359 NLRB 1419
Aggregate Industries US
AGGREGATE INDUSTRIES
1419
359 NLRB No. 156
Aggregate Industries and Teamsters, Chauffeurs,
Warehousemen and Helpers, Local 631, affiliat-
ed with International Brotherhood of Team-
sters. Cases 28–CA–023220 and 28–CA–023250
July 8, 2013
DECISION AND ORDER
BY CHAIRMAN PEARCE AND MEMBERS GRIFFIN
AND BLOCK
On June 6, 2011, Administrative Law Judge Burton
Litvack issued the attached decision. The Acting Gen-
eral Counsel and the Charging Party filed exceptions and
supporting briefs, the Respondent filed an answering
brief, and the Acting General Counsel and the Charging
Party filed reply briefs. The Respondent filed cross-
exceptions and a supporting brief, the Acting General
Counsel filed an answering brief, and the Respondent
filed a reply brief.
The National Labor Relations Board has considered
the decision and the record in light of the exceptions and
briefs and has decided to affirm the judge’s rulings, find-
ings,1 and conclusions only to the extent consistent with
this Decision and Order.2
The principal issues presented are whether the Re-
spondent violated Section 8(a)(5) and (1) of the Act by
unilaterally moving a classification of drivers and the
work they performed from coverage under the Construc-
tion Agreement to coverage under the less-favorable
Ready-Mix Agreement; by bypassing the drivers’ exclu-
sive collective-bargaining representative, Teamsters Lo-
cal 631 (Union), and dealing directly with those drivers;
and by denying employment opportunities to those driv-
ers who refused to agree to work under the terms and
conditions of the Ready-Mix Agreement. The judge
dismissed these allegations. For the reasons set forth
below, we reverse and find that the Respondent violated
the Act as alleged.
Contrary to the judge, we find that the Respondent’s
movement of the drivers was a change in the scope of the
bargaining units—a permissive subject of bargaining—
and therefore could not be implemented without first
reaching agreement with the Union. We further find that
even if the Respondent’s action is properly characterized
1 The Respondent has excepted to some of the judge’s credibility
findings. The Board’s established policy is not to overrule an adminis-
trative law judge’s credibility resolutions unless the clear preponder-
ance of all the relevant evidence convinces us that they are incorrect.
Standard Dry Wall Products, 91 NLRB 544 (1950), enfd. 188 F.2d 362
(3d Cir. 1951). We have carefully examined the record and find no
basis for reversing the findings.
2 We shall modify the judge’s conclusions of law and remedy, and
substitute a new Order and notice, to conform to the violations found,
and to correct inadvertent errors.
as a transfer of unit work, and therefore constituted a
mandatory subject of bargaining, the Respondent violat-
ed the Act by acting without giving the Union sufficient
notice and opportunity to bargain concerning the
change.3
I. FACTS
A. The Respondent’s Operations; the
Construction Agreement
The Respondent quarries and hauls aggregate (crushed
stone and related materials), performs grading and pav-
ing work, operates ready-mix (concrete) batch plants,
hauls cement and ready-mix, and conducts ready-mix
operations at construction sites. It operates under various
trade names, including Frehner Construction, SNP, and
Regal Materials. Frehner and SNP haul aggregate from
Respondent’s Sloan Quarry to construction sites and on
those construction sites. Regal Materials hauls aggregate
to and between batch plants and hauls cement powder
from cement plants to the batch plants.
For many years, the drivers employed by Frehner and
SNP have been represented by the Union. From at least
2001 until 2010, Frehner and SNP were members of the
Association of General Contractors (AGC), which nego-
tiated the Construction Agreement, a multiemployer con-
tract, with the Union and other labor organizations. The
most recent Construction Agreement ran from June 1,
2007, to June 30, 2010. In April 2010, Frehner and SNP
withdrew bargaining authority from the AGC. They con-
tinued to bargain alongside the AGC but advised the Un-
ion that both Frehner and SNP were bargaining for sepa-
rate contracts.
The bargaining unit specified by the Construction
Agreement (the Construction bargaining unit) includes
five classifications of drivers. This case involves the
“off-site material haul” drivers, who haul aggregate from
Sloan Quarry to construction sites. Until the events un-
derlying this case, they were the only drivers employed
by the Respondent who made deliveries to or on con-
struction sites.
3 We agree with the judge, for the reasons set forth in his decision,
that the Respondent violated Sec. 8(a)(5) and (1) of the Act by unilater-
ally reassigning mechanical sweeper truckdriving job duties to employ-
ees in the bargaining unit represented by Laborers’ International Union
of North America, Local 872 (Laborers) when the work had previously
been performed by employees in the Teamsters-represented Construc-
tion Bargaining unit; by unilaterally changing the terms and conditions
of employment of two mechanical sweeper driver employees by treat-
ing them as members of the Laborers’ bargaining unit; and by dealing
directly with the two mechanical sweeper drivers regarding their terms
and conditions of employment.
1420
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
B. The Ready-Mix Agreement
In 2006, the Board certified the Union as the repre-
sentative of a unit of drivers and mechanics at Regal Ma-
terials (the Ready-Mix bargaining unit).4 In December
2007, the Union won a decertification election and was
again certified to represent the same unit. After the De-
cember 2007 certification, the Union and Regal Materials
negotiated
a
collective-bargaining
agreement—the
Ready-Mix Agreement—effective July 1, 2008, to May
31, 2012. The Ready-Mix Agreement includes the clas-
sifications “Transport Drivers (Bulk)” and “Transport
Drivers (S&G).” Transport Drivers (Bulk) transport ce-
ment powder from cement plants to batch plants, and
Transport Drivers (S&G) drive “plant haul” from quar-
ries to batch plants as well as between batch plants.5
There is a substantial difference in wage rates under
the Construction Agreement and the Ready-Mix Agree-
ment. During the last year of the Construction Agree-
ment (from July 1, 2009, to July 1, 2010), drivers were
paid between $30.29 and $31.28 per hour, with $6.45 per
hour paid to benefit funds and a training trust. During
the same time period, Transport Drivers (S&G) under the
Ready-Mix Agreement were paid between $23 and
$24.80 per hour, with $4.16 paid to benefit funds.
C. The Respondent Unilaterally Moves the Drivers Who
Deliver to Construction Sites out of the Construction
Bargaining Unit and into the Ready-Mix
Bargaining Unit
On July 9, 2010,6 the Respondent’s vice president and
regional counsel, Sean Stewart, announced to Wayne
Dey, the Union’s representative with responsibility for
administering the Construction Agreement, that the Re-
spondent was “going to move” the drivers who hauled
aggregate from Sloan Quarry to construction sites from
coverage under the Construction Agreement to coverage
under the Ready-Mix Agreement. Stewart indicated that
he wanted only “to discuss whether we could keep our
own drivers”; that is, he asked Dey whether the Re-
spondent could continue to employ the same individuals
currently covered by the Construction Agreement to haul
the same material in the same trucks but under the terms
of the Ready-Mix Agreement. Dey told Stewart that he
4 The unit was described in the certification as “All full-time and
regular part-time drivers and mechanics employed by the Employer out
of its concrete batch plant in or about Clark County, Nevada; excluding
all other employees, office clerical employees, guards and supervisors
as defined in the Act.”
5 Transport Drivers (S&G) also haul aggregate from the Sloan Quar-
ry to batch plants operated by SNRM, another subsidiary of the Re-
spondent.
6 All dates are in 2010, unless otherwise specified.
did not think he or the union representative representing
the Ready-Mix unit employees would agree to the
movement of the drivers in that manner. In their next
conversation, on August 13, Dey told Stewart that the
Union would oppose the Respondent’s plan. On August
20, the Union reiterated its position in writing. On Sep-
tember 24, the Respondent requested that the Union dis-
patch 64 drivers to perform work, under the terms of the
Ready-Mix Agreement, beginning 4 days later. The par-
ticular work had previously been performed by offsite
material haul drivers working under the terms of the
Construction Agreement. The Union did not fill the dis-
patch request.
On September 27, Stewart sent a letter to the Union
stating that the Ready-Mix Agreement gave the Re-
spondent the right to deliver materials under the terms of
that agreement. On September 28, the parties met in an
attempt to resolve the dispute, but no agreement was
reached.
At the end of the September 28 session, both sides
agreed to consider resolving their differences by settling
on a schedule of transition rates, under which the wage
rate for the drivers in dispute would be lowered in steps
from the Construction Agreement rate to the Ready-Mix
Agreement rate. Later that day, the Respondent sent a
letter to the Union stating that, because the Union had
not dispatched drivers under the Ready-Mix Agreement
as requested, the Respondent was exercising its option to
procure workers from other sources.
In the meantime, Stewart drafted a transition rates pro-
posal, but in a telephone conversation on September 30,
Dey informed Stewart that the Union would not agree to
resolve the dispute in that manner. Stewart nevertheless
asked Dey to pick up a copy of the Respondent’s pro-
posed transition rates and to hand out copies to the driv-
ers at a union meeting that night. Dey said that he would
do so. Later that day, Dey called Stewart and told him
that the Respondent’s transition proposal was unaccepta-
ble. He warned Stewart that if the Respondent imple-
mented it, the Respondent “would have a fight on [its]
hands.”
On October 1, the Respondent met with the affected
drivers at Sloan Quarry; the Respondent invited Dey and
other union representatives to attend, but they were not
permitted to speak. Stewart told the drivers about mov-
ing them to coverage under the Ready-Mix Agreement
but said that the Respondent would apply its transition
proposal to any drivers who agreed to the move.
By letter dated October 5, the Respondent informed
the Union that it would commence performing the affect-
ed drivers’ work under the Ready-Mix Agreement and
offered to pay the proposed transition rates to current
AGGREGATE INDUSTRIES
1421
employees. The Respondent presented a notice with the
same offer to each of the drivers. The document con-
tained a section for the drivers to fill out and return if
they wanted to continue to be employed as of October
11, under the Ready-Mix Agreement. About 60 drivers
agreed.
From October 12 to 15, the Union picketed. On Octo-
ber 15, the Respondent and the Union agreed that, pend-
ing resolution of the instant unfair labor practice charges,
the affected drivers would work under the Ready-Mix
Agreement, with the phased-in wages offered by the Re-
spondent on October 1. The drivers who accepted the
proposal are doing the same work, using the same trucks,
and hauling the same material to and from the same loca-
tions as they did when they worked under the Construc-
tion Agreement. They are, however, no longer covered
by that agreement, and they are getting paid less.
II. ANALYSIS
A. Bargaining Unit Scope is a Permissive Subject
of Bargaining
The Board and the courts have drawn a distinction be-
tween mandatory and permissive subjects of bargaining.
See NLRB v. Borg-Warner Corp., 356 U.S. 342, 349–350
(1958). Generally speaking, mandatory subjects are
those encompassed within the definition of collective
bargaining set forth in Section 8(d) of the Act: “wages,
hours, and other terms and conditions of employment.”
Id. at 349 (quoting Sec. 8(d)). All other lawful bargain-
ing subjects are permissive. Id. at 349. A party may in-
sist to impasse on, and then implement, a bargaining
proposal concerning a mandatory subject. Raymond F.
Kravis Center for the Performing Arts, 351 NLRB 143,
144 (2007), enfd. 550 F.3d 1183 (D.C. Cir. 2008). But if
the subject is a permissive one, the other party may re-
fuse to discuss it; a proposal cannot thereafter be imple-
mented absent an agreement to do so. Hill-Rom Co., Inc.
v. NLRB, 957 F.2d 454, 457 (7th Cir. 1992); Solutia, Inc.,
357 NLRB No. 15, slip op. at 5 (2011), enfd. 699 F.3d 50
(1st Cir. 2012).
A proposal to alter the scope (composition) of an exist-
ing bargaining unit is a permissive subject of bargaining.
See, e.g., Hill-Rom, 957 F.2d at 457. Thus, an employer
(or union) cannot unilaterally change a bargaining unit,
even after bargaining to impasse. Wackenhut Corp., 345
NLRB 850, 853 fn. 8 (2005).7 But a transfer of unit
7 The principal rationale for finding the scope of a bargaining unit to
be a permissive subject is that, if the scope of the bargaining unit were
a mandatory subject, “an employer could use its bargaining power to
restrict (or extend) the scope of union representation in derogation of
employees’ guaranteed right to representatives of their own choosing.”
Idaho Statesman v. NLRB, 836 F.2d 1396, 1400–1401 (D.C. Cir. 1988).
work is a mandatory subject of bargaining. Id. It is the
task of the Board to distinguish between the two.
It can be difficult to draw this line, particularly when
the unit is defined, not in terms of the job classifications
it covers, but in terms of the nature of the work per-
formed by the unit. See, e.g., Hill-Rom, 957 F.2d at 458.
This, however, is not such a case, as both the Construc-
tion Agreement and the Ready-Mix Agreement define
their respective bargaining units in terms of the constitu-
ent job classifications. In Wackenhut Corp., 345 NLRB
at 352, the Board held that once a specific job has been
included within a bargaining unit, the employer cannot
remove it without the consent of the union or action by
the Board. See Hampton House, 317 NLRB 1005, 1005
(1995) (same).
An employer may not, under the guise of transferring
unit work, alter the scope of the bargaining unit. Facet
Enterprises, Inc. v. NLRB, 907 F.2d 963, 975–976 (10th
Cir. 1990); Newport News Shipbuilding v. NLRB, 602
F.2d 73, 77–78 (4th Cir. 1979). The Board has rejected
attempts by employers to characterize a change as a
transfer of work when the same employees continue to
do the work. See, e.g., Beverly Enterprises, Inc., 341
NLRB 296, 296 (2004) (“The same employees continue
to do the work. The Respondent attempted to change the
scope of the bargaining unit by taking the position that
these represented employees and their work were now
outside the bargaining unit.”); Bay Shipbuilding Corp.,
263 NLRB 1133, 1140–1141 (1982), enfd. 721 F.2d 187
(7th Cir. 1983).
B. The Respondent Altered the Scope of the
Bargaining Units
In the present case, the judge found that the Respond-
ent’s plan to move the work was simply a transfer of unit
work, a mandatory subject of bargaining for which the
Union’s consent was not required. “[T]he correct charac-
terization of Respondent’s actions,” the judge observed,
“is that of a transfer of material hauling duties from driv-
ers covered under the Construction Agreement to drivers
covered under the Ready-Mix Agreement.” Relying on
the fact that the Respondent did not eliminate the offsite
material haul classification from the bargaining unit in
the Construction Agreement or create a nonbargaining
unit position and assign the work of Construction Bar-
gaining unit employees to employees in the new job clas-
sification, the judge declined to adopt the Acting General
Counsel’s view that the transfer was properly character-
ized as a change in the scope of the bargaining units. In
so holding, however, the judge acknowledged that the
Acting General Counsel’s position was “equally compel-
ling.”
1422
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
The Acting General Counsel and the Union argue that
when the Respondent moved construction site hauling
work and the drivers who perform it from coverage un-
der the Construction Agreement to coverage under the
Ready-Mix Agreement, it altered the scope of those bar-
gaining units. They contend that this change was not
simply a transfer of unit work because, as a result of the
Respondent’s action, about 60 drivers no longer bargain
collectively with other Construction bargaining unit em-
ployees and no longer receive Construction Agreement
wages. The Union acknowledges that the Respondent
would have been entitled to pursue a reduction in wages
and benefits in bargaining for a new Construction
Agreement, but asserts that “[w]hat the Respondent did
instead—transfer the off-site material haul driver posi-
tions to the Ready-Mix [b]argaining [u]nit—was an eva-
sion of the duty to bargain.”
We find merit in the Acting General Counsel’s and the
Union’s arguments. We conclude, contrary to the judge,
that the Respondent’s action in moving the drivers at
issue constituted a change in the scope of the two bar-
gaining units. Accordingly, we further conclude, in
agreement with the Acting General Counsel and the Un-
ion, that the move was a permissive subject of bargaining
and, therefore, that the Respondent was not privileged to
implement it in the absence of the Union’s consent.
Until October 2010, offsite material haul work was
performed by drivers in the Construction bargaining unit.
