Pub. L. 118-31, div. C, tit. XXXI, subtit. B, sec. 3127 (as amended)
DEADLINES FOR COMMENCEMENT OF OPERATIONS OF CERTAIN ATOMIC ENERGY REPLACEMENT PROJECTS.
SEC. 3127. DEADLINES FOR COMMENCEMENT OF OPERATIONS OF CERTAIN ATOMIC ENERGY REPLACEMENT PROJECTS.
(a) High Explosive Synthesis, Formulation, and Production Facility.—
(1) Deadline for commencement of operations.—Project 21-D-510, the High Explosive Synthesis, Formulation, and Production facility, shall commence operations by not later than December 31, 2034.
(2) Annual report.—
(A) In general.—The Administrator for Nuclear Security shall submit to the congressional defense committees, not later than February 1 of each year until the termination date specified in subparagraph (B), a report that includes a comprehensive estimate of the funds necessary, by year, to achieve the deadline specified in paragraph (1).
(B) Termination date.—The termination date specified in this subparagraph is the date on which the Administrator determines that the facility referred to in paragraph (1) has commenced operations.
(b) Tritium Finishing Facility.—
(1) Deadline for commencement of operations.—Project 18-D-650, the Tritium Finishing Facility, shall commence operations by not later than December 31, 2036.
(2) Annual report.—
(A) In general.—The Administrator for Nuclear Security shall submit to the congressional defense committees, not later than February 1 of each year until the termination date specified in subparagraph (B), a report that includes a comprehensive estimate of the funds necessary, by year, to achieve the deadline specified in paragraph (1).
(B) Termination date.—The termination date specified in this subparagraph is the date on which the Administrator determines that the facility referred to in paragraph (1) has commenced operations.