HAR §11-280.1-33
HAR §11-280.1-33. accordance with section 11-280
Cite as Haw. Code R. § 11-280.1-33
1-31(2) and
(3)
to ensure that it is operating properly;
and
(8}
Prior to the return to use of repaired spill
or overfill prevention equipment, the
repaired spill or overfill prevention
equipment must be tested or inspected, as
appropriate, in accordance with section
11-280.1-35 to ensure it is operating
properly.
(b)
UST system owners and operators must
maintain records, in accordance with section
11-280.1-34, of each repair until the UST system is
permanently closed or undergoes a change-in-service
pursuant to section 11-280.1-71.
(Eff 7/15/18; comp
1/17/20; comp 7/8/21; comp MAR 21 2025
]
(Auth:
HRS
§§342L-3, 342L-32)
(Imp:
HRS §§3421-3, 342L-32)
§11-280.1-34
Notification, reporting, and
recordkeeping.
(a)
Notification. Owners and
operators shall notify the department of any of the
following changes in information relating to an UST or
tank system by submitting the "Notification for
Underground Storage Tanksu form prescribed by the
director:
( 1)
( 2)
{ 3)
( 4)
Completed closure or change-in-service;
Temporary closure or the return to
currently-in-use status;
Changes in product dispensing method,
dispenser system, or under dispenser
containment;
Changes in financial responsibility
mechanism;
(5)
Changes in release detection method;
(6)
Changes in spill and overfill prevention
method;
(7)
Changes in piping;
(8)
Changes in type of regulated substances
stored;
(9)
Changes in corrosion protection mechanism;
280.1-36
3 5 8 4
§11-280.1-34
and
(10)
Installation of or changes in secondary
containment.
(b)
Intent to close notification. Owners and
operators shall notify the department of planned
permanent closure or change-in-service of an UST or
tank system and scheduled excavation work for
permanent closure or change-in-service by submitting
the "Notice of Intent to Close Underground Storage
Tanks" form prescribed by the director.
(c)
Timing of notification. Owners and operators
shall submit the notifications required in subsection
(a) and (b) within thirty days following any of the
changes requiring notification, except that:
(1)
Notification of planned permanent closure or
change-in-service must be received by the
department at least thirty days before
commencement of excavation work for closure
or change-in-service;
(2)
Notification of scheduled excavation work
for permanent closure or change-in-service
must be received by the department at least
seven days before the scheduled work date;
(3)
Notification of change in type of regulated
substance stored to a regulated substance
containing greater than ten percent ethanol
or greater than twenty percent biodiesel
must be received by the department at least
thirty days before the change; and
(4)
Notification of temporary closure must be
received by the department within thirty
days of the UST system having met the
definition of temporary closure in section
11-280.1-12.
(d)
Reporting. Owners and operators must submit
the following information to the department:
(1)
Reports of all releases including suspected
releases (sections 11-280.1-50 and
11-280.1-52), spills and overfills (section
11-280.1-53), and confirmed releases
(section 11-280.1-61);
{2)
Release response actions planned or taken,
280.1-37
3 5 8 4
§11-280.1-34
including initial abatement measures
(section 11-280.1-62), initial site
characterization (section 11-280.1-63), free
product removal (section 11-280.1-64),
investigation for soil and groundwater
cleanup (section 11-280.1-65), and
corrective action plan (section
11-280.1-66);
(3)
Quarterly release response reports (section
11-280.1-65.2);
(4)
Current evidence of financial responsibility
as required in section 11-280.1-110; and
(5)
Notice of changes in Designated Class A or B
Operators (section 11-280.l-241(c)).
(e)
Recordkeeping. Owners and operators must
maintain the following information:
(1)
A corrosion expert's analysis of site
corrosion potential if corrosion protection
equipment is not used (section
11-280.1-20 (b) (4); section
11-280.1-20 (C) (3));
(2)
Documentation of operation of corrosion
protection equipment (section
11-280.1-31(4));
(3)
Documentation of compatibility for UST
systems (section 11-280.1-32(c));
(4)
Documentation of UST system repairs (section
ll-280.1-33(b));
(5)
Documentation of compliance for spill and
overfill prevention equipment and
containment sumps used for interstitial
monitoring of piping (section
11-280.1-35(b));
(6)
Documentation of periodic walkthrough
inspections (section 11-280.1-36(b));
(7)
Documentation of compliance with under
dispenser containment sensing device
requirements (section 11-280.1-37(b));
(8)
Documentation of compliance with release
detection requirements (section
11-280.1-45);
(9)
Results of the site investigation conducted
280.1-38
3 5 8 ";
§11-280.1-35
at permanent closure or change-in-service
(section 11-280.1-74);
(10)
Documentation of operator training (section
11-280.1-245);
(11)
Permits or variances or both, including all
documentation, as specified in section
11-280.1-334(a); and
(12)
Evidence of current financial assurance
mechanisms used to demonstrate financial
responsibility (section 11-280.1-111).