In October, the Respondent moved those jobs to the
Ready-Mix bargaining unit, and uses the same drivers to
perform the work. Those drivers perform the same work
in the same locations, with the same trucks, using the
same procedures, but they are no longer members of the
same bargaining unit and no longer receive Construction
Agreement wages. By unilaterally making those chang-
es, the Respondent changed the scope of both units, di-
minishing the Construction Bargaining unit and enlarg-
ing the Ready-Mix bargaining unit.
In finding that this matter should be characterized as a
transfer of unit work and not a change in unit scope, the
judge relied on the fact that the Respondent did not en-
tirely eliminate the disputed driver classification from the
Construction bargaining unit. Although the judge is cor-
rect in that limited factual respect, his analysis fails to
take into account the Respondent’s movement of about
60 drivers from coverage under the Construction Agree-
ment to coverage under the Ready-Mix Agreement. In
doing so, the Respondent severed their connection to the
Construction bargaining unit, and substantially reduced
the size (and bargaining power) of that unit. This, in our
view, was a change in unit scope, a permissive subject of
bargaining. See generally Walt Disney World Co., 359
NLRB No. 73, slip op. at 4 (2013). Because the Re-
spondent took this action without the Union’s consent,
we conclude that it violated Section 8(a)(5) and (1) of the
Act.
C. Assuming that the Move was a Transfer of Unit
Work, the Respondent’s Implementation
of it Violated the Act
Even if the Respondent’s actions are properly charac-
terized as a transfer of unit work, we would find that the
Respondent violated the Act, because we find, contrary
to the judge, that the parties did not bargain to impasse
over the change, nor did the Union waive its right to bar-
gain over the change.8 Instead, we find that the change at
issue was presented to the Union as a fait accompli.
The Board has repeatedly held that where the manner
of the respondent’s presentation of a change in terms and
conditions of employment to the union precludes a mean-
ingful opportunity for the union to bargain, the change is
a fait accompli and a failure by the union to request bar-
gaining will not constitute a waiver. See, e.g., Pontiac
Osteopathic Hospital, 336 NLRB 1021, 1023 (2001). As
the Board stated in Dresser-Rand Co., 358 NLRB No.
97, slip op. at 36 (2012):
[I]f the notice is too short a time before implementa-
tion, or because the employer has no intention of
changing its mind, then the notice is nothing more than
informing the union of a fait accompli.” [Citations
omitted.] [Emphasis added.] Ciba Geigy Pharmaceu-
tic[al]s Division, 264 NLRB 1013 (1982). Further, “it
is . . . well established that a union cannot be held to
have waived bargaining over a change that has been
presented as a fait accompli. . . .” Intersystems Design
& Technology Corp., 278 NLRB 759 (1986), quoting
Gulf States Mfg., Inc. v. NLRB, 704 F.2d 1390 (5th Cir.
1983).
The Board has also stated that “no impasse is possible
where an employer presents the union with a ‘fait ac-
compli’ as to a matter over which bargaining to impasse
is required.” Castle Hill Health Care Center, 355 NLRB
1156, 1189 (2010); see also S & I Transportation, Inc.,
311 NLRB 1388, 1390 fn. 4 (1993).
8 Because finding a violation pursuant to this alternative theory does
not materially affect the remedy, we find it appropriate to find both
violations. See, e.g., Mt. Sinai Hospital, 331 NLRB 895, 895 fn. 2
(2000) (Board agreed with judge that employer’s unilateral action was
an unlawful change in bargaining unit scope, but also found that even if
the change was a transfer of unit work and not a change in unit scope,
the change still violated Sec. 8(a)(5) and (1) in the absence of agree-
ment, impasse, or waiver), enfd. 8 Fed. Appx. 111 (2d Cir. 2001).
AGGREGATE INDUSTRIES
1423
Relying on the length of time between the Respond-
ent’s July 9 announcement of its plans and the October
11 implementation, the judge found that there was time
for bargaining to have occurred and therefore that the
announcement did not signal a fait accompli. We find,
however, that the record supports the conclusion that, at
the time of the announcement, the Respondent did pre-
sent the Union with a fait accompli because it had a fixed
intent to transfer the disputed drivers and their work and
thus presented the Union with no opportunity for mean-
ingful bargaining.
At the July 9 meeting, Respondent Representative
Stewart told Union Representative Dey that they were
“going to” move the material haulers, not that they were
“considering” doing so.9 Stewart’s August 13 letter to
the Union10 conveyed the same unconditional message—
that the Respondent was not merely proposing a change
subject to bargaining, but was informing the Union that
the change would occur. See Pontiac Osteopathic Hos-
pital, supra, 336 NLRB at 1023–1024 (finding notice to
employees that employer intended to implement changes
shows that employer considered changes to be a final
decision not subject to bargaining).
At the time of the events at issue, as well as throughout
this litigation, the Respondent has asserted that the par-
ties had already explicitly bargained and agreed, in the
negotiations leading to the 2008 Ready-Mix Agreement,
to the disputed change. The judge rejected this assertion
as a matter of fact. The Respondent’s repeated assertion
of that false statement in 2010—that it had no duty to
bargain over the change because the parties had already
discussed it and agreed to it—conveyed an unequivocal
message that there would be no further bargaining. The
Board has found a fait accompli in similar circumstances.
See Westinghouse Electric Corp., 313 NLRB 452, 453
9 Stewart testified:
Q. Okay. And during this July 9th meeting, you told Wayne
Dey that the Company was considering moving the material haul-
ers from the Construction Agreement over to the Ready Mix
Agreement?
A. I informed Wayne that we were going to move them and
the main purpose of our meeting was to discuss whether we could
keep our own drivers. When I say our own, we wanted to keep the
drivers we had.
Q. But that wasn’t my question. You told him at that meeting
—did you tell him you were moving them or you were consider-
ing moving them?
A. We were going to move them.
Tr. 83–84.
10 In that letter, Respondent informed the Union that “[m]aterial de-
liveries for the company will be performed by Teamster employees
under the rules and regulations of the [Ready-Mix] bargaining agree-
ment.”
(1993), enfd. mem. 46 F.3d 1126 (4th Cir. 1995), cert.
denied 514 U.S. 1037 (1995).
We find in these circumstances, where the Respondent
clearly had no intention of altering its plans, that the Un-
ion was presented with a fait accompli. See Ciba Geigy
Pharmaceuticals, 264 NLRB 1013, 1017 (1982). In oth-
er words, it would have been futile for the Union to have
requested bargaining over the matter, and we therefore
conclude that the Union’s failure to do so is excused.
See Solutia, Inc., supra, 357 NLRB 58, slip op. at 64
(“no specific demand was necessary given that Respond-
ent had already decided, even before notifying” the union
of its intended changes, that the decision was not nego-
tiable). Accordingly, even assuming that this change was
a mandatory subject of bargaining, we find that the Un-
ion did not waive its right to bargain over it by failing to
request bargaining.
In addition, in light of our fait accompli finding, we re-
ject the judge’s conclusion that the parties had bargained
to impasse over the matter. See Dorsey Trailers, Inc.,
327 NLRB 835, 858 (1999) (“no impasse is possible
where an employer presents the union with a ‘fait ac-
compli’ as to a matter over which bargaining to impasse
is required”), enfd. in part and denied in part 233 F.3d
831 (4th Cir. 2000). Accordingly, we find no merit to
the Respondent’s contention that it was privileged to act
unilaterally because the parties had reached lawful im-
passe on the matter.
Having rejected the Respondent’s waiver and impasse
defenses, we find that, even if the transfer is properly
characterized as a mandatory subject of bargaining, the
Respondent’s unilateral movement of offsite material
hauling drivers and their work from coverage under the
Construction Agreement to coverage under the Ready-
Mix Agreement violated Section 8(a)(5) and (1).11
D. The Respondent Unilaterally Changed the Terms and
Conditions of Employment of the Material Haul Drivers
The judge found that the Respondent did not unlawful-
ly change the terms and conditions of employment of the
material haul drivers after they were transferred to cover-
age under the Ready-Mix Agreement. Consistent with
11 We also find no merit in the Respondent’s strained argument that,
as a result of an August 2010 amalgamation of its various subsidiaries,
all of the Respondent’s Teamsters-represented employees constitute
one bargaining unit under the Ready-Mix Agreement. The evidence is
clear that the Respondent continued to exist as the employing entity,
and that it continued to recognize and bargain with the Union as the
representative of employees covered by the Construction Agreement, at
all relevant times. Accordingly, there can be no claim that the corpo-
rate amalgamation somehow privileged the Respondent to alter the
existing bargaining units in the absence of the Union’s agreement or
action of the Board.
1424
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
his other findings, he found that the Union had timely
notice of the proposed transition rates and failed to re-
quest bargaining over them. We reverse.
As discussed above, the Respondent violated the Act
by unilaterally moving the drivers, a permissive subject
of bargaining, in the absence of the Union’s agreement.
The Union was under no obligation to bargain over the
terms by which that movement might be facilitated. As
the Union has persuasively argued, the appropriate forum
for renegotiation of the disputed drivers’ wages was in
bargaining for successor agreements to the Construction
Agreement. The Respondent’s decision to act unilateral-
ly violated Section 8(a)(5) and (1) of the Act.
E. The Respondent Engaged in Unlawful Direct Dealing
and, Thereafter, Denied Employment
Opportunities to Drivers
The consolidated complaint alleges that the Respond-
ent unlawfully bypassed the Union and dealt directly
with Construction bargaining unit drivers when it met
with them for the purpose of changing their terms and
conditions of employment and when it required them to
agree to the terms and conditions of the Ready-Mix
Agreement as a condition of keeping their jobs. The
consolidated complaint further alleges that the Respond-
ent unlawfully denied employment to those Construction
bargaining unit drivers who refused to agree to work
under the terms and conditions of the Ready-Mix
Agreement.
We find, in agreement with the Acting General Coun-
sel, that the Respondent’s conduct undermined the Un-
ion’s position as collective-bargaining representative and
therefore constituted unlawful direct dealing. See Allied-
Signal, Inc., 307 NLRB 752, 753–754 (1992). The Re-
spondent presented its wage transition proposal directly
to the assembled drivers on October 1, the day after the
Respondent presented it to the Union. The Respondent
also placed a copy of the proposal in each employee’s
company mailbox, along with a form to be completed
and returned to the Respondent if the employee wanted
to continue working. We find that this conduct, done
without the consent of the Union, eroded the Union’s
position as exclusive bargaining representative, and con-
stituted unlawful direct dealing. See Smith’s Complete
Market, 237 NLRB 1424, 1429, 1435 (1978) (employer’s
discussion in an employee meeting of a pension proposal
it had presented to the union earlier that day as a “con-
cept” constituted direct dealing); Dayton Newspapers,
339 NLRB 650, 653 (2003) (employer’s attempt to ob-
tain a waiver directly from drivers in exchange for re-
turning to work constituted direct dealing), enfd. in rele-
vant part 402 F.3d 651 (6th Cir. 2005).
The fact that union representatives attended the Octo-
ber 1 meeting does not preclude a finding of direct deal-
ing. The union representatives were not there to bargain
on behalf of the employees and, indeed, were not even
permitted to speak. The union representatives were rele-
gated to the status of passive observers, further under-
mining the Union’s position as the unit employees’ col-
lective-bargaining representative. Nor does the fact that
the Union told the Respondent that it was not interested
in bargaining about transition rates preclude a direct
dealing finding. By doing so, the Union did not agree
that the Respondent could deal with employees as if the
work force had no bargaining representative. See Allied-
Signal, supra.
In short, the Respondent’s meeting with the drivers
constituted unlawful direct dealing. It follows from all of
the foregoing findings that the Respondent further violat-
ed the Act by denying employment to those employees
who refused to agree to the unlawfully imposed terms.
AMENDED CONCLUSIONS OF LAW
Insert the following as Conclusions of Law 3, 4, 5, and
6 and renumber the subsequent paragraphs.
“3. The Respondent violated Section 8(a)(5) and (1) by
changing the scope of the Construction bargaining unit
by moving offsite material haul drivers from the Con-
struction bargaining unit to the Ready-Mix bargaining
unit without the Union’s consent.
“4. The Respondent violated Section 8(a)(5) and (1)
by unilaterally moving offsite material haul work from
coverage under the Construction Agreement to coverage
under the Ready-Mix Agreement without giving the Un-
ion sufficient notice and an opportunity to bargain about
the change.
“5. The Respondent violated Section 8(a)(5) and (1)
by changing the terms and conditions of employment of
Construction bargaining unit employees by requiring
them to work under the terms of its Ready-Mix Agree-
ment.
“6. The Respondent violated Section 8(a)(5) and (1)
by bypassing the Union and dealing directly with its
Construction bargaining unit employees, and by denying
employment to Construction bargaining unit employees
who refused to agree to work under the terms and condi-
tions of its Ready-Mix Agreement.”
AMENDED REMEDY
In addition to the remedies recommended by the judge
with respect to the Respondent’s unlawful conduct con-
cerning the mechanical sweeper drivers, we shall order
the Respondent to cease and desist from the above-
described conduct with respect to the offsite material
haul work/drivers.
AGGREGATE INDUSTRIES
1425
We shall also order the Respondent to restore the sta-
tus quo ante with respect to both the Construction bar-
gaining unit and the Ready-Mix bargaining unit by re-
turning the employees performing offsite material haul
work back to the Construction Bargaining unit from the
Ready-Mix bargaining unit, rescinding all unilateral
changes in the employees’ terms and conditions of em-
ployment, and continuing in effect all the terms and con-
ditions of employment contained in the Construction
Agreement for those employees previously covered by
that agreement. In addition, the Respondent shall be
ordered to make whole any former Construction bargain-
ing unit employee performing offsite material haul work
under the Ready-Mix Agreement for any lost wages and
other benefits suffered as a result of the Respondent’s
unlawful conduct, with interest as prescribed in New Ho-
rizons for the Retarded, 283 NLRB 1173 (1987), com-
pounded daily as prescribed in Kentucky River Medical
Center, 356 NLRB 6 (2010).12
We shall also order the Respondent to reinstate and
make whole any former Construction bargaining unit
employee who lost employment for refusing to work
under the terms and conditions of the Ready-Mix
Agreement. Backpay for employees who lost employ-
ment as a result of the Respondent’s unlawful actions
shall be computed in accordance with F. W. Woolworth
Co., 90 NLRB 289 (1950), with interest as prescribed in
New Horizons for the Retarded, supra, compounded dai-
ly as prescribed in Kentucky River Medical Center, su-
pra. In accordance with our recent decision in Latino
Express, Inc., 359 NLRB 518 (2012), we shall order the
Respondent to reimburse former Construction bargaining
unit employees an amount equal to the difference in tax-
es owed upon receipt of a lump-sum backpay payment
and taxes that would have been owed had there been no
12 Backpay shall be computed in the manner set forth in Ogle Protec-
tion Service, 183 NLRB 682, 683 (1970). If the Respondent’s unilat-
eral changes involve the failure to make contractually required contri-
butions to the Union’s fringe benefit funds, we shall order the Re-
spondent to make all required benefit fund contributions, including any
additional amounts applicable to such funds as set forth in Merryweath-
er Optical Co., 240 NLRB 1213, 1216 fn. 7 (1979). In addition, we
shall require the Respondent to reimburse unit employees for any ex-
penses resulting from the Respondent’s failure to make the required
contributions to the funds, as set forth in Kraft Plumbing & Heating,
252 NLRB 891 fn. 2 (1980), enfd. mem. 661 F.2d 940 (9th Cir. 1981).
Such amounts are to be computed in the manner set forth in Ogle Pro-
tection Service, supra, with interest as prescribed in New Horizons for
the Retarded, supra, compounded daily as prescribed in Kentucky River
Medical Center, supra. To the extent that an employee has made per-
sonal contributions to a fund that are accepted by the fund in lieu of the
employer’s delinquent contributions during the period of the delinquen-
cy, the Respondent will reimburse the employee, but the amount of
such reimbursement will constitute a setoff to the amount that the Re-
spondent otherwise owes the fund.
unlawful action against them. Further, we shall order the
Respondent to submit the appropriate documentation to
the Social Security Administration so that when backpay
is paid to the employees, it will be allocated to the ap-
propriate periods.13
ORDER
The Respondent, Aggregate Industries, Las Vegas,
Nevada, its officers, agents, successors, and assigns, shall
1. Cease and desist from
(a) Changing the scope of the Construction bargaining
unit by moving offsite material haul drivers from the
Construction bargaining unit to the Ready-Mix bargain-
ing unit without the Union’s consent.
