HAR §12-223.1-11
HAR §12-223.1-11. provisions for properly draining the piping and valve body
Cite as Haw. Code R. § 12-223.1-11
The size and arrangement of discharge piping shall be such that any pressure that may exist or develop will not reduce the relieving capacity of the relieving devices below that required to protect the water heater. The following shall apply to discharge pipes:
(A) When a discharge pipe is used, it shall be not less than the nominal size of the valve outlet, and shall be as short and straight as possible, properly supported and so arranged as to avoid undue stress on the valve. When an elbow is placed on a temperature and pressure relief discharge pipe, it shall be located close to the valve outlet;
(B) Where multiple valves relieve into a common discharge pipe, the cross-sectional flow area of the common discharge pipe shall be equal to or greater than the sum of the individual temperature and pressure relief valve discharge pipe areas;
(C) Discharge piping shall be rated for the discharge fluid conditions of pressure and temperature including a minimum and maximum design temperature. Material selection for the discharge piping shall consider the reduction in material toughness at the low end of design temperature and the reduction in material strength at the high end of design temperature. Rigid pipe or tubing should be used for discharge lines that carry hot water or steam;
(D) Plastic discharge pipe and fittings are permitted (when compatible with the process fluid, system design temperatures, and other ambient conditions such as light and humidity) and shall conform to NSF/ANSI 14 Plastics
223.1-33
3559
§12-223.1-12
Piping System Components and Related Materials; and
(E) Discharge piping shall be rated for any static pressure present and the back pressure that may develop when the pressure relief device is at full capacity. Where multiple pressure relief devices or vents discharge into common piping, the back pressure that could develop due to simultaneous flow from all sources shall be considered. [Eff and comp 12/21/19; am and comp SEP - 3 2024 ] (Auth: HRS §397-4) (Imp: HRS §397-4)