CSR 45-14-21

CSR 45-14-21. Conflict with Other Permitting Rules

SupersededLast amended: 2012Length: 121 wordsOfficial source

Cite as W. Va. Code R. § 45-14-21

45-14-21. Conflict with Other Permitting Rules. 21.1. For sources required to obtain a permit under this rule, the provisions of 45CSR13 requiring a permit do not apply, so that only a single permit is required; provided, however, that: 21.1.a. The base permit application fee of $1,000 pursuant to 45CSR22, subdivision 3.4.a shall apply to such sources in addition to other applicable fees; and 21.1.b. Any permit issued under this rule includes conditions that ensure compliance with the provisions of 45CSR13 to the extent applicable to any regulated air pollutant (as defined in 45CSR13) not otherwise covered under this rule. 21.2. For sources that may be subject to 45CSR13, 45CSR14 and/or 45CSR19, the more stringent provisions of each applicable rule shall apply.