(f)
Availability and maintenance of records.
(1)
Owners and operators must keep the required
records at the UST site or an alternative
location approved by the department.
(2)
Owners and operators must make the records
immediately available for inspection by the
department at the UST site.
(3)
Permanent closure records required under
section 11-280.1-74 may be maintained or
submitted to the department as provided in
section 11-280.1-74.
(g)
Owners and operators of UST systems must
cooperate fully with inspections, monitoring, and
testing conducted by the department, as well as
requests by the department for document submission,
testing, and monitoring by the owner or operator
pursuant to chapter 342L, Hawaii Revised Statutes.
[Eff 7/15/18; comp 1/17/20; am and comp 7/8/21; comp
MAR212025
]
(Auth:
HRS §§3421-3, 3421-7.5)
(Imp:
HRS §§342L-3, 342L-7, 342L-7.5, 3421-30)
§11-280.1-35
Periodic testing of spill
prevention equipment and containment sumps used for
interstitial monitoring of piping and periodic
inspection of overfill prevention equipment.
(a)
Owners and operators of UST systems with spill and
overfill prevention equipment and containment sumps
used for interstitial monitoring of piping must meet
these requirements to ensure the equipment is
operating properly and will prevent releases to the
280.1-39
3 5 8 4
§11-280.1-35
environment:
(1)
Spill prevention equipment (such as a
catchment basin, spill bucket, or other
spill containment device) must prevent
releases to the environment by meeting one
of the following:
(A)
The equipment is double walled and the
integrity of both walls is periodically
monitored at a frequency not less than
once every thirty-one days. Owners and
operators must begin meeting the
requirements of subparagraph (B) and
conduct a test within thirty days of
discontinuing periodic monitoring of
this equipment; or
(B)
The spill prevention equipment is
tested at least once every three
hundred sixty-five days to ensure the
equipment is liquid tight by using
vacuum, pressure, or liquid testing in
accordance with one of the following
criteria:
(i)
Requirements developed by the
manufacturer. (Note: Owners and
operators may use this option only
if the manufacturer has developed
requirements.);
(ii)
Code of practice developed by a
nationally recognized association
or independent testing laboratory;
or
(iii)
Requirements determined by the
department to be no less
protective of human health and the
environment than the requirements
listed in clauses (i) and (ii).
(2)
Containment sumps used for interstitial
monitoring of piping must prevent releases
to the environment by meeting one of the
following:
(A)
The equipment is double walled and the
integrity of both walls is periodically
280.1-40
3 5 8 4
§11-280.1-35
monitored at a frequency not less than
annually. Owners and operators must
begin meeting the requirements of
subparagraph (B) and conduct a test
within thirty days of discontinuing
periodic monitoring of this equipment;
or
(B)
The containment sumps used for
interstitial monitoring of piping are
tested at least once every three years
to ensure the equipment is liquid tight
by using vacuum, pressure, or liquid
testing in accordance with one of the
criteria in paragraph (1) (B) (i) to
(iii).
(3)
Overfill prevention equipment must be
inspected at least once every three years.
At a minimum, the inspection must ensure
that overfill prevention equipment is set to
activate at the correct level specified in
section ll-280.l-20(d) and will activate
when regulated substance reaches that level.
Inspections must be conducted in accordance
with one of the criteria in paragraph
(1) (B) (i) to (iii).
(b)
Owners and operators must maintain records
as follows (in accordance with section 11-280.1-34)
for spill prevention equipment, containment sumps used
for interstitial monitoring of piping, and overfill
prevention equipment:
(1)
All records of testing or inspection must be
maintained for three years; and
(2)
For spill prevention equipment not tested
every three hundred sixty-five days and
containment sumps used for interstitial
monitoring of piping not tested every three
years, documentation showing that the
prevention equipment is double walled and
the integrity of both walls is periodically
monitored must be maintained for as long as
the equipment is periodically monitored.
