The Honorable Savannah Hill Wilkins
Tucker County Prosecuting Attorney
Tucker County Courthouse Annex
211 First Street, Suite 207
Parsons, WV 26287
Dear Prosecutor Wilkins:
Your office has asked for an Opinion of the Attorney General about the ownership and
ongoing maintenance of a dike or diversion wall on property that is currently legally owned by
the City of Parsons. This Opinion is being issued under West Virginia Code § 5-3-2, which
provides that the Attorney General "may consult with and advise the several prosecuting
attorneys in matters relating to the official duties of their office." When this Opinion relies on
facts, it depends solely on the factual assertions in your correspondence with the Office of the
Attorney General.
You explain that the Tucker County Commission was a sponsor for several different
projects following a severe flood in 1985, including a dike that is currently owned by the City of
Parsons. With the Commission serving as a sponsor, the City contacted the U.S. Soil
Conservation Service, now known as the U.S. Natural Resources Conservation Service (NRCS),
to obtain funding for dike repairs through the Emergency Watershed Protection (EWP) program.
Most recently, the Commission served as a sponsor to secure additional funding in August 2014
to repair damage to the dike. Citing a federal regulation, the Prosecuting Attorney at that time
concluded that the County Commission was deemed the owner of the dike because the
Commission had served as the sponsor for the project. The dike is once again in need of repairs,
and the City of Parsons is insisting that the Tucker County Commission be responsible for these
repairs.
With these facts in mind, your letter raises the following questions:
Hon. Savannah Hill Wilkins
Page 2
1.
Does the County Commission "own" the dike because of its
sponsorship assistance in funding?
2.
What ongoing duty does the County Commission have for the
maintenance and repair of the dike?
We conclude that, under the facts you have described, the County Commission is not the
owner of the dike. We also conclude that the 1986 Tucker County Commission likely agreed to
be responsible for maintaining the dike for at least some time. But the terms and duration of that
maintenance are likely limited by agreement or by public policy.
Discussion
The U.S. Department of Agriculture administers several programs to help affected areas
recover from natural disasters. Relevant here, the Emergency Watershed Protection (EWP)
program offers financial and technical assistance to relieve imminent threats to life and property
caused by natural disasters that impair a watershed. You ask whether the county's involvement
in securing funds for the Parsons dike through the EWP program has obliged the county to
maintain and repair the dike indefinitely.
I.
The County Commission Does Not Own the Dike.
First, the County Commission does not own the dike simply by serving as the project
sponsor.
All EWP projects must have a project sponsor, which can include any "local unit of
government with a legal interest in or responsibility for the values threatened by a watershed
emergency." 7 C.F.R. § 624.4(g). These project sponsors must be able to "obtain[ necessary
land rights" and "carry[ out any operation and maintenance responsibilities that may be
required." Id. But nothing in the relevant regulations requires the sponsor to own the project.
Indeed, the regulations contemplate the existence of both the project sponsor and the "landuser":
one who is the "owner" of the "land involved." Id. § 654.2 (defining "Landuser"). Likewise, the
regulations repeatedly refer to "landowners" and "sponsors" separately. See, e.g., id. § §§ § 624.2,
654.2. But in contrast, the Sponsor is there to "provide local responsibility for [the]
financially-assisted local project." Id. § 654.2; cf. id. § 624.4 (defining "project sponsor" as the
state government entity "with a legal interest in or responsibility for the values threatened by a
watershed
emergency and is capable of maintain[ing]" it.). "In a given statute, the same
term usually has the same meaning and different terms. usually have different meanings."
Pulsifer V. United States, 601 U.S. 124, 149 (2024).
In short, landusers (that is, owners) and sponsors play distinct roles. Because the
regulatory scheme contemplates a difference between the landowner and the project sponsor and
provides no direct language requiring project sponsors to own the land, the County Commission
did not become the Dike's owner by agreeing to sponsor its development.
Hon. Savannah Hill Wilkins
Page 3
II.
The County Commission Was Likely Responsible for At Least Some Repairs and
Maintenance.
Second, the County Commission likely accepted responsibility in 1986 for the dike's
maintenance under an operation and maintenance agreement.
When the County Commission agreed to sponsor the dike, it did so under the regulations
provided by the Emergency Watershed Protection program and the program's administrator, the
Natural Resources Conservation Service. See 7 C.F.R. § 624.1 ("The Natural Resources
Conservation Service (NRCS) [is] responsible for administering the Emergency Watershed
Protection (EWP) Program."). These regulations discuss the need for a project sponsor to handle
the ongoing maintenance for federally funded projects, like the prior dike repairs. In particular,
"[s]ponsors must [a]gree to provide for any required operation and maintenance of the
completed emergency measures." Id. § 624.6(a)(2)(iii). "Typically, the word 'must' is afforded
a mandatory connotation." Guido v. Guido, 222 W. Va. 528, 532, 667 S.E.2d 867, 871 (2008)
(cleaned up).
The details for the sponsor's operation and maintenance obligations are to be found in an
"operation and maintenance agreement" (O&M agreement). See 7 C.F.R. §§ 654.40-41; see also
id. § 624.8(c) ("Before the release of financial assistance, NRCS will enter into a Cooperative
Agreement with a sponsor that specifies the responsibilities of the sponsor under this part,
including any required operation and maintenance responsibilities."). When a sponsor applies
for funds for a particular project under the EWP program-as the County Commission did-the
State Conservationist "determine[s]" if an "O&M agreement is necessary." Id. § 654.40.
However, the State Conservationist does not have full discretion. An O&M agreement is
required if the EWP project "needs to be operated and maintained in order to serve its intended
purpose" or "to insure that [the project] will not become hazardous." Id. § 654.41(a)(1)-(2).
