35 Ill. Adm. Code 170.114
Step 4 – Submission of Total Project Application
Section 170
Section 170.114 Step 4 – Submission
of Total Project Application
The permit application shall
incorporate each medium and phase of the overall project. If a series of
applications is contemplated because of the phased nature of a project, where
final design commitments may not be feasible for the latter phases at the same
time that a permit application must be made for the initial phases, the
applications may be staggered, provided that the project plan has adequately
addressed the preliminary design considerations for each medium and phase.
a) Upon receipt of the project permit application, the Project
Coordinator will transmit appropriate sections of the application to specific
Divisions.
b) If one Division's application is incomplete then the total
project application shall be deemed incomplete. However, the technical review
of the application will continue for complete sections of the application.
c) After review by each Division, denials in the form of notices
of incompleteness, if appropriate, shall be prepared and transmitted to the
applicant within 30 days.
d) All resubmissions of applications will be handled in the same
manner as the initial submissions.
e) During the Agency review period all applicant-Agency
interaction will be through the Project Coordinator.
f) After completion of review of the total project application,
if one Division denies its section of the application, then the total
application will be denied.
g) When an application is denied, a meeting may be scheduled
between the applicant and the Agency to discuss the denial.