[Eff 7/15/18; comp 1/17/20; comp 7/8/21;
280.1-41
3 5 8 4
§11-280.1-36
comp MAR 2 1 2025
342L-7.5, 342L-32)
(Auth:
HRS §§342L-3,
(Imp:
HRS §§342L-3,
342L-7.5, 342L-32)
§11-280.1-36 Periodic operation and maintenance
walkthrough inspections.
(a)
To properly operate and
maintain UST systems, beginning not later than July
15, 2019, owners and operators must conduct
walkthrough inspections that, at a minimum, check the
following equipment as specified below:
(1)
Every thirty-one days:
(A)
Spill prevention equipment:
(i)
Visually check for damage;
(ii)
Remove liquid or debris;
(iii)
Check for and remove obstructions
in the fill pipe;
(iv)
Check the fill cap to make sure it
is securely on the fill pipe; and
(v)
For double walled spill prevention
equipment with interstitial
monitoring, check for a leak in
the interstitial area; and
(B)
Release detection equipment:
(i)
Check to make sure the release
detection equipment is operating
with no alarms or other unusual
operating conditions present; and
(ii)
Ensure records of release
(2)
Annually:
detection testing are reviewed and
current;
(A)
Containment sumps:
(i)
Visually check for damage, leaks
to the containment area, or
releases to the environment;
(ii)
Remove liquid (in contained sumps)
or debris; and
(iii)
For double walled sumps with
interstitial monitoring, check for
a leak in the interstitial area;
280.1-42
3 5 8 4
§11-280.1-37
and
(B)
Hand held release detection equipment:
Check devices such as tank gauge sticks
or groundwater bailers for operability
and serviceability;
(3)
For UST systems receiving deliveries at
intervals greater than every thirty-one
days, spill prevention equipment may be
checked in accordance with paragraph (1) (A)
prior to each delivery; and
(4)
For airport hydrant systems, at least once
every thirty-one days if confined space
entry according to the Occupational Safety
and Health Administration is not required or
at least annually if confined space entry is
required (see 29 C.F.R. part 1910):
(A)
Hydrant pits:
(i)
Visually check for any damage;
(ii)
Remove any liquid or debris; and
(iii)
Check for any leaks; and
(B)
Hydrant piping vaults: Check for any
hydrant piping leaks.
(b)
Owners and operators must maintain records,
in accordance with section 11-280.1-34, of operation
and maintenance walkthrough inspections for three
years. Records must include a list of each area
checked, whether each area checked was acceptable or
needed action taken, a description of actions taken to
correct an issue, and delivery records if spill
prevention equipment is checked less frequently than
every thirty-one days due to infrequent deliveries.
[ÃAR2/flifÄ8; comp 1/17/20; am and comp 7/8/21; comp
]
(Auth:
HRS §§342L-3, 342L-7.5,
342L-32) (Imp:
HRS §§342L-3, 342L-7.5, 342L-32)
§11-280.1-37
Periodic inspection and maintenance
of under-dispenser containment.
(a)
Under-dispenser
containment that allows for visual inspection and
access to the components in the containment system to
meet the requirements of section 11-280.1-25 must be
280.1-43
3 5 8 4 .
§11-280.1-37
visually inspected for damage and have any liquid or
debris removed every thirty-one days.
(b)
Sensing devices for under-dispenser
containment used to meet the requirements of section
11-280.1-25 must:
(1)
Be operated and maintained in accordance
with one of the following:
(A)
The manufacturer's instructions;
(B)
A code of practice developed by a
nationally recognized association or
independent testing laboratory; or
(C)
Requirements determined by the
department to be no less protective of
human health and the environment than
those in subparagraphs (A) and (B); and
(2)
Be inspected for proper operation, and
electronic and mechanical components tested,
at least annually.
(c)
OST system owners and operators must
maintain records in accordance with section
11-280.1-34 demonstrating compliance with subsection
(a)
or (b). Written documentation of all inspection,
testing, and maintenance must be maintained for at
least three years. All records that the ODC sensor and
connected equipment are designed to produce must be
maintained for at least three years after the record
is generated.