Given the 2014 repairs and current repair needs, it seems likely that the dike project
would have satisfied that definition and, thus, had an O&M agreement. After all, the dike's
original purpose was to "deflect[] the river flow"-a purpose that is plainly undermined by
breaches in the dike. See Letter from Bernard R. Lindstrom, Colonel, Corps of Eng'rs, to David
B. McKinley, W. Va. House Rep. (undated) (on file with Commission). And the project could
become hazardous if flood waters are allowed to flow unabated, as evidenced by the flooding in
1985.
The O&M agreement should have laid out the terms and duration of the County
Commission's maintenance duties for the dike. By regulation, the O&M agreement "shall
include" the sponsor's "known and anticipated" maintenance for the project, the sponsor's
"explanation of how the [maintenance] activities may be carried out," the sponsor's "general
time frame" for inspecting and maintaining the project, and how the sponsor will record and
report their obligations. 7 C.F.R. § 654.19.
In short, even though the County Commission doesn't own the dike, it may still be
responsible for the dike's ongoing maintenance because, in its role as project sponsor, it
"[a]gree[d] to provide for any required operation and maintenance of the completed emergency
Hon. Savannah Hill Wilkins
Page 4
measures." Id. § 624.6(a)(2)(iii); see also id. § 654.11(a) (providing that a sponsor is
"responsible for financing and performing needed operation and maintenance (O&M) of
project measures"); cf. id. § 624.6(b)(2)(ii) (providing that "EWP assistance will not be used to
perform operation or maintenance, such as the periodic work that is necessary to maintain the
efficiency and effectiveness of a measure to perform as originally designed and installed").
III.
Lacking More Information, We Are Unable To Determine The Extent Of Any
Continuing Obligations Of The County To Maintain the Dike.
We have requested but have not received any record of an O&M agreement. Although
we have received a copy of a project agreement between the Soil Conservation Service and the
County Commission, the agreement does not include any provisions speaking specifically to
operation and maintenance.
The O&M agreement could not require the County Commission to maintain the dike
forever. After all, the regulation says an O&M agreement must define the "duration" of the
sponsor's maintenance. 7 C.F.R. § 654.14. The start date of that duration begins when the
project is completed and may "continue through (1) the evaluated life of the project"; "(2) the
evaluated life of measures that are economically evaluated as a unit"; or "(3) the useful life of
cost-shared measures that are for land conservation or land utilization." Id. In short, the O&M
agreement should have told the signing County Commission the duration of its dike maintenance
obligations. But lacking any copy of the agreement, we are unable to offer any opinion on its
limits.
Any ongoing duty of the County Commission to maintain the dike may face legal
challenges beyond the O&M agreement. As with all county commissions, the Tucker County
Commission is "created by statute, and possessed only of such powers as are expressly conferred
by the Constitution and legislature, together with such as are reasonably and necessarily implied
in the full and proper exercise of the powers so expressly given." Syl. pt. 1, State ex rel. State
Line Sparkler of WV Ltd. V. Teach, 187 W. Va. 271, 418 S.E.2d 585 (1992); see generally W. VA
CONST. art. IX, § 11 ("Powers of county commissions").
Our Supreme Court has observed that it is against public policy for county commissions
to enter long-term commitments that tie the hands of future commissions. "[I]t is beyond the
power of the governing body of a municipality to tie the hands of future governing bodies in
exercising the full jurisdiction of their office by depriving them of a discretion which public
policy demands remain unimpaired." Rogers V. City of South Charleston, 163 W. Va. 285, 293,
256 S.E.2d 557, 562 (1979). So, for instance, the Court rejected a three-year employment
contract that would allow a county court the "power to extend through contracts the period of
their control long beyond the terms for which they were elected, and thus to deprive their
regularly elected successors of the important right to exercise some of the functions normally
incident to the office." Barbor V. Cnty. Ct. of Mercer Cnty., 85 W. Va. 359, 362, 101 S.E. 721,
722 (1920). These long-term contracts are "overrule[ed]" by "[p]ublic policy" because they
"cramp the powers of the town, defeat the performance of some of its essential functions, and
[are] very hurtful to public interests." Bradford V. W. Va. Solid Waste Mgmt. Bd., 246 W. Va.
Hon. Savannah Hill Wilkins
Page 5
17, 25, 866 S.E.2d 82, 90 (2021) (quoting Town of Davis V. Filler, 47 W. Va. 413, 415, 35 S.E.
6, 7 (1900)).
Although there is relatively little West Virginia case law applying the public-policy
analysis, the key theme is protecting local governments' statutory "discretion." In cases like
Davis, Barbor, Rogers, and Bradford, the Court's refrain is that because a municipality is a
creation of statute, it may not act to limit a future municipality's statutorily granted discretion.
That's because letting a local government's governing body bind a future governing body's
discretion would, in fact, elevate the current body above its originating statute and de facto allow
it to amend a statutory grant of power.
We recognize that these standards do not provide a simple, timebound, brightline test
(e.g., no contracts over two years). Instead, the analysis requires a clear sense of what a local
government is statutorily entitled to do and what the current or past governing body has agreed
to. Because we do not have the O&M agreement, we cannot definitively complete that analysis.
Even so, it appears likely that the County Commission would have exceeded its powers if it tied
the hands of the current commission by somehow agreeing to maintain the dike forever.
Conclusion
The Tucker County Commission does not own the dike and likely does not have a duty to
maintain it. Without a copy of the possible O&M agreement though, it is impossible to answer
your second question (concerning the duration of these obligations) definitively.
Sincerely,
John B.
John B. McCuskey
Attorney General
Michael R. Williams
Solicitor General
Spencer J. Davenport
Frankie A. Dame
Assistant Solicitors General