WAC 296-900-15015
WAC 296-900-15015. Progress reports
(1) The employer must submit written progress reports on corrections when required in the citation and notice (C&N) or corrective notice of redetermination (CNR), and briefly explain the:
(a) Status of each violation.
(b) Action taken to correct each violation.
(c) Date each action has or will be taken.
What to expect from DOSH:
(2) DOSH will state in the C&N or CNR if progress reports are required, including:
(a) Items that require progress reports.
(b) Date when an initial progress report must be submitted. The initial progress report is due no sooner than 30 calendar days after you submit a correction action plan.
(c) Whether additional progress reports are required, and the dates by which they must be submitted.