WAC 136-130-050. Supplemental rules in northeast region (NER)
Each county in the NER may submit projects requesting RATA funds not to exceed 25 percent of the forecasted NER biennial apportionment.
Bridge projects may be submitted requesting RATA funds under one of the following conditions:
(1) Bridges must be approved for federal bridge funding and RATA funds shall be used only as a match for such federal funding. Bridges will be ranked for RATA funding using the WSDOT priority list and may be added to the NER Category 1 priority array at any time during the biennium upon approval of the bridge for federal bridge funding.
(2) A stand-alone bridge project may be submitted as an ordinary reconstruction or 3R RAP project provided that its priority rating has been computed by the bridge rating method in the NER RAP rating procedures. Such projects shall not be considered for funding from the bridge reserve described above.