23 CAR § 469-501. Interconnection with the grid

Last amended: 2026Length: 93 wordsOfficial source
(a) If the operator of a wind energy facility or wind energy facility expansion seeks to interconnect into the grid, the operator shall provide any approved Generation Interconnection Agreement with any relevant regional transmission organization, independent transmission system operator, or similar organization, or with any relevant transmission owner, or reference to any such Federal Energy Regulatory Commission docket in which such Generation Interconnection Agreement was approved. (b) The operator shall provide this information in the same docket in which it received the permit for the wind energy facility or wind energy facility expansion.