R23-3-3. When a Program Document is Required

Last amended: 2025Length: 82 wordsOfficial source

Cite as Utah Admin. Code R23-3-3

(1) For capital development projects, a program document must be completed before the design may begin unless the director determines that a program document is not needed for that specific project. Examples of capital development projects that may not require a program document include land purchases, building purchases requiring little or no remodeling, and projects repeating a previously used design. (2) For capital improvement projects, the director shall determine whether the nature of the project requires that a program document be prepared.