HAR §15-215-65
HAR §15-215-65. Joint zone development
Cite as Haw. Code R. § 15-215-65
Where a
project is proposed within more than one transect
zone, the allocation of uses shall be in proportion to
that which is permitted within each zone. The
location of those uses within the project need not
comply with the zone boundaries.] [Eff 10/27/12;
R ] (Auth: HRS §§206E-4, 206E-5, 206E-
7) (Imp: HRS §§206E-4, 206E-5, 206E-7)