27 CAR § 91-1102
27 CAR § 91-1102. Preliminary engineering agreement
Length: 62 wordsOfficial source
(a) An executed PE agreement establishes the estimated cost for preliminary engineering services if a utility owner is not adequately staffed to carry out the necessary preliminary engineering required for the relocations.
(b) Reimbursement will be made at the same ratio as the relocation of the facilities is eligible.
(c) The PE agreement may be on an actual cost or lump-sum basis.