(b) Unilaterally moving offsite material haul work
from coverage under the Construction Agreement to
coverage under the Ready-Mix Agreement without giv-
ing the Union sufficient notice and an opportunity to
bargain about the change.
(c) Changing the terms and conditions of employment
of Construction bargaining unit employees by requiring
them to work under the terms of its Ready-Mix Agree-
ment.
(d) Bypassing the Union and dealing directly with its
Construction bargaining unit employees, and denying
employment opportunities to Construction bargaining
unit employees who refuse to agree to work under the
terms and conditions of its Ready-Mix Agreement.
(e) Bypassing the Union and dealing directly with its
mechanical sweeper truckdrivers in the Construction
bargaining unit with regard to their terms and conditions
of employment.
13 No exceptions were filed to the judge’s failure to include the
Board’s standard electronic notice-posting language in the Order pursu-
ant to J. Picini Flooring, 356 NLRB No. 9 (2010). In fn. 60 of his
decision, the judge found it inappropriate to require the Respondent to
disseminate the notice electronically because he found that each em-
ployee has a mail slot for employment-related documents and that there
was no record evidence “to suggest that Respondent regularly com-
municates with its employees via e-mail or other electronic means.”
The absence of evidence at the merits stage of an unfair labor practice
proceeding that an employer regularly communicates with its employ-
ees via e-mail or other electronic means would normally be insufficient
to warrant the omission of the Board’s standard J. Picini electronic
notice-posting language from a Board order. J. Picini specifically
provided that this type of evidence may appropriately be raised at the
compliance stage, as well as at the merits stage. Id., slip op. at 4. We
note, however, that when the judge asked the Respondent’s vice presi-
dent and regional counsel, Sean Stewart, whether the Respondent
communicated with the drivers by email, Stewart testified, “No. Every-
thing with the drivers is printed out and given to them or in person.”
Tr. 164–165. In light of this testimony, and in the absence of excep-
tions on this matter, we adopt the judge’s decision not to order electron-
ic dissemination of the notice in this case. We shall, however, order the
Respondent to place a copy of the notice in each driver’s mail slot, in
lieu of electronic posting.
1426
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
(f) Unilaterally, without notice to the Union or afford-
ing the Union an opportunity to bargain, assigning me-
chanical sweeper truckdriving work to drivers who are
represented by the Laborers Union, when such work had
previously been performed by drivers who were included
in the Construction bargaining unit.
(g) Unilaterally, without notice to the Union or afford-
ing the Union an opportunity to bargain, changing the
terms and conditions of its mechanical sweeper truck-
drivers by treating them as employees in the bargaining
unit covered by the Laborers’ collective-bargaining
agreement.
(h) In any like or related manner interfering with, re-
straining, or coercing employees in the exercise of the
rights guaranteed them by Section 7 of the Act.
2. Take the following affirmative action necessary to
effectuate the policies of the Act.
(a) Restore the status quo ante with respect to both the
Construction Bargaining unit and the Ready-Mix bar-
gaining unit, by returning the employees performing
offsite material haul work back to the Construction bar-
gaining unit from the Ready-Mix unit, rescinding all uni-
lateral changes in the employees’ terms and conditions of
employment, and continuing in effect all the terms and
conditions of the Construction Agreement for those em-
ployees.
(b) Make former Construction bargaining unit employ-
ees performing offsite material haul work under the
Ready-Mix Agreement whole for any loss of wages and
other benefits suffered as a result of its unlawful actions,
in the manner set forth in the amended remedy section of
this decision.
(c) Reimburse former Construction bargaining unit
employees for any expenses resulting from the Respond-
ent’s failure to make any required contributions to bene-
fit funds, in the manner set forth in the amended remedy
section of this decision.
(d) Within 14 days from the date of this Order, offer
any former Construction bargaining unit employee who
lost employment for refusing to work under the terms
and conditions of the Ready-Mix Agreement full rein-
statement to their former jobs or, if those jobs no longer
exist, to substantially equivalent positions, without prej-
udice to their seniority or any other rights or privileges
previously enjoyed.
(e) Make any former Construction bargaining unit em-
ployee who lost employment for refusing to work under
the terms and conditions of the Ready-Mix Agreement
whole for any loss of earnings and other benefits suffered
as a result of the unlawful action against them, in the
manner set forth in the amended remedy section of this
decision.
(f) Reimburse former Construction bargaining unit
employees an amount equal to the difference in taxes
owed upon receipt of a lump-sum backpay payment and
taxes that would have been owed had there been no un-
lawful action against them.
(g) Submit the appropriate documentation to the Social
Security Administration so that when backpay is paid to
former Construction bargaining unit employees, it will be
allocated to the appropriate periods.
(h) Within 14 days from the date of this Order, remove
from its files any reference to the loss of employment
opportunities for any former Construction bargaining
unit employee who lost employment for refusing to work
under the terms and conditions of the Ready-Mix
Agreement and, within 3 days, thereafter, notify them in
writing that this has been done and that the unlawful ac-
tion will not be used against them in any way.
(i) Restore the status quo ante by returning and assign-
ing the work of driving its mechanical sweeper trucks to
employees who are represented by the Union and em-
ployed in the Construction bargaining unit.
(j) Make sweeper truckdrivers Andrew Barnum and
Mike Crane whole for any loss of wages and other bene-
fits suffered as a result of its unilateral change, in the
manner set forth in the remedy section of the judge’s
decision.
(k) Preserve and, within 14 days of a request, or such
additional time as the Regional Director may allow for
good cause shown, provide at a reasonable place desig-
nated by the Board or its agents, all payroll records, so-
cial security payment records, timecards, personnel rec-
ords and reports, and all other records, including an elec-
tronic copy of such records if stored in electronic form,
necessary to analyze the amount of backpay due under
the terms of this Order.
(l) Within 14 days after service by the Region, post at
its facility in Las Vegas, Nevada, and its truck yard in
Sloan, Nevada, and distribute in the employees’ mail
slots, copies of the attached notice marked “Appendix.”14
Copies of the notice, on forms provided by the Regional
Director for Region 28, after being signed by the Re-
spondent’s authorized representative, shall be posted by
the Respondent and maintained for 60 consecutive days
in conspicuous places including all places where notices
to employees are customarily posted. Reasonable steps
shall be taken by the Respondent to ensure that the notic-
14 If this Order is enforced by a judgment of a United States court of
appeals, the words in the notice reading “Posted by Order of the Na-
tional Labor Relations Board” shall read “Posted Pursuant to a Judg-
ment of the United States Court of Appeals Enforcing an Order of the
National Labor Relations Board.”
AGGREGATE INDUSTRIES
1427
es are not altered, defaced, or covered by any other mate-
rial. If the Respondent has gone out of business or closed
the facility involved in these proceedings, the Respond-
ent shall duplicate and mail, at its own expense, a copy
of the notice to all current employees and former em-
ployees employed by the Respondent at any time since
October 1, 2010.
(m) Within 21 days after service by the Region, file
with the Regional Director for Region 28 a sworn certifi-
cation of a responsible official on a form provided by the
Region attesting to the steps that the Respondent has
taken to comply.
APPENDIX
NOTICE TO EMPLOYEES
POSTED BY ORDER OF THE
NATIONAL LABOR RELATIONS BOARD
An Agency of the United States Government
The National Labor Relations Board has found that we
violated Federal labor law and has ordered us to post and
obey this notice.
FEDERAL LAW GIVES YOU THE RIGHT TO
Form, join, or assist a union
Choose representatives to bargain with us on
your behalf
Act together with other employees for your bene-
fit and protection
Choose not to engage in any of these protected
activities.
WE WILL NOT change the scope of the Construction
bargaining unit by moving offsite material haul drivers
from the Construction bargaining unit to the Ready-Mix
Bargaining unit without the Union’s consent, or unilater-
ally move offsite material haul work from coverage un-
der the Construction Agreement to coverage under the
Ready-Mix Agreement without giving the Union suffi-
cient notice and an opportunity to bargain about the
change.
WE WILL NOT change the terms and conditions of em-
ployment of Construction bargaining unit employees by
requiring them to work under the terms of our Ready-
Mix Agreement.
WE WILL NOT bypass the Union and deal directly with
our Construction bargaining unit employees, and WE
WILL NOT deny employment opportunities to Construc-
tion bargaining unit employees who refuse to agree to
work under the terms and conditions of our Ready-Mix
Agreement.
WE WILL NOT bypass the Union and deal directly with
our mechanical sweeper truckdrivers in the Construction
bargaining unit with regard to their terms and conditions
of employment.
WE WILL NOT unilaterally, without notice to the Union
or affording the Union an opportunity to bargain, assign
mechanical sweeper truckdriving work to drivers who are
represented by Laborers’ International Union of North
America, Local 872 (Laborers), when such work had
previously been performed by drivers who were included
in the Construction bargaining unit.
WE WILL NOT unilaterally, without notice to the Union
or affording the Union an opportunity to bargain, change
the terms and conditions of our mechanical sweeper
truckdrivers by treating them as employees in the bar-
gaining unit covered by the Laborers’ collective-
bargaining agreement.
WE WILL NOT in any like or related manner interfere
with, restrain, or coerce our employees in the exercise of
the rights listed above.
WE WILL restore the status quo ante with respect to
both the Construction bargaining unit and the Ready-Mix
bargaining unit, by returning the employees performing
offsite material haul work back to the Construction bar-
gaining unit from the Ready-Mix unit, rescinding all uni-
lateral changes in the employees’ terms and conditions of
employment, and continuing in effect all the terms and
conditions of the Construction Agreement for those em-
ployees.
WE WILL make former Construction bargaining unit
employees performing offsite material haul work under
the Ready-Mix Agreement whole for any loss of wages
and other benefits suffered as a result of its unlawful ac-
tions, plus interest compounded daily.
WE WILL reimburse former Construction bargaining
unit employees for any expenses resulting from the Re-
spondent’s failure to make any required contributions to
benefit funds, plus interest compounded daily.
WE WILL, within 14 days from the date of the Board’s
Order, offer any former Construction bargaining unit
employees who lost employment for refusing to work
under the terms and conditions of the Ready-Mix
Agreement full reinstatement to their former jobs or, if
those jobs no longer exist, to substantially equivalent
positions, without prejudice to their seniority or any oth-
er rights or privileges previously enjoyed.
WE WILL make any former Construction bargaining
unit employees who lost employment for refusing to
work under the terms and conditions of the Ready-Mix
Agreement whole for any loss of earnings and other ben-
efits suffered as a result of the unlawful action against
them, less any net interim earnings, plus interest com-
pounded daily.
1428
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
WE WILL reimburse former Construction bargaining
unit employees an amount equal to the difference in tax-
es owed upon receipt of a lump-sum backpay payment
and taxes that would have been owed had there been no
unlawful action against them.
WE WILL submit the appropriate documentation to the
Social Security Administration so that when backpay is
paid to former Construction bargaining unit employees, it
will be allocated to the appropriate periods.
WE WILL, within 14 days from the date of the Board’s
Order, remove from our files any reference to the loss of
employment opportunities for any former Construction
bargaining unit employees who lost employment for re-
fusing to work under the terms and conditions of the
Ready-Mix Agreement, and WE WILL, within 3 days
thereafter, notify them in writing that this has been done
and that the unlawful action will not be used against
them in any way.
WE WILL restore the status quo ante by returning and
assigning the work of driving our mechanical sweeper
trucks to employees who are represented by the Union
and employed in the Construction bargaining unit.
WE WILL make sweeper truckdrivers Andrew Barnum
and Mike Crane whole for any loss of wages and other
benefits suffered as a result of our unilateral change, plus
interest compounded daily.
AGGREGATE INDUSTRIES
John Giannopoulos, Esq. and Pablo A. Godoy, Esq., for the
General Counsel.
James T. Winkler, Esq. (Littler, Mendelson, P.C.), of Las Ve-
gas, Nevada, for the Respondent.
Richard G. McCracken, Esq. and Patrick Domholdt, Esq.
(McCracken, Stemerman & Holsberry), of Las Vegas, Ne-
vada, for the Charging Party.
DECISION
STATEMENT OF THE CASE
BURTON LITVACK, Administrative Law Judge. The unfair
labor practice charge in Case 28–CA–023220 was filed by
Teamsters, Chauffeurs, Warehousemen and Helpers, Local 631,
affiliated with International Brotherhood of Teamsters (the
Union), on October 13, 2010. The original and first amended
unfair labor practice charges in Case 28–CA–023250 were filed
by the Union on November 9 and December 22, 2010, respec-
tively. After investigations, on December 29, 2010, the Acting
Regional Director for Region 28 of the National Labor Rela-
tions Board (the Board) issued a consolidated complaint, alleg-
ing that Aggregate Industries (the Respondent) engaged in, and
continues to engage in, acts and conduct violative of Section
8(a)(1) and (5) of the National Labor Relations Act (the Act).
Respondent timely filed an answer, denying the commission of
the alleged unfair labor practices and asserting certain affirma-
tive defenses. Based upon a notice of hearing, on February 15–
17, 2011, a trial on the merits of the alleged unfair labor prac-
tices was conducted before the above-named administrative law
judge in Las Vegas, Nevada. At the hearing, all parties were
afforded the opportunity to call witnesses on their respective
behalves, to cross-examine witnesses, to offer into the record
relevant documentary evidence, to argue legal positions orally,
and to file posthearing briefs. Each party filed a posthearing
brief, and each brief has been carefully considered. According-
ly, based on the entire record,1 including the posthearing briefs
and my observations of the credibility of the several witnesses,
I make the following
FINDINGS OF FACT
I. JURISDICTION
At all times material, Respondent, a State of Delaware cor-
poration, with offices and places of business in various States
of the United States, including offices and facilities located in
Las Vegas, Nevada, has engaged in the business of producing
construction materials. During the 12-month period ending
October 13, 2010, in conducting its business operations de-
scribed above, Respondent, through subsidiary corporations,
purchased and received at its Las Vegas, Nevada facilities
goods and materials valued in excess of $50,000, directly from
suppliers located outside the State of Nevada. Respondent
admits that, at all times material, it has been an employer en-
gaged in commerce within the meaning of Section 2(2), (6),
and (7) of the Act.
II. LABOR ORGANIZATION
Respondent admits that, at all times material, the Union has
been a labor organization within the meaning of Section 2(5) of
the Act.
III. THE ISSUES
The consolidated complaint alleges that Respondent changed
the scope of the work of its so-called construction bargaining
unit employees by moving delivery of materials work form the
construction bargaining unit employees to its ready-mix bar-
gaining unit employees; that Respondent changed the terms and
conditions of employment of construction bargaining unit em-
ployees by requiring them to work under the terms of its ready-
mix collective-bargaining agreement; that Respondent the
terms and conditions of employment of two sweeper driver
employees by moving the work of the sweeper drivers from the
terms and conditions of its construction collective-bargaining
agreement to the terms and conditions of its Laborers’ collec-
tive-bargaining agreement; that Respondent changed the scope
of the work of its construction bargaining unit employees by
removing mechanical sweeper driving work form the construc-
tion bargaining unit and assigning such work to the bargaining
unit covered by the Laborers’ collective-bargaining agreement;
and that Respondent violated Section 8(a)(1) and (5) of the Act
by engaging in the aforementioned acts and conduct without
prior notice to the Union and without affording the Union an
opportunity to bargain with it concerning the acts and conduct
1 I grant counsel for the Acting General Counsel’s motion to correct
the record.
AGGREGATE INDUSTRIES
1429
or the effects of the acts and conduct on the construction bar-
gaining unit employees. The consolidated complaint further
alleges that Respondent engaged in acts and conduct violative
of Section 8(a)(1) and (5) of the Act by bypassing the Union
and dealing directly with its construction bargaining unit em-
ployees by meeting with its semployees for the purpose of
changing their terms and conditions of employment and requir-
ing said employees to agree in writing to the terms and condi-
tions of employment of its ready-mix collective-bargaining
agreement as a condition of continuing to be employed by Re-
spondent; by denying employment opportunities to construction
bargaining unit employees who refused to agree to work under
the terms and conditions of its ready-mix collective-bargaining
agreement; and by dealing directly with sweeper drivers for the
purpose of changing the terms and conditions of their employ-
ment by Respondent.
