WAC 468-16-060. Criteria for a determination of inability to comply with performance schedules

Last amended: 1993Year: 2026Length: 97 wordsOfficial source
The following discrepancies may be cause for a determination of inability to comply with performance schedules: (1) A majority of responses to inquiries made to owners of previously completed projects reveal that projects have not been completed on time; or (2) A major portion of projects completed within the last three years for the department have not been completed on time; or (3) When two or more consecutive performance reports are rated below standard in the area of "progress of work"; or (4) Neglectful or willful failure to meet interim completion dates as defined in the contract.