Pub. L. 118-31, div. C, tit. XXXI, subtit. B, sec. 3128 (as amended)
INTEGRATED SCHEDULE FOR FUTURE-YEARS NUCLEAR SECURITY PROGRAM.
SEC. 3128. [50 U.S.C. 2453 note] INTEGRATED SCHEDULE FOR FUTURE-YEARS NUCLEAR SECURITY PROGRAM.
(a) In General.—The Administrator for Nuclear Security shall—
(1) develop and maintain a high-level milestone schedule document for all covered construction projects that includes production infrastructure modernization schedules with weapons modernization programs; and
(2) for each covered construction project included in the high-level milestone schedule document under paragraph (1), include in such document an identification and explanation of the status of any associated integrated master schedule.
(b) Inclusion in Future-years Nuclear Security Program.—The milestone schedule document required under subsection (a) shall be included in the future-years nuclear security program for fiscal year 2025 and each subsequent fiscal year.
(c) Covered Construction Project. In this section, the term “covered construction project” means—
(1) a construction project that is subject to Department of Energy Order 413.3B, or a successor order; or
(2) a program designated as Enhanced Management A or B under the Program Execution Instruction of the Office of Defense Programs of the National Nuclear Security Administration.