In addition to generally denying the commission of any of
the above-alleged unfair labor practices, Respondent affirma-
tively alleges that the allegations of the consolidated complaint
are barred by Section 10(b) of the Act; that Respondent’s ac-
tions are privileged by the most favored nations clause of its
ready-mix collective-bargaining agreement; that Respondent’s
Las Vegas area subsidiary corporations have, at all times mate-
rial herein, constituted a single employer and that there exists
one bargaining unit covering two collective-bargaining agree-
ments with the Union; and that the actions of Respondent with
regard to its sweeper drivers involve a jurisdictional work dis-
pute which is not subject to unfair labor practices within the
meaning of Section 8(a)(1) and (5) of the Act.
IV. THE ALLEGED UNFAIR LABOR PRACTICES
The Material Haul Drivers
Respondent, a State of Delaware corporation, is a subsidiary
of the Holcim Group, a Switzerland-based company, which,
through subsidiary companies located throughout the world, is
engaged in business as a manufacturer and supplier of construc-
tion industry building supplies including ready-mix concrete
and rock, sand, and gravel aggregates. The record establishes
that, commencing in 2003, Respondent began operating in the
Las Vegas, Nevada area by purchasing existing companies,
who were engaged in business in different segments of the
building and construction industry. Thus, in November 2003,
Respondent purchased the business of Southern Nevada Pav-
ing, Inc. (SNP), a State of Nevada corporation, which, for sev-
eral years, had been engaged in the building and construction
industry as an excavation, paving, and grading contractor on
private road and large building projects such as shopping cen-
ters, hotels, and casinos. Subsequent to the acquisition, until
2010, while a corporate subsidiary of Respondent, SNP contin-
ued to operate as a legal entity under its same name, performing
the same work with the same work force. Then, in May 2004,
Respondent purchased the business of Frehner Construction
Company, Inc. (Frehner), a State of Nevada corporation, which,
since 1970, had been engaged as a general contractor on large
public works construction projects such as highways, bridges,
and dams. Thereafter, until 2010, while a corporate subsidiary
of Respondent, Frehner continued to operate as a legal entity
under its own name, performing the same work in the building
and construction industry. At the time of the purchase and
continuing thereafter, Frehner owned a 50-percent interest in a
quarry located in Sloan, Nevada; the other half interest in the
quarry (Sloan Quarry), was, and continues to be, owned by
Aggregate Industries––WCR, a State of Colorado corporation.
At the Sloan Quarry, the owners mine aggregate materials,
processing the rock through various crusher machines in order
to create different sizes of aggregates for sale. Also in May
2004, Respondent, which owned the corporate name Regal
Materials, purchased two Las Vegas area business entities,
Regency Ready-Mix, a ready-mix concrete manufacturer, and
Bradstone Pavers, which manufactured decorative pavers and
blocks for driveways, roads, and highways, combined both
under the corporate name, Regal Materials, and began engaging
in the ready-mix concrete business under the fictitious name,
Regal Ready-Mix. At the time of purchase, Regal Materials,
Inc. d/b/a Regal Ready-Mix (Regal), operated only one Las
Vegas area ready-mix concrete production facility, termed a
batch plant, which was located in Summerlin, and employed
approximately 18 full-time and regular part-time ready-mix
concrete delivery drivers and mechanics. In 2006, the Union
was victorious in a representation election amongst Regal’s
drivers and mechanics and was certified as their exclusive rep-
resentative for purposes of collective bargaining. In late 2007,
after a year of contract bargaining between the parties, Regal’s
bargaining unit employees filed a decertification petition, and
after a decertification election, the Board again certified the
Union as the exclusive bargaining representative of Regal’s
employees in the same bargaining unit.2 Subsequently, in early
February 2008, while retaining its delivery trucks, Regal closed
its Summerlin batch plant and laid off its ready-mix concrete
drivers and mechanics; however, in March or April, Respond-
ent reconsidered its earlier actions, decided to become a com-
petitor in the Las Vegas area ready-mix concrete business, reo-
pened its Summerlin batch plant, and began construction of two
other batch plants––one on the grounds of the Sloan Quarry and
another in North Las Vegas (the Delhi batch plant). Thereafter,
until 2010, Respondent operated its Las Vegas area ready-mix
concrete business under the name, Regal Materials, Inc. d/b/a
Southern Nevada Ready-Mix (SNRM). The record further
establishes that, while, through August 2010, Respondent whol-
ly owned SNP, Frehner, and SNRM, Sean Stewart worked as
the general counsel of each business entity, Steve Jensen was
the human resources director for each, and there was an “over-
lap” of supervision on identical work performed by SNP and
Frehner, each was held out as a separate business entity, nego-
tiating collective-bargaining agreements with the Union and
bidding for and performing work in the Las Vegas area build-
ing and construction industry under its own name. Then, on or
about August 7, 2010, Respondent merged SNP and Regal into
Frehner and, on the same date, renamed the business Aggregate
2 There is no dispute that the decertification petition and the subse-
quent certification involved the ready-mix delivery drivers and mechan-
ics, who were based at Regal’s Summerlin plant.
1430
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
Industries–––SWR, Inc.3 In this regard, while subsequent to
the merger, Respondent replaced the names on its equipment
with Aggregate Industries––SWR and bargained with the Un-
ion under the latter name, at least through the start of the hear-
ing, Respondent’s website continued to list SNP, Frehner, and
SNRM, by name, as separate divisions of Aggregate Indus-
tries—SWR, Respondent retained the names, SNP, Frehner,
and SNRM as fictitious company names, and Sean Stewart4
admitted that, prior to the merger, he informed the Union that,
thereafter, Aggregate Industries––SWR would continue to exist
as “separate divisions that would operate construction and op-
erate ready-mix.”
The record establishes that the Union has had a long history
of representing certain employees of both Frehner and SNP
pursuant to the terms of successive construction master labor
agreements between the Union and Nevada Contractors Asso-
ciation and Associated General Contractors (AGC). Thus,
through 2010, Frehner and SNP were each members of the
AGC, which negotiates collective-bargaining agreements on
behalf of its members with the Union and other unions, includ-
ing the Operating Engineers Union and the Laborers Union,
and, thereby, parties to the aforementioned successive collec-
tive-bargaining agreements,5 the most recent of which (the
Construction Agreement), was effective from July 1, 2007,
through June 30, 2010.6 Two months prior to the start of nego-
tiations for a successor Construction Agreement, in June 2010,
SNP and Frehner each withdrew its proxy from the AGC to
represent it during bargaining and, after the Union demanded to
bargain with both companies, each commenced bargaining with
3 Apparently, the merger was an aspect of Respondent’s nationwide
plan to limit the number of affiliated corporations and to make its busi-
ness enterprise more manageable.
4 Under initial questioning by counsel for the Acting General Coun-
sel, Stewart denied that Respondent continues to hold Aggregate Indus-
tries––SWR as operating as three separate divisions.
5 Apparently, on occasion, Frehner would execute a proxy for AGC
to represent it during contract negotiations with the Union and be
bound to the master labor agreement. On other occasions, Frehner
would withdraw its proxy and, by itself, negotiate a collective-
bargaining agreement with the Union, the terms of which would be
virtually identical to the master labor agreement.
6 In part, art. 3 of the Construction Agreement states:
It is further agreed and understood that employees covered by this
Agreement shall continue to be assigned all work which they have his-
torically or customarily been assigned by the Employer to perform.
The Employer agrees that such work assignments under this Agree-
ment are to be awarded to employees under this Agreement as op-
posed to any other represented or unrepresented employees of the
Employer and that if there is any dispute or claim raised by any other
employees of the Employer as to such work assignments, the Em-
ployer agrees to assign the work to the employees covered by this
Agreement.
Art. 43 of the agreement is entitled “Supplemental Agreements” and
states, “Supplemental Agreements may be negotiated covering Signato-
ry Employers engaged in commercial sand and gravel operations to
allow for competitive wage/fringe amounts prevailing in that industry.”
Dana Wiggins, a former director of labor relations for AGC, testified
that said provision “gives the contractor the right to negotiate a rock,
sand, and gravel agreement for his trucking so he’s not competing
against people at a lesser rate.”
the Union along with the AGC but on a separate basis.7 How-
ever, subsequent to August 7, SNP and Frehner continued ne-
gotiating with the Union but under the new corporate name,
Aggregate Industries––SWR. Basically, the Union represents
each signatory employer’s material haul dump and transit truck
drivers, water and fuel truckdrivers, forklift drivers, off road
equipment drivers, sweeper truckdrivers employed by the sig-
natory contractors,8 and covers both onsite and offsite work by
the bargaining unit employees of each signatory contractor.9
At some point in early 2008, following the Union’s certifica-
tion as the exclusive bargaining representative of Regal’s driv-
ers and mechanics and the latter’s layoff of its bargaining unit
employees and closure of its Summerlin facility and upon be-
coming aware that Regal was considering reopening its existing
batch plant and constructing two others, representatives of the
Union approached Regal, and the parties commenced discus-
sions on Regal’s future plans.10 Then, when the latter reopened
its Summerlin batch plant, their discussions morphed into nego-
tiations for a collective-bargaining agreement. Wayne King,
the secretary/treasurer, Dewaine (Dewey) Darr, a business
agent, and an attorney primarily represented the Union during
bargaining, and representing SNRM were Stewart, Jensen, and
Pat Ward, Respondent’s regional president. At the time, the
Union had existing collective-bargaining agreements with two
other ready-mix concrete manufacturers, Nevada Ready-Mix
and Rinker Materials, which, in 2007, was purchased by Ce-
mex, and Darr informed SNRM that the Union desired the col-
lective-bargaining agreement with SNRM to “mostly . . . mirror
the other two contracts.” According to Stewart, there were
three distinct aspects to the bargaining––the ready-mix concrete
delivery drivers, who had been laid off from the Summerlin
plant prior to the contract negotiations and rehired during the
discussions,11 nine off-road equipment operators who were
employed by Frehner at the Sloan Quarry and working under
the terms and conditions of employment set forth in the Con-
7 Frehner and SNP made initial contract proposals to the Union,
which, among other requests, would have decreased wage rates signifi-
cantly.
8 Frehner did not employ drivers, who transported materials to its
jobsites and, instead, relied on SNP material haul drivers or drivers of
outside vendors to deliver construction material to its jobsites. On the
other hand, SNP employed a complement of approximately 60 material
haul drivers, who operated such equipment as 10-wheel dump trucks,
double belly dump trucks, double side dump trucks, and end dump
trucks, to deliver construction materials to its jobsites. Neither compa-
ny employed drivers, who drove ready-mix concrete delivery trucks.
9 The record establishes that the Construction Agreement bargaining
unit material haul drivers deliver aggregates and other materials, in-
cluding asphalt, from quarries to construction sites, drive dump trucks
on construction sites, and haul trash from construction sites to dump
sites.
10 At some point during the bargaining, Regal informed the Union
that it would thereafter be known as SNRM, and I shall refer to this
entity as SNRM.
11 At the time and through August 2010, SNRM employed no mate-
rial haul drivers. When SNRM reopened its Summerlin plant and be-
gan production at its Delhi batch plant, it utilized SNP’s material haul
drivers to transport material from the Sloan Quarry to those batch
plants.
AGGREGATE INDUSTRIES
1431
struction Agreement, and the hauling of aggregate materials.
As to the ready-mix concrete delivery drivers, the record evi-
dence is that the parties eventually agreed upon terms and con-
ditions of employment virtually identical to those of the Un-
ion’s collective-bargaining agreements with Nevada Ready-
Mix and Cemex, memorializing them in a collective-bargaining
agreement (the Ready-Mix Agreement),12 effective from July 1,
2008, through May 31, 2012. Regarding the nine Frehner em-
ployees, who worked under the terms of the Construction
Agreement at the Sloan Quarry, the record discloses that three
drove water trucks and water pulls and six operated large rock
hauling vehicles, which hauled material around the site and
“the farthest they would go would be ready-mix plants that are
set up within a mile where they don’t have to go on main
roads”;13 that SMRM wanted them to be covered under its con-
tract with the Union rather than Frehner’s collective-bargaining
agreement with the Union; that the Union viewed SNRM’s
request as reasonable as the latter was going to assume respon-
sibility for operating the quarry, and that the parties eventually
entered into a Memorandum of Understanding, agreeing that
the nine employees would thereafter work for SNRM under the
terms of its contract with the Union with implementation de-
layed until January 2009.14
The third aspect of the parties’ bargaining is most relevant to
the instant matters and a point of contention between them.
While agreeing to accept almost all of the terms and conditions
of employment of the Nevada Ready-Mix and Cemex collec-
tive-bargaining agreements demanded by the Union, SNRM
insisted that the appendix A of the agreements also be incorpo-
rated in the parties’ eventual collective-bargaining agreement.
Those appendices set forth wage rates for ten classifications of
bargaining unit employees including, transport driver (bulk)
and transport driver (S&G), the latter of which covers aggre-
gates material haul drivers,15 and a similar appendix were even-
tually included in the parties’ Ready-Mix Agreement.16 Ac-
12 At the hearing, witnesses and attorneys referred to this agreement
as the Ready-Mix Agreement or the Rock, Sand, and Gravel Agree-
ment. I shall refer to it as the former.
13 Three ready-mix concrete batch plants, including that owned by
SNRM, are located within a mile of the quarry.
14 The Union’s new administration, which assumed office in January
2009, initially challenged the implementation of the parties’ agreement
on the nine employees but, upon becoming aware of the terms of the
Memorandum of Understanding, withdrew its objections.
15 The record establishes that material haul drivers, employed by
ready-mix concrete companies, deliver aggregates, in the form of so-
called plant mix, from quarries to batch plants, deliver aggregates, of
various sizes, to construction projects under subcontract arrangement
with contractors signatory to the Construction Agreement, and, pursu-
ant to retail sales agreements, deliver aggregates to customers on con-
struction sites or elsewhere. In this regard, Larry Miller, the corporate
administrator for Nevada Ready-Mix Corporation, testified that his
company owns a quarry site at which it mines, crushes, screens, and
washes concrete aggregates and other building materials, and “we haul
the material ourselves.” to customers on construction sites or ready-mix
concrete batch plants in dump trucks, transfer trucks, and other road
haul trucks.
16 Analysis of art. 34 of the Construction Agreement and app. A dis-
closes that, effective July 1, 2009, the wage rates for construction mate-
cording to Darr, fully cognizant that SNRM did not own any
aggregate transport trucks but, rather, utilized SNP’s equip-
ment17 and drivers18 for material hauls, union representatives
asked why the company was insisting upon inclusion of the
transport driver (S&G) classification in the collective-
bargaining agreement, and Ward replied “that, if we needed
equipment for the ready-mix, we would obtain [trucks] through
Colorado . . . and that would be ready-mix trucks and material
trucks.” Stewart testified that, in response to Darr’s question,
the parties actually “discussed . . . how we would truck materi-
als under the [Ready-mix] Agreement. . . . We weren’t sure
how to do it. We had construction trucks doing both. . . . The
same guy was doing . . . material deliveries” to batch plants and
working on construction sites, and “we needed the flexibility to
be competitive and we delivered materials. We tried to figure
out how to do that at that time.” Darr testified that he respond-
ed, mentioning that, during visits to the Sloan Quarry, he no-
ticed between10 to 15 SNP “non-utilized” trucks always parked
daily and asking Ward “if he had extra [SNP] trucks, why
wouldn’t
you
just
paint
them
[SNRM]
and
. . . utilize those trucks as you plant haul, why would you be
using construction trucks to haul your material into all three of
your plants at construction wages.” Stewart testified that Darr
went further, saying “[Y]ou’ll have an advantage because
you’ll be able to truck your materials under the [ready-mix
collective-bargaining agreement].” While Darr insisted that he
referred only to plant hauls (material hauls from the Sloan
Quarry to SNRM’s batch plants), Stewart recalled Darr saying,
“[I]t would have been our plant hauls and then materials that
we made at Sloan Quarry that we sold both to outside custom-
ers, internal customers, ourselves and to other ready-mix cus-
tomers.”19 While he specifically denied stating that, after Re-
spondent transferred material haul trucks from SNP to SNRM,
the latter would be able to haul aggregate materials to construc-
tion projects at ready-mix agreement wage rates, Darr later
contradicted himself. Thus, after noting that Nevada Ready-
Mix and Cemex drivers haul aggregates to jobsites on a sub-
contract basis and for direct retail sales, he conceded that “what
[SNRM] did with their trucks that had to [have] SNRM on
them was up to them . . . [the trucks] had to say SNRM on
rial haul drivers ranged between $30.29 and $31.28 per hour, while
ready-mix material haul drivers were paid either $24.50 or $23 per
hour.
