R746-318-202

R746-318-202. The Commission's Review of Large Load Contracts

Last amended: 2026Length: 93 wordsOfficial source

Cite as Utah Admin. Code R746-318-202

(1) The Commission shall approve or disapprove an application for approval of a large load contract within 60 days of the application being filed. (2) The Commission shall approve an application for a large load contract if the Commission finds: (a) the contract complies with Title 54, Chapter 26, Large-Scale Electric Service Requirements; (b) the large load customer bears each just and reasonable incremental cost attributable to receiving the requested electric service; and (c) existing ratepayers do not bear costs justly and reasonably attributable to providing electric service for the large load customer.
R746-318-202: R746-318-202. The Commission's Review of Large Load Contracts | Justis AI