R432-4-12

R432-4-12. Construction Inspections

Last amended: 2025Length: 88 wordsOfficial source

Cite as Utah Admin. Code R432-4-12

(1) The applicant or licensee shall allow OL to conduct interim inspections during construction. (2) Before OL conducts a final construction inspection, the applicant or licensee shall pay the OL construction plan review fee and inspection fee in accordance with the fee schedule established by the Legislature. (3) The applicant or licensee shall schedule a final construction inspection with OL before utilization when the project is complete and furnishings and equipment are in place. (4) The applicant or licensee shall correct any noncompliant item before licensure and utilization.