17 While “primarily” engaged in paving and excavation operations,
SNP also was in the business of hauling aggregate materials around the
Las Vegas area. In doing so, SNP utilized so-called “dual use trucks,”
with the same equipment being used on jobsites and for material hauls.
18 In using SNP’s drivers for its material hauls, SNRM was required
to pay Construction Agreement wage rates.
19 Stewart testified, “Dewey said specifically to me . . . that they
would be able to transfer the Sloan Quarry to the Ready-Mix and that
also we’d be able to run material trucks under SNRM. Now, he did
have the stipulation that if we did that, we would have to change the
name on the door so there was a distinction between SNP trucks and
SNRM trucks. And we discussed that in detail and it wasn’t something
that we were willing to do at that point.”
The record reveals that, unlike Nevada Ready-Mix, SNRM did not
own or produce its own aggregate for its ready-mix concrete business.
1432
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
them to haul plant mix but they were allowed to use those
trucks just like [Cemex] and [Nevada] Ready-Mix. It was nev-
er our intent to stop that.”20 In any event, Stewart testified that
he responded to Darr that the latter’s suggestion was not feasi-
ble at the time because SNP was utilizing its trucks on con-
struction for 4 days a week and for material hauling just 1 day a
week––”my heartburn was we weren’t ready to take [such a
step].” Thus, following Darr’s suggestion, “we would’ve had
to have taken the SNP truck, relicensed it, registered it under
[Regal] . . . so that we could put SNRM on the door. In addi-
tion, we would’ve had to . . . laid off the driver . . . and redis-
patched him under the [ready-mix] list.”21 Finally, asked
whether, during the 2008 negotiations,22 Darr referred to trucks
or people, Stewart conceded that the former “was talking about
trucks . . . about assets” and that he knew that if SNRM wanted
drivers for its trucks, it was required to seek dispatches from
the Union.23
20 There does not seem to be any dispute that material haul drivers,
employed by a signatory to a ready-mix agreement, may haul aggre-
gates to a jobsite whether on a subcontract basis for a Construction
Agreement contractor or on a direct retail sale basis to a Construction
Agreement contractor. In such a circumstance, the driver must drop his
load at a designated stockpile site. If delivering to a jobsite on a sub-
contract basis, a ready-mix agreement signatory must pay its material
haul drivers at the prevailing or Construction Agreement wage rate;
while, if doing so on a retail sale basis, the contractor may pay its driv-
ers at the ready-mix agreement wage rate. Finally, on either basis, if
the material haul driver is utilized for work on the jobsite (for example,
delivering aggregates from the stockpile to the worksite), he or she
must be paid at the Construction Agreement wage rate.
21 Stewart testified that Darr told the SNRM negotiators that, after
the foregoing steps, pursuant to the Construction Agreement rules, a
truck could no longer be utilized for construction work if no ready-mix
work was available. Indeed, art. 4 of the agreement sets restrictions on
the use of nonsignatory contractors for material hauling work––the
signatory contractor must have utilized all of its equipment and no
other signatory contractors have available equipment.
22 Respondent contends that Darr, on behalf of the Union, agreed
that, by entering into the Ready-Mix agreement, Respondent would
have the right to transport aggregates from the Sloan Quarry to con-
struction sites just as Cemex and Nevada Ready-Mix did, and to pay its
material haul drivers at the Ready-Mix Agreement wage rate for doing
so. In this regard, I note that, in 2008, SNRM did not employ any
material haul drivers and did not own its own rock. Moreover, if such
an agreement was reached, the parties failed to enter into a Memoran-
dum of Understanding, memorializing their said agreement. In this
regard, Sean Stewart testified that there was no such document as “we
were not willing to commit to transferring material driver trucks at that
time because of the type of work that we were doing. So there was no
definite date set for any transfer [of] material drivers,” further, when
asked why Respondent failed to implement the Union’s agreement at
any time after July 2008, Stewart testified that there were two reasons.
First, in 2008, SNP had a great deal of construction work, and its trucks
were “tied up on projects.” Next, the Union was specific that, if SNRM
was going to operate material haul trucks, its logo would have to be on
the doors of the vehicles––”So that would have required us to take
assets that were busy on construction sites and put new names on the
doors and send them out with [SNRM],” and doing so would have been
“silly.”
23 As set forth above, whatever agreement may have been reached by
the parties regarding any transfer of trucks from SNP to SNRM, the
SNRM and the Union completed negotiations and entered in-
to their Ready-Mix Agreement on July 11, 2008, and from that
date until the merger of SNP, SNRM, and Frehner in August
2010,24 SNRM owned and operated only ready-mix concrete
delivery trucks from its three batch plants and employed drivers
and mechanics under the terms of its aforementioned collec-
tive-bargaining agreement with the Union.25 For deliveries of
aggregate materials from the Sloan Quarry to its three batch
plants or to retail purchasers of its aggregates, SNRM contin-
ued to utilize SNP’s material haul trucks and drivers, who were
paid pursuant to the terms of the Construction Agreement. The
record establishes that SNP’s and Frehner’s combined construc-
tion revenues began declining in 2009; such revenues had been
approximately $350 million in that year and were projected to
be only $120 million in 2010. Conversely, as a consequence of
its expansion in operations during 2008 and 2009, SNRM’s
revenues substantially increased. Also, according to Sean
Stewart, two business developments occurred during the sum-
mer of 2010, which necessitated changes in its material hauling
operations. First, two major construction projects were sched-
uled to end in or about September, and Respondent anticipated
that “a substantial number of trucks would be returning to Las
Vegas that had been dedicated to those projects.” Such meant
that Respondent “would have to find a way to use [the trucks]
delivering materials or selling materials.” Fortuitously, Stewart
testified, in June 2010, Cemex, which purchased all of its ag-
gregates from the Sloan Quarry and utilized its own trucks and
drivers to haul said material to its local batch plants, ap-
proached Respondent “about the possibility of not only making
the material for them but delivering [the aggregate] to their
[batch] plants, which for us was a good idea since they’re one
of our major competitors.” Stewart estimated that SNRM
would need 15 to 20 trucks to deliver the aggregate material for
Cemex to the latter’s ready-mix concrete manufacturing facili-
ties.
In the foregoing circumstances (ongoing negotiations be-
tween the Union and SNP and Frehner for a successor to their
Construction Agreement, the possible parking of several mate-
rial haul trucks, a decline in Respondent’s construction business
transfer of the material haul drivers to coverage under the Ready-Mix
Agreement, and the usage of the material haul drivers, it is clear that
the parties failed to draft a memorandum of understanding on the is-
sues. Thus, Stewart admitted that “other than the [language of the
Ready-Mix Agreement], there is nothing” in writing, permitting Re-
spondent to transfer drivers from coverage under the Construction
Agreement to coverage under the Ready-Mix Agreement.
24 The record evidence is that, between July 2008 and August 2010,
SNP, Frehner, and SNRM each had stable work forces, with SNP’s and
Frehner’s employees being dispatched to work for said employers by
the Union pursuant to the terms of the Construction Agreement and
SNRM’s employees being dispatched to it by the Union pursuant to the
terms of the Ready-Mix Agreement.
25 In January 2009, a new administrative assumed the governing po-
sitions of the Union. Thus, the secretary-treasurer was John Philli-
penas, Wayne Dey became the business agent responsible for servicing
the Construction Agreement, and Johnny Gonzalez became the busi-
ness agent in charge of servicing the ready-mix agreements with Neva-
da Ready-Mix, Cemex, and SNRM.
AGGREGATE INDUSTRIES
1433
offset by an increase in its ready-mix concrete business possi-
bly aided by gaining work for Cemex, and the pending merger
of Frehner, SNP, and SNRM), on July 9, 2010,26 Wayne Dey,
the Union’s business agent, telephoned Stewart27 and asked
whether he could come to the latter’s offices to discuss a possi-
ble grievance situation.28 Upon arriving, Dey was met by
Stewart29 and five of Respondent’s managers. After discussing
the incident, which involved the grievance, one of the managers
raised “the issue we had with the trucks coming back . . . and
the fact that we did not anticipate a very good year in construc-
tion.” Then, Stewart explained that Respondent was undertak-
ing a corporate “reorganization” and gave to Dey “a kind of
timeframe.” Continuing, Stewart told Dey “that we were mov-
ing to Aggregate Industries as a name and we would have sepa-
rate divisions that would operate construction and operate
ready-mix and rock, sand, and gravel but it would be under one
name.” Then, Stewart asked Dey if the latter was aware that
Respondent was signatory to a ready-mix collective-bargaining
agreement, and Dey said he “did know” Respondent was a
ready-mix signatory. Stewart then “told him that we were
planning to move the trucks that we were bringing back to town
under the [Ready-Mix] Agreement” and that “we wanted to do
all of our material hauls under the [Ready-Mix Agreement].
We understand there’s going to be jobs for onsite work, and
we’re willing to keep a group of trucks for that. That’s when
we got into a discussion where Wayne said that’s hard to do
because if you need more in a day, you can’t just transfer a
driver back and forth.” Dey also said that he had “anticipated”
Respondent would like to operate its material haul trucks under
that agreement, and that “he didn’t think there was anything he
could do to stop that.” According to Stewart, he and Dey next
discussed SNP’s material haul drivers, who had returned with
the material haul trucks, and Respondent’s intent to move the
drivers from the Construction Agreement to the Ready-Mix
Agreement,30 and “I asked Wayne if there’s any way that we
can keep our same drivers . . . . Wayne informed me that there
was no call by name out of the [hiring halls] anymore so it’d be
impossible for us to call them out by name.”31 Also, Dey told
26 The record establishes that as of July 2010 other than the 9 quarry
drivers, SNRM employed 20 ready-mix concrete drivers who hauled
ready-mix from batch plants to customers in large bubble trucks;
Frehner employed no truckdrivers; and SNP employed approximately
60 material haul drivers, water truckdrivers, and sweeper truckdrivers.
27 The following account of the meeting and, indeed, of all the con-
versations and meetings thereafter is taken from the uncontroverted
testimony of Sean Stewart. Neither counsel for the Acting General
Counsel called Wayne Dey as a witness during the hearing.
28 Dey asserted that SNP appeared to be using a third party for mate-
rial deliveries when some of its equipment was parked.
29 While aware of Dey’s reason for desiring to meet, Stewart testified
that his intent was “we wanted to start doing all of our material hauls
that we had done previously under the construction agreement under
the [ready-mix] agreement.”
30 This was the first time Respondent had informed the Union of its
plan to move the material haul drivers from SNP and representation
under the Construction Agreement to SNRM and representation under
the Ready-Mix Agreement.
31 Under the Union’s administration prior to January 2009, call-by-
names from the Union’s hiring halls was permitted. The new admin-
Stewart that he did not think Johnny Gonzalez, the business
agent, who operated the ready-mix driver hiring hall dispatch
list, would permit construction drivers to “jump” over other
ready-mix drivers on the ready-mix driver out-of-work list and
that he needed to speak to Gonzalez. Finally, Dey suggested
we look at how Cemex does it, where Cemex has everyone
under the [ready-mix] collective-bargaining agreement, and, if
the company does construction work, they have to pay a higher
rate. Finally, Stewart testified that Dey’s “concern was he
didn’t think there was any way to take drivers who had been
driving . . . under construction and move [them] to ready-
mix.”32
Stewart testified that there was no further contact between
Respondent and the Union on the subject of the material haul
drivers until August 1333 when, on that date, Wayne Dey tele-
phoned him and said “we’re going to have to object to [Re-
spondent’s stated intent to move its material haul drivers from
coverage under the Construction Agreement to coverage under
the Ready-Mix Agreement]. The attorney had looked into it,
and we’re going to object to it. I said, so we’re not going to be
able to keep our own drivers, we’re going to have to lay them
off. He said, no, you’re not going to be able to transfer trucks
because that work has always customarily been done under the
Construction Agreement.”34 After speaking to Dey, Stewart
drafted the following letter, and sent it to the Union by facsimi-
le:
As discussed with the Union in prior meetings, Aggregate In-
dustries is reorganizing its business structure in the Las Vegas
area. As part of the reorganization, [SNP and Regal are being
merged into Frehner, and Frehner’s name will be changed to
Aggregate Industries—SWR, Inc.
In conjunction with the name changes, Aggregate Indus-
tries—SWR, Inc. will be adjusting the size and application of
its trucking fleet to meet market demand. Material hauls for
the company will be performed by Teamster employees under
the rules and regulations of the [Ready-Mix Agreement]. The
contracting division will continue to utilize teamsters under
istration discontinued this hiring hall procedure. Thus, all dispatches
were done in seniority order.
32 According to Stewart, his discussion with Dey, regarding retaining
SNP’s existing material haul drivers but placing them under the terms
and conditions of employment of the Ready-Mix Agreement, was about
not having to go through the process of laying them off and then hiring
them after dispatch from the Union’s hiring hall. Asked whether, dur-
ing his meeting with Dey, they discussed merely transferring the mate-
rial haul drivers from the Construction Agreement bargaining unit to
the Ready-Mix Agreement bargaining unit, Stewart responded, “No,
no, not at all.” What Stewart wanted was to be able to call for the
drivers “by name” from the Union’s ready-mix drivers hiring hall, “but
I knew that the procedure had changed and I was asking Wayne if
there’s any way to get around it so we could keep our same drivers.”
33 According to Stewart, at this point, “we hadn’t talked to the driv-
ers at all. . . . We had just talked to Wayne about [transferring] trucks to
[ready-mix] and we wanted to man them with our existing drivers.”
34 Stewart denied ever stating to Dey that Respondent would just
transfer the material haul drivers from one bargaining unit to the other,
thereby bypassing the hiring hall procedure of the collective-bargaining
agreements.
1434
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
the Construction [Agreement] for on site material hauls, water
trucks, and equipment transfers.
Two days later, by letter, Wayne Dey responded to Stewart,
writing that “the delivery of materials to job sites . . . must con-
tinue to be done under the construction agreement. Material
deliveries to job sites have historically been performed only
under the construction agreement. This is part of the bargain-
ing unit work under the construction agreement and may not be
done under any other agreement.”
Stewart further testified that, for the next 21 days, he and
Dey exchanged several letters concerning the material haul
drivers, “and we had come to a stalemate that the Union was
not going to allow us to lay off drivers and rehire them” after
dispatch from the Union. Then, on September 24, Respondent,
by facsimile, submitted a dispatch request to the Union for 64
drivers in four job classifications (22 transfer drivers, 20 double
belly drivers, 12 double-side dump drivers, and 10 end dump
drivers) covered under the terms of the Ready-Mix Agreement.
The Union failed to act upon Respondent’s dispatch request,
and, 2 days later, on September 26, Stewart and Dey spoke,
with Stewart asking “if we were going to get drivers, and [Dey]
said, no, there would be no drivers coming from the hall” inas-
much as “he didn’t agree that we had the right to transfer the
trucks and the work under the [Ready-Mix] collective-
bargaining agreement.” That same day, pursuant to article 3 of
the Ready-Mix Agreement, which permits a signatory employer
to procure employees from other sources if the Union fails to
dispatch workers, Respondent “started to look for outside
sources to fill our trucks. . . . We put an advertisement in the
newspaper.” Also, “we put the word out on the street” and
solicited company employees as to whether they knew anyone
looking for material haul work. The next day, September 27,
by facsimile, Stewart sent a letter to the Union, disagreeing
with the latter’s view “that delivery of materials had always
been covered under the construction contract.” Continuing,
Stewart asserted that a signatory contractor to the Construction
Agreement always has a “freedom of choice in the purchase of
materials” and that, during bargaining for the Ready-Mix
Agreement,
[T]he Union agreed that, in order for [Respondent] to remain
competitive in the materials business, [Respondent] had to be
allowed to compete under the same terms and conditions as
other competitors who were signatory to a [ready-mix]
agreement
. . . .
