32 Ill. Adm. Code 601.220
Disposal Site Design and Construction
Section 601.220 Disposal Site Design and Construction
The disposal site shall be designed and constructed, based
on accepted engineering principles and practices, to further the following:
a) Site
design features shall be directed toward long-term isolation and avoidance of
the need for continuing active maintenance after site closure.
b) Site
design and operation shall be compatible with the closure and post-closure
plans and lead to disposal site closure that provides reasonable assurance that
the performance objectives will be met.
c) The
disposal site shall be designed to complement and improve, where appropriate,
the ability of the disposal site's natural characteristics to assure that the
performance objectives will be met.
d) Surface
features shall direct surface water drainage away from disposal units at
velocities and gradients that will not result in erosion that will require
active maintenance in the future.
e) The
site design shall allow closure in a manner that isolates the wastes and waste
constituents and that requires only minor custodial care to assure long-term
performance.
f) The
site shall be designed and constructed to allow remedial action, if necessary.
Achievement of this objective shall not be accomplished by compromising, or in
any way lessening, the ability of the site to satisfy the performance
objectives and requirements of this Part.
g) The
site shall be designed to accept waste for disposal for a period of at least 50
years. The site shall be designed to accommodate waste generated during the
decommissioning of nuclear power stations in Illinois.