R354-15-105

R354-15-105. Dividing a Procurement to Avoid Using a Standard Procurement Process

Last amended: 2021Length: 77 wordsOfficial source

Cite as Utah Admin. Code R354-15-105

(1) It is prohibited for a person knowingly to divide a single Procurement into multiple smaller Procurements if dividing the single Procurement: (a) is done with the intent to avoid the use of a Standard Procurement Process that would have otherwise been required if the Procurement had not been divided; (b) constitutes prohibited conduct under Section R354-2-103; or (c) is otherwise prohibited by this Procurement Procedure. (2) A violation of Subsection (1) is subject to Subsection R354-15-104(4).
R354-15-105: R354-15-105. Dividing a Procurement to Avoid Using a Standard Procurement Process | Justis AI