In June of 2008, [the Union and Respondent] entered
into a [ready-mix] agreement which covers, among other
things, the delivery of materials. At the time of signing,
[the Union] encouraged [Respondent] to transfer trucks to
the [ready-mix] division so that [Respondent] could com-
pete directly with other signatory material suppliers. At
that time, [Respondent’s] construction divisions were so
busy that the trucks were needed for construction work on
site more than they were needed for material deliveries
from the commercial plant. As a result, [Respondent]
chose not to immediately make changes but to wait for a
more appropriate time.
[The Union] was aware of [Respondent’s] plans to reclassify
work under the current Teamsters labor agreement, and, in
fact, [the Union] assisted [Respondent] in the process of doing
so. In late December of 2008 and early January of 2009 [Re-
spondent] transferred all Teamster workers at its commercial
site from the construction agreement to the [ready-mix]
agreement. Prior to the change, [the Union’s] representatives
met with the affected drivers and explained the need and rea-
soning behind the changes.
The next day, September 28, Stewart and other managers for
Respondent met with union officials including Dey and its at-
torney. Stewart testified that the discussion during the meeting
that day was “whether or not we had the right to move trucks
and call for drivers under the [Ready-Mix Agreement]. Both
parties were pretty entrenched in their position[s].” He added
that “the meeting was very heated and very short. There was
no discussion on how we would [gain the dispatch of drivers]
or if we would do it.” At one point, a company representative
raised the possibility that Respondent could no longer afford to
continue operating its material haul trucks under the Construc-
tion Agreement, and “we discussed the possibility of downsiz-
ing.” According to Stewart, at the end of the meeting, “as we
were leaving . . . their attorney asked the parties if we’d ever
discussed a transition rate. . . . We said we hadn’t; they said we
hadn’t, and so we were both supposed to go home and think
about it.” Shortly after the conclusion of the above meeting,
assertedly taking the Union attorney’s remark as a suggestion,
Stewart drafted Acting General Counsel’s Exhibit 26, entitled
“Proposal for Existing Drivers interested in Transferring to
Active Agreement,” in which he set forth a proposal for any
SNP material haul driver who was interested in continuing to
work for Aggregate Industries––SWR after Monday, October 4,
2010, under the terms and conditions of employment of the
Ready-Mix Agreement. Under that proposal, a material haul
driver would be paid a $27.83 hourly wage rate between Octo-
ber 4 and December 31, 2010, a $24.50 hourly wage rate from
January 1 through March 31, 2011, and a wage rate commensu-
rate with the Ready-Mix Agreement wage rate after April 1,
2011. In addition, Respondent proposed that each material haul
driver would receive the latter agreement’s benefits package
after October 4, 2010.
Two days later, on September 30, Stewart telephoned Dey
and asked, “[I]f we were going to have a chance to get together
and talk about transition rates. Wayne indicated that he had
nothing for me and that the Union wouldn’t be putting together
transition rates.” Nevertheless, Stewart asked Dey to come to
Respondent’s offices and pick up a copy of the former’s draft
proposal. Later that day, Dey did come to Respondent’s offices
and “[reiterated that] the Union didn’t have any proposal for us
and I asked him to . . . give [the draft] to the driver[s at a] meet-
ing that night and he said he would.” Subsequently, Dey tele-
phoned Stewart and told him that Respondent’s transition pro-
posal was unacceptable and then warned Stewart that, if Re-
spondent implemented it, “we would have a fight on our
AGGREGATE INDUSTRIES
1435
hands.”35
With the parties unable to reach agreement on Respondent’s
desire to have its material haul drivers working within the for-
mer SNRM bargaining unit and under the terms and conditions
of the Ready-Mix Agreement and the Union declining to bar-
gain over Respondent’s transition wage rate proposal, Re-
spondent scheduled a meeting with the SNP material haul driv-
ers on October 1 at SNRM’s Sloan Quarry truck yard, at which
its material haul trucks were based, and invited union officials
to attend. The meeting was held as scheduled, with approxi-
mately 50 day shift material haul drivers attending. Represent-
ing Respondent were Sean Stewart, Pat Ward, and Michael
Kuck, the transportation manager for Aggregate Industries–
SWR; Wayne Dey and other officials attended on behalf of the
Union. According to Dean Mulvaney,36 who, since 2008, had
worked for SNP as a material haul driver37 under the terms and
conditions of employment embodied in the Construction
Agreement, Stewart spoke for Respondent about moving the
drivers to employment under the terms of the Ready-Mix col-
lective-bargaining agreement. He explained “what they wanted
to offer us . . . as a package.” Additionally, “there was a lot of
questions asked and . . . it was a little heated at times.” Mul-
vaney added that Sean Stewart “wasn’t sure” on some of the
important issues, saying that “he didn’t have a detailed answer
at that time” and that “when we’re done, you can ask . . . your
[business agent] and he’ll be able to clarify maybe.”38 Stewart
testified that he told the attending material haul drivers that
Respondent had requested the Union to dispatch them under the
terms of the Ready-Mix Agreement; that the Union had refused
to do so; that Respondent was now seeking drivers from other
sources; that the Union had requested
Respondent to draft a phase-in agreement designed to mini-
mize any impact on the drivers;39 and that, if they were inter-
ested in continuing to work for Respondent under the terms of
the Ready-Mix Agreement, they should inform Respondent’s
dispatchers “and we would make arrangements to get them on
the list.” He further testified that he showed the drivers a copy
of Acting General Counsel’s Exhibit 26, and “I told them this
had been given to Wayne Dey the night before and there were
multiple drivers that said they hadn’t seen it and so I had copies
35 Upon being confronted with Respondent’s attorney’s position
statement to the above-captioned unfair labor practice charges, Stewart
conceded that, during his conversation with Dey on August 13, the
latter may have said the Union would “fight” Respondent over chang-
ing the material haul drivers to the Ready-Mix Agreement.
36 Mulvaney testified that he has been a member of the Union since
1996.
37 Mulvaney transports aggregate materials to construction sites and
drives trash from such sites to dump sites.
38 Stewart refused to permit Dey to speak during the meeting; how-
ever, Dey did meet with the attending drivers at the conclusion of Re-
spondent’s meeting.
39 Stewart conceded that his statement was not true and testified that
he meant to convey to the attending material haul drivers that he had
prepared AGC Exh. 26 “at the request of [the Union’s] attorney. He
also maintained that he did not imply that the Union had agreed to it.
made and we left copies at the front desk.”40 Further, Stewart
admitted informing the attending drivers that Respondent had
proposed the above-described proposal to the Union; that Re-
spondent would honor the terms of Acting General Counsel’s
Exhibit 26 for any employees interested in working under the
new wage rates and benefits structure; and that the changes
were “imminent.”41
On Tuesday, October 5, by facsimile, Sean Stewart sent a
letter to the Union, informing the latter that, on the following
Monday, October 11, Respondent would “commence perform-
ing material hauls under the terms and conditions of the
[Ready-Mix Agreement]. All new-hire Teamster material
haulers will be paid the wage rate and benefits set forth in the
CBA. Stewart continued, writing that, “pursuant to discussions
with Local 631 initiated by your attorney, AI is offering current
employees who desire to continue working under the terms and
conditions of the CBA a graduated pay scale . . . designed to
lessen the financial burden to interested employees as they
transition.” Two days later, Respondent placed a copy of Act-
ing General Counsel’s Exhibit 27 in the mail slot of each of the
SNP material haul drivers. The document, entitled “Aggregate
Industries–SWR, Inc. Notice to Employees,” states:
On Monday October 11th, 2010 Aggregate Industries–
SWR-Inc. . . . will commence performing material hauls
under the terms and conditions of the 2008–2012 collec-
tive bargaining agreement. . . . All new Teamster material
haulers will be paid under the terms of the CBA.
AI is offering current employees who desire to contin-
ue working under the terms and conditions of the CBA a
graduated pay scale. In order to qualify, current employ-
ees must fill out and turn in this form to Dispatch no later
than 3pm on Friday October 8th.
Following the foregoing, the document set forth wage rate
and benefits packages for employees virtually identical to those
set forth in the document, which Respondent made available for
the SNP material haul drivers after the October 1 meeting.
There is no dispute that some of the former SNP material haul
drivers agreed to continue working for Respondent under the
terms and conditions set forth in the above document. There is
no record evidence that, having been informed by Respondent
of its intent to implement its plan to perform material hauls
under the terms of the Ready-Mix Agreement 6 days later, the
Union ever requested Respondent to bargain.
Thereafter, on Monday, October 11, having implemented its
transfer of material hauling work to drivers working under the
Ready-Mix Agreement, Respondent continued normal opera-
tions but with limited crews working due to rain. On Tuesday,
40 Stewart said that the document, which he made available to the
drivers did not contain the October 4 implementation date.
41 Asked by me whether he is contending that Respondent acted up-
on Darr’s suggestion in 2010 or is he contending that union officials in
2008 actually agreed with him that you should be able to transfer mate-
rial haul drivers to coverage under the Ready-Mix Agreement, Stewart
answered “the latter” inasmuch as “ we negotiated for the classification
of drivers and one of those classifications was material hauls. And
there was some discussions . . . on how to do that without interrupting
construction work.”
1436
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
October 12, the Union commenced picketing at the Sloan Quar-
ry truck yard. The picketing continued for 2 days at which
point the parties reached an agreement that the striking material
haul drivers would return to work under the terms of the Ready-
Mix Agreement pending resolution of the instant unfair labor
practice charges.42 Dean Mulvaney testified that, subsequent to
returning to work, he is performing the same work as prior to
the work stoppage. Likewise, material haul driver, Phillip
Willars, testified that, prior to October 2010, he hauled asphalt
for SNP and that, subsequent to the work stoppage, the scope of
his work remains unchanged––”I drive all kinds of different
trucks, but I still do the same work.”
With regard to Respondent’s material haul drivers, who had
been working for SNP under the terms and conditions of the
Construction Agreement, the instant consolidated complaint
alleges, and counsel for the Acting General Counsel argues,
that Respondent engaged in acts and conduct, violative of Sec-
tion 8(a)(1) and (5) of the Act, by, on or about October 1, 2010,
unilaterally, without initially affording notice to the Union or
an opportunity to bargain, changing the scope of the Construc-
tion Agreement bargaining unit by moving delivery of materi-
als work from said bargaining unit to the Ready-Mix Agree-
ment bargaining unit43 and changing the terms and conditions
of employment of its above-described employees by requiring
them to work under the terms and conditions of the Ready-Mix
Agreement. Further, as to those material haul drivers, the con-
solidated complaint alleges that Respondent engaged in acts
and conduct, violative of Section 8(a)(1) and (5) of the Act, by
bypassing the Union and dealing directly with those employees
by meeting with them on or about October 1, 2010, for the
purpose of changing their terms and conditions of employment
and requiring said employees to agree in writing to the terms
and conditions of the Ready-Mix Agreement as a condition for
continuing to be employed by Respondent, and, by, from on or
about October 11 through 15, 2010, denying employment op-
portunities to said material haul drivers who had not agreed to
work under the terms and conditions of the Ready-Mix Agree-
ment. Initially, as to the foregoing allegations, I note that al-
most the entirety of the relevant record evidence is not in dis-
pute. Thus, as opposed to his testimony regarding the 2008
negotiations for the Ready-Mix Agreement,44 Sean Stewart’s
42 There is no dispute that, when Respondent’s material haul drivers
are working on jobsites as opposed to merely delivering aggregates to
stockpile sites on jobsites, they are paid at the Construction Agreement
wage rate.
43 While the consolidated complaint par. 7(a) alleges that Respond-
ent unlawfully changed “the scope of the work of the Construction
Unit,” in his posthearing brief, counsel for the Acting General Counsel
describes Respondent’s alleged unfair labor practice as changing the
“scope (definition)” of the Construction Agreement bargaining unit by
removing the material haul drivers from coverage under that agreement
and covering them under the Ready-Mix Agreement. I shall consider
counsel’s contention as the Acting General Counsel’s allegation.
44 What is in dispute is whether, during the 2008 negotiations for the
Ready-Mix Agreement, the Union’s main negotiator, Dewey Darr,
agreed that, by entering into that collective-bargaining agreement,
SNRM, which employed no material haul drivers and did not own or
produce its own aggregate, would have the right to pay its material haul
testimony concerning the events of July through October 2010
was uncontroverted and, as he did not appear to be testifying in
a disingenuous manner, I shall credit his version of the events
of that time period.45
Counsel for the Acting General Counsel and counsel for the
Union contend that, on October 11, by moving all of its materi-
al hauling work from the Construction Agreement bargaining
unit to the Ready-Mix Agreement bargaining unit, Respondent
unilaterally changed the scope of the Construction Agreement
bargaining unit in violation of Section 8(a)(1) and (5) of the
Act. In this regard, of course, the general topics of bargaining
fall into three broad categories––mandatory, permissive, and
illegal. The mandatory subjects of bargaining are those con-
cerning the bargaining unit employees’ wages, hours, and other
terms and conditions of employment and are those over which
the parties must bargain in good faith. Further, an employer
may not impose a unilateral change in a mandatory subject of
bargaining unless it has bargained in good faith to an impasse;
upon such a deadlock in bargaining, the employer may imple-
ment such a change without the consent of the labor organiza-
tion. Hill-Rom Co. v. NLRB, 957 F.2d 454, 457 (7th Cir. 1992).
“Illegal subjects are simply those proscribed by federal, or
where appropriately applied, state law.” Id. The permissive
subjects of bargaining are those matters which fall outside the
purview of Section 8(d) of the Act and are those over which the
parties may voluntarily engage in bargaining. However, in
contrast to a mandatory subject of bargaining, not only may
neither party insist to impasse over a permissive subject but
also an employer may not implement its proposal without the
consent of the labor organization. Id.; Douds v. Longshoremen,
241 F.2d 278 (2d Cir. 1957); Bozzuto’s Inc., 277 NLRB 977,
977 (1985). Put another way, once a labor organization objects
to a permissive subject of bargaining, an employer may not
implement its proposal. Finally, in this regard, and of utmost
significance herein, the scope of a contractual bargaining unit is
such a permissive subject of bargaining, and counsel for the
drivers for hauling aggregate materials not only from the Sloan Quarry
to its batch plants but also from the Sloan Quarry to construction job
sites at the Ready-Mix Agreement wage rate. As to this, as between
Dewey Darr and Sean Stewart, notwithstanding his sometimes confus-
ing and contradictory testimony, I found the former to have been the
more forthright witness regarding said bargaining. Thus, I believe that
Darr, in discussing the material haul driver classification and the matter
of transferring trucks from SNP to SNRM, was concerned only with
hauls from the Sloan Quarry to SNRM’s batch plants and that he would
never have agreed to anything which would have abrogated or dimin-
ished the terms of the Construction Agreement. Further, in this regard,
as I stated at the hearing, I find it telling that Respondent failed to de-
mand that the Union enter into a memorandum of understanding, simi-
lar to that which it negotiated for the nine Sloan Quarry employees,
concerning the rate of pay for any material haul drivers whom SNRM
might employ in the future for transporting aggregates to construction
sites. Of course, such a document would have memorialized any 2008
agreement between the parties, binding the parties for an uncertain
event at an unforeseen time, and would have certainly permitted Re-
spondent, if it had so desired, to immediately have taken advantage of a
cost saving.
45 Likewise, Stewart was uncontroverted as to all of the background
information herein, and I shall rely on such testimony.
AGGREGATE INDUSTRIES
1437
Acting General Counsel therefore contends that Respondent
could not have unilaterally removed or modified a Construction
Agreement bargaining unit position without first obtaining the
consent of the Union. Id.
My quandary is that there exists another—and equally com-
pelling—way to characterize Respondent’s actions herein.
Thus, putting aside the addling existence of the same group of
employees and the same labor organization, it may well be
argued that Respondent’s actions actually constituted a change
in the assignment of work to employees in another bargaining
unit while leaving the Construction Agreement bargaining unit
intact. The significance of such a view of the facts is that, un-
like altering the scope of a bargaining unit, the transfer of work
out of a bargaining unit constitutes a mandatory subject of bar-
gaining and, of course, after bargaining to impasse or waiver by
the Union, Respondent was then free to implement its assign-
ment of material hauling work to drivers, covered under the
Ready-Mix Agreement, unilaterally. Id.
