WAC 173-407-130
WAC 173-407-130. Emissions performance standard under Part II
(1) A baseload electric generation facility or unit or baseload electric cogeneration facility or unit must comply with the GHG EPS in subsection (2) of this section in effect at the time when the facility or unit triggers the applicability in WAC 173-407-120 .
(2) GHG EPS.
Table 1
GHG EPS by Time Period
GHG EPS lb GHG/MWh First Applicable Date Last Applicable Date 1,100 July 1, 2008 March 23, 2018 970 March 24, 2018 Determined by chapter 194-26 WAC Chapter 194-26 WAC (Starting March 24, 2018)*
GHG EPS
lb GHG/MWh
First Applicable Date
Last Applicable Date
1,100
July 1, 2008
March 23, 2018
970
March 24, 2018
Determined by chapter 194-26 WAC
Chapter 194-26 WAC (Starting March 24, 2018)*
* Commerce reviews and, if appropriate, updates the GHG EPS every five years as directed by RCW 80.80.050 .
*
Commerce reviews and, if appropriate, updates the GHG EPS every five years as directed by RCW 80.80.050 .
(3) A facility may comply with the GHG EPS through the use of:
(a) Fuel and power plant design; or
(b) GHG emission control and sequestration methods meeting the requirements of WAC 173-407-220 or 173-218-115, as appropriate.