[Eff 7/15/18; comp 1/17/20; am and comp
7/8/21; comp
MAR 212025
)
(Auth:
HRS §§3421-3,
3421-7. 5, 3421-32)
(Imp:
HRS §§3421-3, 3421-7. 5,
3421-32)
§11-280.1-38
General operating requirements-
codes of practice.
(a}
The following codes of
practice may be used to comply with section
11-280.1-30(a): the transfer procedures described in
National Fire Protection Association Standard 385,
"Standard for Tank Vehicles for Flammable and
Combustible Liquids" or American Petroleum Institute
Recommended Practice 1007, "Loading and Unloading of
MC 306/DOT 406 Cargo Tank Motor Vehicles". Further
280.1-44
3 5 8 4
§11-280.1-38
guidance on spill and overfill prevention appears in
American Petroleum Institute Recommended Practice
1621, "Bulk Liquid Stock Control at Retail Outlets".
(b)
The following codes of practice may be used
to comply with section 11-280.1-31(2):
(1)
NACE International Test Method TM 0101,
"Measurement Techniques Related to Criteria
for Cathodic Protection of Underground
Storage Tank Systems";
(2}
NACE International Test Method TM0497,
"Measurement Techniques Related to Criteria
for Cathodic Protection on Underground or
Submerged Metallic Piping Systems";
(3)
Steel Tank Institute Recommended Practice
ROSI, "Cathodic Protection Testing
Procedures for STI-P38 USTs";
(4)
NACE International Standard Practice SP
0285, "External Control of Underground
Storage Tank Systems by Cathodic
Protection"; or
(5)
NACE International Standard Practice SP
0169, "Control of External Corrosion on
Underground or Submerged Metallic Piping
Systems".
(c)
The following code of practice may be useful
in complying with section 11-280.1-32: American
Petroleum Institute Recommended Practice 1626,
"Storing and Handling Ethanol and Gasoline-Ethanol
Blends at Distribution Terminals and Filling
Stations".
(d)
The following codes of practice may be used
to comply with section 11-280.1-33(a) (1):
(1)
National Fire Protection Association
Standard 30, "Flammable and Combustible
Liquids Code";
(2)
American Petroleum Institute Recommended
Practice RP 2200, "Repairing Crude Oil,
Liquified Petroleum Gas, and Product
Pipelines";
(3)
American Petroleum Institute Recommended
Practice RP 1631, "Interior Lining and
280.1-45
a 5 s 4
§11-280.1-38
Periodic Inspection of Underground Storage
Tanks";
(4)
National Fire Protection Association
Standard 326, "Standard for the Safeguarding
of Tanks and Containers for Entry, Cleaning,
or Repair";
(5)
National Leak Prevention Association
Standard 631, Chapter A, "Entry, Cleaning,
Interior Inspection, Repair, and Lining of
Underground Storage Tanks";
(6)
Steel Tank Institute Recommended Practice
R972, "Recommended Practice for the Addition
of Supplemental Anodes to STI-P3® Tanks";
(7)
NACE International Standard Practice SP
0285, "External Control of Underground
Storage Tank Systems by Cathodic
Protection"; or
(8)
Fiberglass Tank and Pipe Institute
Recommended Practice T-95-02,
"Remanufacturing of Fiberglass Reinforced
Plastic (FRP) Underground Storage Tanks".
(e)
The following codes of practice may be used
to comply with section 11-280.l-33(a)(6):
(1)
Steel Tank Institute Recommended Practice
R012, "Recommended Practice for Interstitial
Tightness Testing of Existing Underground
Double Wall Steel Tanks";
(2)
Fiberglass Tank and Pipe Institute Protocol,
"Field Test Protocol for Testing the Annular
Space of Installed Underground Fiberglass
Double and Triple-Wall Tanks with Dry
Annular Space"; or
(3)
Petroleum Equipment Institute Recommended
Practice RP1200, "Recommended Practices for
the Testing and Verification of Spill,
Overfill, Leak Detection and Secondary
Containment Equipment at UST Facilities".
(f)
The following code of practice may be used
to comply with section 11-280.1-35(a) (1),
(2) and (3):
Petroleum Equipment Institute Publication RP1200,
"Recommended Practices for the Testing and
Verification of Spill, Overfill, Leak Detection and
280.1-46
3 5 8 4