35 Ill. Adm. Code 370.210
Engineering Report
Section 370
Section 370.210 Engineering
Report
a) General
1) The engineering report assembles basic information; presents
design criteria and assumptions; examines alternate projects including
preliminary layouts and cost estimates; describes financing methods, user
charges and operation and maintenance costs; reviews organizational and
staffing requirements; offers a conclusion with a proposed project for client
consideration; and outlines official actions and procedures to implement the
project.
2) The concept, factual data and controlling assumptions and
considerations for the functional planning of sewerage facilities are presented
for each process unit and for the whole system. These data form the continuing
technical basis for the detailed design and preparation of construction plans
and specifications.
3) Architectural, structural, mechanical and electrical designs
are usually excluded. Sketches may be used to aid in presentation of a
project. Outline specifications of process units, special equipment, etc., may
be included.
4) Engineering reports are not required for sewer extensions or
sewer connections, but shall be required for the following projects:
A) New treatment plants.
B) Expansion or major modification of existing plants.
C) New collection systems.
D) Major upgrading of existing collection systems.
b) Content
The
engineering report shall:
1) Prescribe design period and projected population.
2) Describe the specific service area for immediate consideration
and indicate possible extensions and ultimate use.
3) Present data and information on anticipated quantities of flow
and wastewater constituents. Data from comparable existing installations may
be used to develop the design basis of the proposed facilities if data for the
project under design cannot be obtained in accordance with procedures set forth
in Subparts C, D and E of these standards.
4) Specify the scope and nature of collection system including
pump stations and force mains for immediate and ultimate service areas.
5) Discuss various treatment alternatives with reference to
optimum treatability and other relevant factors.
6) Develop a detailed basis of design for the recommended
treatment process.
7) Indicate compliance with applicable effluent limitations and
discuss the impact of the project on receiving waters.
8) Indicate compliance with the requirements of the Illinois
Groundwater Protection Act [415 ILCS 55].