WAC 173-187-110
WAC 173-187-110. Financial responsibility amounts for facilities
The owner or operator of any facility that is covered by this chapter must demonstrate financial responsibility as defined in the table below:
Facility Type Financial Responsibility Amounts Maximum Amount Required Class 1 facility (oil handling facilities including refineries and marine terminals) $12,500 per barrel times worst case spill (WCS) volume $300,000,000 Class 1 facility (offshore facilities) $12,500 per barrel times worst case spill (WCS) volume $300,000,000 Class 1 facility (pipelines) $12,500 per barrel times worst case spill (WCS) volume $300,000,000 Class 2 facility (mobile tank units) $12,500 per barrel times 30 percent of the entire contents of the container(s) in which the oil is stored or transported $5,000,000 Class 3 facility (small marine terminals) $12,500 per barrel times the volume of the largest facility tank $5,000,000
Facility Type
Financial Responsibility Amounts
Maximum Amount Required
Class 1 facility (oil handling facilities including refineries and marine terminals)
$12,500 per barrel times worst case spill (WCS) volume
$300,000,000
Class 1 facility (offshore facilities)
$12,500 per barrel times worst case spill (WCS) volume
$300,000,000
Class 1 facility (pipelines)
$12,500 per barrel times worst case spill (WCS) volume
$300,000,000
Class 2 facility (mobile tank units)
$12,500 per barrel times 30 percent of the entire contents of the container(s) in which the oil is stored or transported
$5,000,000
Class 3 facility (small marine terminals)
$12,500 per barrel times the volume of the largest facility tank
$5,000,000