§45-23-3. Requirements.
3.1. No person may construct, reconstruct, modify, or operate, or cause to be constructed, modified, or operated a MSW landfill which results in a violation of this rule.
3.2. Each new MSW landfill shall comply with all of the applicable standards, requirements and provisions of 40 CFR Part 60 Subpart WWW, as amended including any reference methods, performance specifications and other test methods associated with Subpart WWW, which are herein incorporated by reference with the exceptions as follows:
3.2.a. In lieu of 40 CFR 60.758(a), the following provision applies: Each owner or operator of a MSW landfill subject to the provisions of 40 CFR 60.752(b) shall keep for at least 5 years up-to-date, readily accessible, on-site records of the maximum design capacity, surface monitoring design plan, the current amount of solid waste in-place, and the year-by-year waste acceptance rate. Either paper copy or electronic format records are acceptable.
3.3. Each existing MSW landfill shall comply with all of the applicable standards, requirements and provisions of 40 CFR Part 60 Subpart Cc and 40 CFR Part 60 Subpart WWW, as referenced in 40 CFR 60 Subpart Cc, and as amended including any reference methods, performance specifications and other test methods associated with Subpart WWW, which are herein incorporated by reference with the exceptions as follows:
3.3.a. '40-60.750
3.3.b. In lieu of 40 CFR 60.752(b)(2)(i)(B), the following provision applies: The collection and control system design plan shall include any alternatives to the operational standards, test methods, procedures, compliance measures, monitoring, record keeping or reporting provisions of 40 CFR 60.753 through 40 CFR 60.758 proposed by the owner or operator. In addition, the collection and control design plan must specify:
3.3.b.1. The date by which contracts for control system/process modifications shall be awarded, (which shall be no later than 20 months after the date the NMOC emission rate is first calculated to meet or exceed 50 megagrams per year).
3.3.b.2. The date by which on-site construction or installation of the air pollution control device(s) or process changes will begin (which shall be no later than 24 months after the date the NMOC emission rate is first calculated to meet or exceed 50 megagrams per year).
3.3.b.3. The date by which the construction or installation of the air pollution control device(s) or process changes capable of meeting the emission standards established under 40 CFR 60.752(b)(2)(iii) will be complete (which shall be no later than 30 months after the date the NMOC emission rate is first calculated to meet or exceed 50 megagrams per year).
3.3.b.4. The date by which the MSW landfill will achieve compliance with 40 CFR 60.753 (which shall be no later than 30 months [except where 40 CFR 60 indicates otherwise] after the date the NMOC emission rate is first calculated to meet or exceed 50 megagrams per year).
3.3.b.5 The date by which the MSW landfill will demonstrate compliance with applicable requirements by conducting a performance test in accordance with procedures specified by the Director (which shall be no later than 180 days after completion of construction or installation of the air pollution control device).
3.3.c. In lieu of 40 CFR 60.758(a), the following provision applies: Each owner or operator of a MSW landfill subject to the provisions of 40 CFR 60.752(b) shall keep for at least 5 years up-to-date, readily accessible, on-site records of the maximum design capacity, surface monitoring design plan, the current amount of solid waste in-place, and the year-by-year waste acceptance rate. Either paper copy or electronic format records are acceptable.