R746-312-16
R746-312-16. Public Utility Maps, Records, and Reports
Cite as Utah Admin. Code R746-312-16
(1) Each public utility shall maintain current records of interconnection customer generating facilities showing size, location, generator type, and date of interconnection authorization.
(2) By July 1 of each year, each public utility whose governing authority is the commission shall submit to the commission an annual report with the following summary information for the previous calendar year:
(a) the total number of generating facilities approved and their associated attributes including resource type, generating capacity, and zip code of the generating facility location;
(b) the total rated generating capacity of generating facilities by resource type;
(c) for net metering interconnections, the total net excess generation kilowatt-hours received from interconnection customers by month; and
(d) for net metering interconnections, the total amount of excess generation credits in kilowatt-hours, and their associated dollar value that have expired at the end of each annualized billing period.