40 C.F.R. § 60.2952
What must I submit prior to commencing construction?
Cite as 40 C.F.R. § 60.2952 (2026)
You must submit a notification prior to commencing construction that includes the five items listed in paragraphs (a) through (e) of this section. (a) A statement of intent to construct. (b) The anticipated date of commencement of construction. (c) All documentation produced as a result of the siting requirements of § 60.2895. (d) The waste management plan as specified in §§ 60.2899 through 60.2901. (e) Anticipated date of initial startup.
- Cross-references to the CFR
- 60.2895.60.2899