed.
REGULATIONS FOR GAS COMPANIES
CHAPTER 1220-04-05
(e)
Each standard must be accompanied at all times by a certificate or calibration card,
duly signed and dated, on which are recorded the corrections required to compensate
for errors found at the customary test points at the time of the last previous test.
(f)
Each utility must have properly calibrated orifices, as may be necessary, to achieve the
rates of flow required to test the meters on its system.