35 Ill. Adm. Code 218.446
Monitoring Program Plan for Leaks
Section 218
Section 218.446 Monitoring
Program Plan for Leaks
The owner or operator of a
petroleum refinery shall prepare a monitoring program plan which contains, at a
minimum:
a) An identification of all refinery components and the period in
which each will be monitored pursuant to Section 218.447 of this Part;
b) The format for the monitoring log required by Section 218.448
of this Part;
c) A description of the monitoring equipment to be used pursuant
to Section 218.447 of this Part; and
d) A description of the methods to be used to identify all
pipeline valves, pressure relief valves in gaseous service and all leaking
components such that they are obvious to both refinery personnel performing
monitoring and Agency personnel performing inspections.