Distinguishing between these two views is not an easy task;
however, contrary to counsel for the Acting General Counsel
and counsel for the Union, after consideration of the record as a
whole, I believe that the correct characterization of Respond-
ent’s actions is that of a transfer of material hauling work duties
from drivers covered under the Construction Agreement to
drivers covered under the Ready-Mix Agreement. As to this, I
note initially that neither counsel for the Acting General Coun-
sel nor counsel for the Union actually indentified in what man-
ner Respondent altered the scope of the Construction Agree-
ment bargaining unit; in fact, paragraph 7(a) of the consolidated
complaint refers to the alleged unlawful unilateral change as
“moving of delivery of materials work from the Construction
Unit to the Ready-Mix Unit”; and counsel for the Union refers
to it as unilaterally moving all of its material hauling work from
[the Construction Agreement bargaining unit to the Ready-Mix
Agreement bargaining unit].” Further, there is no contention
that Respondent eliminated the material driver position from
the Construction Agreement bargaining unit or eviscerated the
position by creating a nonbargaining unit position and assign-
ing the work of bargaining unit employees to employees in the
new job classification. To the contrary, in his August 13 letter
to the Union, Sean Stewart wrote that Construction Agreement
bargaining unit drivers would continue to perform construction
site material hauling work, and it is undisputed that Respond-
ent’s drivers, who currently perform material hauling work on
construction sites, are paid at the Construction Agreement wage
rate. Moreover, Respondent and the Union bargained for and
agreed to a Ready-Mix Agreement bargaining unit job classifi-
cation, transport drivers (S&G), in which material haul truck-
drivers perform virtually the identical off site driving work46 as
their driver counterparts covered by the Construction Agree-
ment. In these circumstances, I believe Respondent’s alleged
unlawful act must correctly be characterized as a transfer of
work from Construction Agreement bargaining unit employees
46 As the record clearly demonstrates, Construction Agreement bar-
gaining unit material haul drivers and Ready-Mix Agreement bargain-
ing unit transport drivers each utilize the identical equipment to
transport aggregate and other materials to construction sites.
to Ready-Mix bargaining unit employees. Therefore, as the
record evidence seems clear, and there is no real dispute, that
Respondent acted unilaterally without the assent of the Union,
the issues are whether it did so after bargaining in good faith to
impasse or, absent impasse, after the Union waived its right to
demand bargaining.
Regarding these issues, the governing legal principles are
well established. Thus, with regard to impasse, the Board law
is that:
[A] genuine impasse exists only where the parties have ex-
hausted all avenues for reaching agreement and there is “no
realistic possibility that continuation of discussion at time
would have been fruitful.” There is no impasse when one of
the parties makes concessions that are not “trivial or meaning-
less”; for a concession by either party “on a significant issue
in dispute precludes a finding of impasse even if a wide gap
between the parties remains because under such circumstanc-
es there is reason to believe that further bargaining might pro-
duce additional movement.” . . . The essential question is
whether there has been movement sufficient “to open a ray of
hope with a real possibility for agreement if explored in good
faith in bargaining sessions.”
Rochester Telephone Corp., 333 NLRB 30, 30 fn. 3 (2001),
quoting Hayward Dodge, 292 NLRB 434, 468 (1989). Con-
cerning the issue of waiver, which, counsel for Respondent
contends, occurred, as stated above, prior to implementing a
change in a mandatory subject of bargaining, an employer is
required to provide timely notice to a labor organization and a
meaningful opportunity for the latter to request bargaining.
Then, upon receiving such notice, the labor organization “must
act with due diligence to request bargaining or risk a finding
that it has waived its right to do so.” However, if the employ-
er’s notice provides insufficient time for negotiations before
implementation or if the employer has made it otherwise clear
that it has no intention of bargaining about the issue, a labor
organization may be excused from the foregoing bargaining
request requirement. Further, in these circumstances, a bar-
gaining request might well be futile as the employer’s notice
“informs” the labor organization of nothing more than a fait
accompli. A latter finding requires objective evidence, and a
labor organization’s subjective impression of its bargaining
partner’s intention is insufficient. KGTV, 355 NLRB 1283,
1283 (2010); Bell Atlantic Corp., 336 NLRB 1076, 1086
(2001).
While Respondent does not assert such a defense, it certainly
appears that, as of October 11, the parties were at impasse over
Respondent’s stated desire to have its offsite material hauling
performed by drivers working under the terms and conditions
of employment established by the Ready-Mix Agreement.
Thus, from July 9, 2010, through mid-September, during face-
to-face meetings and telephone conversations and in letters,
Sean Stewart continually informed the Union that Respondent
intended to have its off-construction site material hauls per-
formed by drivers, who are working under the terms and condi-
tions of employment embodied in the Ready-Mix Agreement,
and that it wanted its former SNP material haul drivers to con-
tinue to perform the work. Likewise, Wayne Dey consistent-
1438
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
ly—and adamantly—maintained the Union’s position—raising
its “objection” to Respondent’s intended course of action and
demanding that the delivery of materials to jobsites remain the
domain of drivers working under the terms and conditions of
employment of the Construction Agreement. Then, during
their meeting on September 28, after Respondent had sought
the dispatch of material haul drivers from the Union’s ready-
mix drivers hiring hall and the Union had refused to honor the
former’s requests, each party remained “entrenched” in its posi-
tion regarding which bargaining unit’s drivers should perform
Respondent’s offsite material hauls. Further, on September 30,
after drafting Respondent’s planned continuation of employ-
ment offer to the former SNP material haul drivers, by which, I
believe, Respondent intended to effectuate the transfer of its
material hauling work to drivers in the Ready-Mix Agreement
bargaining unit, Stewart spoke to Dey, asking whether the Un-
ion desired to bargain over the terms of Respondent’s employ-
ment offer to the former SNP material haul drivers; which in-
cluded the transition wage rate, and the latter, who, I believe,
understood Stewart’s document as implementing the transfer of
material hauling work to drivers in the Ready-Mix Agreement
bargaining unit, initially told Stewart that “he had nothing . . .
and . . . the Union wouldn’t be putting together transition
rates,” later reiterated that the Union would have no proposal
for Respondent, and ultimately warned Stewart that if Re-
spondent implemented its planned course of action regarding
assigning offsite material haul work to Ready-Mix Agreement
bargaining unit material haul drivers, the latter “would have a
fight on [its] hands.” The foregoing establishes that, at no time
between July 9 and October 11, did either Respondent or the
Union demonstrate any interest in making a concession from its
intractably-held position, and there is no reason to believe that
further meetings would have resulted in movement by either
party. In these circumstances, given their intransigence, I think
impasse may well have existed as of October 11 when Re-
spondent implemented its unilateral change. Rochester Tele-
phone Corp., supra.
Nevertheless, assuming the parties had failed to meaningful-
ly bargain to impasse, I also think the Union waived its right to
bargain regarding implementation of Respondent’s plan to
transfer its offsite material hauling work from drivers in the
Construction Agreement bargaining unit to drivers in the
Ready-Mix Agreement bargaining unit. In this regard, on Sep-
tember 30, Dey rebuffed Respondent’s offer to bargain regard-
ing the latter’s continuation of employment offers for the for-
mer SNP material haul drivers––an offer to bargain which, I
think Dey understood, would have opened the entire transfer of
work issue for discussion. Then, on October 5, 4 days after
Stewart had informed the former SNP material haul drivers
regarding Respondent’s terms for them to remain employed by
Respondent, he formally provided notice to the Union that the
drivers’ new terms and conditions of employment, which in-
cluded working pursuant to the Ready-Mix Agreement, would
be implemented on October 11. Notwithstanding having, at
least, 6 days’ notice prior to implementation by Respondent,
presumably bent upon maintaining its legal position regarding
the transfer of the driving work, the Union failed to request
bargaining, and Respondent implemented its announced change
on October 11.
Counsel for the Union contends that there can be no finding
of acquiescence by his client as it had been presented with a fait
accompli by Respondent; therefore, it would have been futile
for the Union to have requested that the former engage in bar-
gaining. I disagree. At the outset, counsel may not justifiably
assert that Respondent’s October 5 notice left insufficient time
prior to implementation for the Union to engage in meaningful
bargaining. In this regard, I note that the Union had been aware
since July 9 that Respondent was determined to move material
hauling work to drivers, who were working under the terms and
conditions of employment embodied in the Ready-Mix Agree-
ment, and that, from July 9 through the September 28 meeting,
rather than engaging in meaningful bargaining, Wayne Dey
merely objected and remained intransigent in the Union’s posi-
tion that Respondent’s offsite material hauls must continue to
be done by Construction Agreement bargaining unit drivers.
Then, on September 30, after Stewart asked whether the Union
desired to bargain over the terms of its proposed continuation
of employment offer to the material haul drivers, Dey rejected
Stewart’s offer, stating that the Union had nothing to offer and
warned it would “fight” implementation. Finally, on October 5
when informed by Respondent that the terms of its continuation
of employment offer would be implemented 6 days later, ap-
parently maintaining its legal position, the Union responded
with silence, failing to exercise its right to demand that Re-
spondent bargain with regard to the above issues. In these cir-
cumstances, the Union had in excess of 90 days in which to
bargain over Respondent’s stated desire to have its material
hauling work performed by its drivers working under the terms
of the Ready-Mix Agreement and, at most, 10 and, at least, 6
days in which to demand bargaining prior to Respondent’s
implementation of its continuation of employment offers to its
material haul drivers,47 by which Respondent effectuated the
transfer of its material hauling work, and, other than protest-
ing,48 and failed to do so. Furthermore, there is no record evi-
dence that Stewart’s September 30 invitation to bargain was
insincere or that Respondent indicated it would not bargain in
good faith concerning its desire that its offsite material haul
work be performed by Ready-Mix Agreement bargaining unit
drivers and to have its former SNP material haul drivers per-
form the work. Based on the foregoing, I find that the Union
had timely notice of Respondent’s intent to implement its trans-
fer of offsite material haul driving work to drivers in the Ready-
Mix Agreement bargaining unit on October 11 and, presumably
47 In Jim Walter Resources, 289 NLRB 1441, 1442 (1988), an em-
ployer provided a union with 10 days’ notice of a change and, during
said time period, the union failed to request bargaining. The Board
concluded that the 10 days provided a “meaningful opportunity” for the
union to have requested bargaining and noted that it has, on occasion,
found as few as 2 days’ adequate notice.
48 The Board has held that “mere protest” is not sufficient to satisfy
the requirement that a union must request bargaining after receipt of
notice of an intended change in terms and conditions of employment or
risk a finding of waiver. KGTV, supra, fn. 7; Medicenter, Mid-South
Hospital, 221 NLRB 670, 673 & 678 (1975).
AGGREGATE INDUSTRIES
1439
maintaining its entrenched legal position, failed to diligently
request bargaining. The Union thereby waived its right to bar-
gain, and Respondent’s implementation of the transfer of work
did not constitute an unlawful unilateral change. Therefore, I
shall recommend dismissal of paragraph 7(a) of the consolidat-
ed complaint. KGTV, supra; Bell Atlantic Corp., supra, at
1087; Jim Walter Resources, supra. 49
I now turn to the second consolidated complaint allegation
pertaining to the material haul drivers––that Respondent unlaw-
fully, unilaterally changed the terms and conditions of em-
ployment of its former SNP material haul drivers by requiring
them to work under the terms and conditions of employment
embodied in the Ready-Mix Agreement––and note that this
issue is but a variant of the initial issue raised by the consoli-
dated complaint. Thus, there is no dispute that, by virtue of its
continuation of employment offers to its material haul drivers,
whose terms and conditions of employment were embodied in
the Construction Agreement, which became effective on Octo-
ber 11, Respondent unilaterally changed their terms and condi-
tions of employment, requiring, as a condition for being re-
tained as an employee, that said drivers agree to work under the
terms embodied in the Ready-Mix Agreement and be paid at
transition wage rates until that collective-bargaining agree-
ment’s wage rate became effective for them. As with Respond-
ent’s reassignment of off-site material hauling work from Con-
struction Agreement bargaining unit drivers to Ready-Mix
Agreement bargaining unit drivers, I believe that whether Re-
spondent’ violated Section 8(a)(1) and (5) of the Act by unilat-
erally changing the terms and conditions of employment of its
former SNP material haul drivers depends upon whether the
parties were at impasse or whether the Union waived its right to
engage in bargaining. In these regards, irrespective of the ques-
tion of impasse, as above, there can be no doubt that the Un-
ion’s inaction constituted a waiver. Thus, Stewart gave notice
to Dey on September 30 of Respondent’s intent to implement
its continuation of employment offer and inquired as to whether
the Union wanted to bargain about the terms of said offer, and
Dey inexplicably spurned Stewart’s offer. Subsequently, on
October 5, Stewart gave notice to the Union that Respondent
would implement its offer of continued employment on Octo-
ber 11, and, the Union failed to request bargaining. Moreover,
I do not believe that Respondent’s implementation on October
11 was a fait accompli. Thus, the Union had, at least, 6 days
prior to the October 11 implementation date to request bargain-
ing but failed to act. Furthermore, there exists no record evi-
dence establishing that Stewart’s offer to bargain on September
30 was disingenuously stated or that Respondent would not
49 Two Board decisions, which are cited by counsel for the Union,
are distinguishable. In Bohemian Club, 351 NLRB 1065, 1066 (2007),
the Board found that a change was a fait accompli as “the union learned
of the change1 week after it happened.” Likewise, in Ciba-Geigy
Pharmaceuticals Division, 264 NLRB 1013, 1018 (1982), the Board
found that a union was faced with a fait accompli when it futilely re-
quested bargaining as “the new program had already been implement-
ed.” Herein, of course, I believe the Union had ample time to have
requested bargaining prior to Respondent’s implementation of its con-
tinuation of employment offer to its material haul drivers.
thereafter have agreed to bargain concerning the terms of its
employment offers. Therefore, I must, and do, conclude that
the Union had timely notice of Respondent’s intent to imple-
ment its continuation of employment offer to its former SNP
material haul drives and that the Union failed to do so, thereby
waiving its right to bargain. Id. In these circumstances, Re-
spondent’s unilateral change was not unlawful, and I shall rec-
ommend that paragraph 7(b) of the consolidated complaint be
dismissed.
Next, with regard to the former SNP material haul drivers, I
consider the allegation that, in meeting with its said employees
on October 1, Respondent bypassed the Union, its employees’
bargaining representative, and engaged in direct dealing in
violation of Section 8(a)(1) and (5) of the Act. The Board law
is clear that an employer is obligated to bargain exclusively
with the designated bargaining representative of its employees
with regard to their terms and conditions of employment, and,
by dealing directly with employees, who are represented by a
labor organization, or with any representative other than the
exclusive bargaining representative regarding such matters, an
employer violates Section 8(a)(1) and (5) of the Act. SPE
Utility Contractors, LLC, 352 NLRB 787, 791 (2008). The
crux of this violation of the Act is that dealing directly with
represented employees undercuts the labor organization’s abil-
ity to function as the bargaining representative and interferes
with the employees’ right to union representation. “This is true
whether it concerns a decision which is contemplated or wheth-
er it concerns a decision . . . that has already been made by an
employer.” Master Plastering Co., 314 NLRB 349, 351
(1994); Ad-Art, Inc., 290 NLRB 591, 606 (1988). Finally, “an
element of direct dealing with employees is the lack of consent
by the designated bargaining representative to these employee
contacts.” Kansas Education Assn., 275 NLRB 638, 640
(1985).
In assessing the merits of this unfair labor practice allega-
tion, I note that, for some reason unknown to me, counsel for
the Acting General Counsel failed to present any underlying
theory or supporting legal argument in his post-hearing brief,
and, given the context, I do not believe that Respondent en-
gaged in direct dealing. Thus, on September 30, the day before
the meeting, Wayne Dey had adamantly rejected Sean Stew-
art’s offer to bargain over the terms of Respondent’s continua-
tion of employment offers to its former SNP material haul driv-
ers and had held a meeting for those drivers during which he
presumably presented the terms of the offers to them. Further,
rather than in order to bypass the Union and to bargain with its
former SNP material haul drivers, Respondent used the October
1 meeting with them merely to disclose its plan to transfer its
material hauling work to those drivers, who agreed to work
pursuant to the terms of the Ready-Mix Agreement, and to
announce implementation of its continuation of employment
offers. In this regard, during the meeting, Stewart set forth
Respondent’s intent to have its material hauling work per-
formed pursuant to the terms of the above-collective-bargaining
agreement and the Union’s refusal to consent, presented the
terms of the continuation of employment offers to the attending
drivers, and answered their angry questions. Moreover, rather
than being excluded, Dey and other union representatives were
1440
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
invited and, in fact, attended the meeting, and, while not being
allowed to speak during Respondent’s meeting, they met with
the drivers immediately after it concluded. Perhaps, in other
circumstances, a meeting, such as conducted by Respondent on
October 1, might be categorized as unlawful direct dealing but
not on the instant facts. Accordingly, I shall recommend that
paragraph 7(c) of the consolidated complaint be dismissed.
