R652-70-1800

R652-70-1800. Overhead Clearance

Last amended: 2022Length: 39 wordsOfficial source

Cite as Utah Admin. Code R652-70-1800

Overhead clearance between the ordinary high water mark and any structure, pipeline, or transmission line must be sufficient to pass the largest vessel which may reasonably be anticipated to use the subject waters in the vicinity of the easement.
R652-70-1800: R652-70-1800. Overhead Clearance | Justis AI