Finally, concerning the former SNP material haul drivers, the
consolidated complaint alleges that Respondent unlawfully
denied employment opportunities to those former SNP material
haul drivers who refused to agree to work under the terms and
conditions of the Ready-Mix Agreement. Contrary to the Act-
ing General Counsel, I have found that the Union waived its
right to bargain regarding Respondent’s transfer of material
hauling work to Ready-Mix Agreement bargaining unit drivers
and concerning the terms of its continuation of employment
offer to the above employees. Consequently, Respondent’s
implementation of neither of those changes in the terms and
conditions of employment of the material haul drivers may be
found unlawful, including Respondent’s requirement that each
driver sign a document, agreeing to continue working under the
terms of the Ready-Mix Agreement. In these circumstances, I
find no merit to the above allegation and shall recommend dis-
missal of paragraph 7(d) of the consolidated complaint.
The Sweeper Truckdrivers
The record next reveals that, in addition to material haul
trucks, Respondent utilizes sweeper trucks at its constructions
sites and vehicle yards and employs sweeper truckdrivers to
operate said vehicles. Thus, prior to the August merger, SNP
utilized three mechanical sweeper trucks, which have brooms
that push aside the dirt, on its construction sites and at its truck
yard, and Frehner utilized two vacuum sweepers, which vacu-
um up dirt and dust, on its jobsites. SNP employed members of
the Union to operate its equipment, and Frehner utilized mem-
bers of the Operating Engineers Union, whose collective-
bargaining agreement with AGC contains a sweeper driver job
classification, to operate its equipment.50 According to Sean
Stewart, in 2004, during its contract negotiations with AGC,
after presenting evidence to AGC that it had successfully orga-
nized three sweeper companies, Laborers International Union
of North America, Local 872 (the Laborers), demanded and
was granted a sweeper driver job classification in its new col-
lective-bargaining agreement. Then, in 2005, after the Laborers
filed a grievance against either SNP or Frehner for contracting
with a nonunion sweeper company, the parties settled the mat-
ter, “and, from that point forward, if we needed additional
sweeper help, we would hire the [Laborers-represented] sweep-
er companies.51
50 According to Michael Kuck, any available operating engineer em-
ployee on a jobsite could operate a sweeper truck.
51 Apparently, there no longer are any Teamsters Union or Operating
Engineers Union-represented sweeper truck companies.
Asked if the Laborers Union had ever demanded to represent either
SNP’s or Frehner’s sweeper drivers, Stewart testified that “on numer-
ous occasions” during 2010 the Laborers Union secretary/treasurer had
requested that the sweeper driving work be assigned to the Laborers
The record further reveals that two of SNP’s sweeper truck-
drivers, Andrew Barnum and Mike Crane, continued to work
for Aggregate Industries––SWR, Inc. after the merger, operat-
ing the same mechanical sweepers on job sites and in the truck
yard at Sloan Quarry. According to Barnum, he and Crane had
often discussed withdrawing from the Union, and, “mostly due
to the fact that . . . our benefits package was being reduced,”
during a telephone conversation with Michael Kuck in October
about a job, “I finally just asked him . . . with the situation
that’s going on . . . is it possible that [we] might be able to
withdraw from the Teamsters––still maintain [our jobs] here at
AI––and be able to join another union or transfer into a differ-
ent union.” Kuck replied that “he didn’t know but he would
look into it and he would get back to me.” Subsequently, Bar-
num testified, he spoke to Wayne Dey, and he told Dey he
wanted to switch to another union; Dey replied that he wouldn’t
let that happen. Then, after the Union commenced its picketing
against Respondent and while it continued, Barnum encoun-
tered Kuck and asked what was going on with his earlier re-
quest about switching unions. Kuck said he was “looking into
it” and would get back to Barnum.
Michael Kuck confirmed that, in early October, Barnum
spoke to him regarding his and Crane’s desire to no longer be
represented by the Union and asked what options were availa-
ble to them for continuing to work for Respondent. Barnum
asked whether Respondent would be willing to switch them to
another union, either the Operating Engineers or the Laborers.
Kuck said he would speak with his supervisors but would have
to also hear from Crane. Then, “I spoke to Sean about it and
what our options were, and he said that we could switch over to
the Laborers.”52 Kuck then telephoned Barnum, and, according
to the latter, said Barnum had two options––”because most of
the trucks had already been in the [Operating Engineers], they
could probably switch us into Operators and . . . he said that it
looked like we could switch into [the Laborers Union].” Bar-
num told Kuck he would think about it and get back to him.
Thereafter, Barnum testified, he spoke to Crane, and they dis-
cussed their problem “in detail” and reached a decision. He
then telephoned Kuck, and told him that, after he and Crane53
had looked over “everything that was going on with the pension
and the Operators [they would] rather go with the Laborers due
to the fact that their . . . benefits were strong.” Kuck said he
would take care of it and would call Barnum and let him know
when their dispatches would be available. Some time later,
Kuck telephoned Barnum and “let me know that dispatch is
available for me at the Laborers hall and I just needed to go
down and get signed up with the Laborers to be redispatched
Union. On this point, Kuck contradicted Stewart, denying that the
Laborers had ever demanded or claimed the sweeper driver work.
52 Stewart testified that, after Kuck spoke to him he initially did
nothing, hoping the matter would “blow over.” Then, when the request
was renewed to Kuck, “I sent a letter of assignment to the Laborers
872, explaining our current situation. Then, I made a call to the [La-
borers] to see if they would be willing to dispatch these drivers.” Stew-
art admitted he undertook the foregoing without notice to the Union or
affording it an opportunity to bargain.
53 Barnum said that this was a “joint” decision by Crane and him.
AGGREGATE INDUSTRIES
1441
out.” Thereafter, on October 29, he and Crane went to the La-
borers’ hiring hall, joined that labor organization,54 and were
dispatched to Respondent,55 performing the same sweeper work
utilizing the same equipment and some additional laborer work.
Pertaining to the two sweeper truckdrivers, the consolidated
complaint alleges that Respondent engaged in acts and conduct,
violative of Section 8(a)(1) and (5) of the Act, by dealing di-
rectly with said employees for the purpose of changing their
terms and conditions of employment, and by unilaterally, with-
out notice to the Union or affording it an opportunity to bar-
gain, changing said employees’ terms and conditions of em-
ployment by moving the work of sweeper drivers from cover-
age under the Construction Agreement to coverage under its
collective-bargaining agreement with the Laborers Union, and
by changing the scope of the work of the Construction Agree-
ment bargaining unit employees by moving the sweeper drivers
from the Construction Agreement bargaining unit and assigning
such work to the bargaining unit covered by the Laborers Un-
ion collective-bargaining agreement. In these regards, I note
that the facts are not in dispute and that, on all but one issue
discussed below, the three witnesses, who testified regarding
the issues, Stewart, Michael Kuck, and Andrew Barnum, were
mutually corroborative. Initially, turning to Respondent’s al-
leged unlawful assignment of its mechanical sweeper driving
work to drivers in the Laborers’ bargaining unit, I have previ-
ously stated that a transfer of work out of a bargaining unit by
an employer constitutes a mandatory subject of bargaining.
Hill-Rom Co., supra. Further, when an employer unilaterally,
without affording notice or an opportunity to bargain to the
labor organization, which represents certain of its employees,
assigns bargaining unit work to employees outside the bargain-
ing unit and the job duties and functions remain essentially the
same, such acts and conduct violate Section 8(a)(1) and (5) of
the Act. McDonnell Douglas Corp., 312 NLRB 373, 377
(1993); cf. Hanson SJH Construction, 342 NLRB 967, 969
(2004). Herein, Respondent admits that it assigned mechanical
sweeper truckdriving duties, which had been previously been
performed by Construction Agreement bargaining unit drivers,
to sweeper truckdrivers, represented by the Laborers, and that it
did so without notice to or affording the Union an opportunity
to bargain. Moreover, I have found that, since changing their
union affiliations, employees Barnum and Crane have contin-
ued to perform the same sweeper truck duties utilizing the same
equipment.
In its defense, citing J.L. Allen Co., 199 NLRB 675 (1972),
and Brady-Hamilton, 198 NLRB 147 (1972), Respondent con-
tends that it engaged in the above-described acts and conduct in
the context of a work jurisdictional dispute between the Union
and the Laborers and that, therefore, it was insulated from any
asserted violations of Section 8(a)(1) and (3) and Section
8(a)(1) and (5) of the Act. Contrary to counsel, I do not believe
that there existed herein any work jurisdictional dispute be-
tween the Union and the Laborers over which group of bargain-
54 According to Barnum, while the nominal initiation fee was $500,
he and Crane were each required to pay only $90.
55 Both sweeper drivers then went to the Union’s office and were
given “honorable” withdrawals from the labor organization.
ing unit employees should perform Respondent’s mechanical
sweeper truck job duties. In this regard, there is no evidence
that drivers, represented by the Laborers, have ever performed
mechanical sweeper truck work for Respondent. Moreover, in
agreement with counsel for the Acting General Counsel, I also
do not believe that the record warrants the conclusion that the
Laborers ever demanded that the work be assigned to employ-
ees represented by it or ever claimed the work. On this point,
Michael Kuck, who is Respondent’s transportation manager
and obviously in a position to have such knowledge, contra-
dicted Sean Stewart and denied that the Laborers have ever
demanded that its members perform Respondent’s sweeper
driver job duties or claimed said work for its members. Surely,
Stewart would have alerted Kuck to the Laborers’ repeated
requests to perform the mechanical sweeper truckdriving work
for Respondent. In these circumstances, I find that Respondent
engaged in acts, violative of Section 8(a)(1) and (5) of the Act,
by unilaterally, without notice to or affording the Union an
opportunity to bargain, assigning sweeper truckdriving work to
employees, who are in the bargaining unit represented by the
Laborers. McDonnell Douglas Corp., supra.56
Finally, with regard to the allegation of the consolidated
complaint that Respondent bypassed the Union and engaged in
unlawful direct dealing with its Construction Agreement bar-
gaining unit employees, Andrew Barnum and Mike Crane, I
have found that, upon being informed by Barnum that said
employees desired to join another labor organization, Mike
Kuck and him discussed the employees’ options and other labor
organizations whose collective-bargaining agreements covered
the same work and which they might join. Respondent failed to
inform the Union of said conversations. There can be no doubt
that any change in the employees’ bargaining representative
would directly impact their terms and conditions of employ-
ment, and I think that Kuck and, later, Stewart clearly were
aware of this. Further, after Barnum stated that he and Crane
desired to join the Laborers, Respondent apparently facilitated
their membership in the labor organization. As an employer is
obligated to bargain only with the representative of its employ-
ees, the foregoing patently establishes unlawful direct dealing,
and it makes no difference that employees initiated the con-
tacts. Kansas Education Assn., supra at 640 fn. 11. According-
ly, Respondent engaged in conduct violative of Section 8(a)(1)
and (5) of the Act.
CONCLUSIONS OF LAW
1. Respondent is an employer engaged in commerce within
the meaning of Section 2(2), (6), and (7) of the Act.
56 Clearly, Respondent also changed Barnum’s and Crane’s terms
and conditions of employment by recognizing the Laborers as their
representative for purposes of collective bargaining and treating them
as employees in the bargaining unit covered by the Laborers’ collec-
tive-bargaining agreement. Inasmuch as Respondent concedes it failed
to give notice to the Union or afford it an opportunity to bargain when
it assigned mechanical sweeper truck work to the Laborers, I find merit
to the consolidated complaint allegation that Respondent violated Sec.
8(a)(1) and (5) of the Act by unilaterally changing the sweeper truck
drivers’ terms and conditions of employment. LTD Ceramics, 341
NLRB 86, 87 (2004); Bouille Clark Plumbing, 337 NLRB 743 (2002).
1442
DECISIONS OF THE NATIONAL LABOR RELATIONS BOARD
2. The Union is a labor organization within the meaning of
Section 2(5) of the Act.
3. In or about October 2010, during conversations with two
mechanical sweeper truckdrivers, by bypassing the Union and
dealing directly with said employees regarding their respective
terms and conditions of employment, Respondent engaged in
acts and conduct violative of Section 8(a)(1) and (5) of the Act.
4. In or about October 2010, by unilaterally, without afford-
ing notice to the Union or affording it an opportunity to bar-
gain, assigning mechanical sweeper truckdriving job duties to
employees in the bargaining unit represented by the Laborers
Union when such work had previously been done by Construc-
tion Agreement bargaining unit employees, Respondent en-
gaged in acts and conduct violative of Section 8(a)(1) and (5) of
the Act.
5. In or about October 2010, by unilaterally, without afford-
ing notice to the Union or affording it an opportunity to bar-
gain, changing the terms and conditions of employment of two
mechanical sweeper truckdrivers by treating them as members
of the Laborers’ bargaining unit, Respondent engaged in acts
and conduct violative of Section 8(a)(1) and (5) of the Act.
6. Respondent’s unfair labor practices affect commerce with-
in the meaning of Section 2(6) and (7) of the Act.
7. Unless specifically set forth above, Respondent engaged
in no other unfair labor practices.
REMEDY
I have found that Respondent has engaged in serious unfair
labor practices within the meaning of Section 8(a)(1) and (5) of
the Act. Accordingly, I shall recommend that it be ordered to
cease and desist therefrom and to take certain affirmative ac-
tions designed to effectuate the purposes and policies of the
Act. Specifically, I shall recommend that Respondent be or-
dered to cease and desist from bypassing the Union and directly
dealing with its Construction Agreement bargaining unit
sweeper truckdrivers. Further, I shall recommend that Re-
spondent be ordered to cease and desist from unilaterally, with-
out affording notice to the Union or affording the latter an op-
portunity to bargain, assigning mechanical sweeper truck work
to bargaining unit employees, who are represented by the La-
borers, when said work had always been performed by drivers
included in the Construction Agreement bargaining unit and
that Respondent be ordered to restore the status quo ante by
returning the work to Construction Agreement bargaining unit
sweeper truckdrivers and by making sweeper truckdrivers Bar-
num and Crane whole for any lost wages57 and other benefits,
with interest as prescribed in New Horizons for the Retarded,
283 NLRB 1173 (1987),58 caused by its unlawful unilateral
change.59 Moreover, I shall recommend that Respondent be
ordered to post a notice, setting forth its above obligations.60
[Recommended Order omitted from publication.]
57 Back pay shall be computed in the manner set forth in Ogle Pro-
tection Service, Inc., 183 NLRB 682, 683 (1970).
58 Interest shall be compounded daily as prescribed in Kentucky Riv-
er Medical Center, 356 NLRB 6 (2010).
59 By recommending that Respondent be required to restore the sta-
tus quo ante, I recognize that, as the Union would have the right to refer
two new sweeper truckdrivers to Respondent to operate its mechanical
sweeper trucks, Laborers-represented employees Barnum and Crane
may be left without jobs. However, within the parameters of the al-
leged unfair labor practices and in the absence of an allegation that
Respondent’s acts and conduct were violative of Sec. 8(a)(1) and (2) of
the Act, I have no jurisdiction to require either employee to again
change his union affiliation or to require Respondent to utilize either
Barnum or Crane to perform the sweeper truck duties.
60 I shall not require Respondent to disseminate the notice electroni-
cally to its employees. Thus, in J. Picini Flooring, 356 NLRB 11
(2010), the Board required that the notice therein be transmitted elec-
tronically to the respondent’s employees as it customarily communicat-
ed to its employees in such a manner. There is no record evidence in
these matters to suggest that Respondent regularly communicates with
its employees via email or other electronic means. In fact, each em-
ployee has an actual mail slot in which Respondent inserts mail or other
employment-related documents.