35 Ill. Adm. Code 370.410
Design
Section 370
Section 370.410 Design
The following items should be
given consideration in the design of sewage pumping stations:
a) Type
Sewage pumping stations in general use fall into three
types: wet well/dry well, submersible, and suction lift.
b) Structures
1) Separation
Dry wells, including their superstructure, shall be
completely separated from the wet well. Common walls must be gastight.
2) Pump Removal
Provision shall be made to facilitate removing pumps and
motors.
3) Access
A) Suitable and safe means of access shall be provided to dry
wells and to wet wells. Access to wet wells containing either bar screens or
mechanical equipment requiring inspection or maintenance shall conform to
Section 370.600(a)(2)(C).
B) For built-in-place pump stations, a stairway to the dry well
with rest landings shall be provided at vertical intervals not to exceed 12
feet. For factory-built pump stations over 15 feet deep, a rigidly fixed
landing shall be provided at vertical intervals not to exceed 10 feet. Where a
landing is used, a suitable and rigidly fixed barrier shall be provided to
prevent an individual from falling past the intermediate landing to a lower
level. A manlift or elevator may be used in lieu of landings in a
factory-built station, provided emergency access is included in the design.
4) Buoyancy
Where high ground water conditions are anticipated, buoyancy
of the sewage pumping station structures shall be considered and, if necessary,
adequate provisions shall be made for protection.
c) Pumps and Pneumatic Ejectors
1) Multiple Units
Multiple pumps or ejector units shall be provided. Where
only two units are provided, they shall be of the same size. Units shall have
capacity such that, with any unit out of service, the remaining units will have
capacity to handle the design peak flows. A single pump equipped with an
audio-visual alarm system to warn of failure may be used when serving only one
single-family dwelling.
2) Protection Against Clogging
A) Pumps handling combined sewage shall be preceded by readily
accessible bar racks to protect the pumps from clogging or damage. Bar racks
should have clear openings not exceeding 1 inch. Where a bar rack is provided,
a mechanical hoist shall also be provided. Where the size of the installation
warrants, mechanically cleaned and/or duplicate bar racks shall be provided.
B) Pumps handling separate sanitary sewage from 30 inch or larger
diameter sewers shall be protected by bar racks meeting the above
requirements. Appropriate protection from clogging shall also be considered
for small pumping stations.
3) Pump Openings
Pumps handling raw sewage shall be capable of passing spheres
of at least 3 inches in diameter. Pump suction and discharge openings shall be
at least 4 inches in diameter. Grinder pumps that do not meet these
requirements may be used solely for lift stations with a capacity of 70 gpm or
less with the largest unit out of service.
4) Priming
The pump shall be so placed that under normal operating
conditions it will operate under a positive suction head, except as specified
in Section 370.133.
5) Electrical Equipment
Electrical systems and components (e.g., motors, lights,
cables, conduits, switchboxes, control circuits, etc.) in raw sewage wet wells,
or in enclosed or partially enclosed spaces where hazardous concentrations of
flammable gases or vapors may be present, shall comply with the National
Electrical Code requirements for Class 1 Group D, Division 1 locations. In
addition, equipment located in the wet well shall be suitable for use under
corrosive conditions. Each flexible cable shall be provided with water-tight
seal and separate strain relief. A fused disconnect switch located above ground
shall be provided for all pumping stations. When such equipment is exposed to
weather, it shall meet the requirements of weatherproof equipment (National
Electric Manufacturers Association (NEMA) 3R or 4).
6) Intake
Each pump shall have an individual intake. Wet well and
intake design should be such as to avoid turbulence near the intake and to
prevent vortex formation.
7) Dry Well Dewatering
Duplicate sump pumps equipped with dual check valves for each
pump shall be provided in the dry well to remove leakage or drainage with
discharge above the maximum high water level of the wet well. Water ejectors
connected to a potable water supply will not be approved. All floor and
walkway surfaces should have an adequate slope to a point of drainage. Pump
seal leakage shall be piped or channeled directly to the sump. The sump pumps
shall be sized to remove the maximum pump seal water discharge which would
occur in the event of a pump seal failure.
8) Pumping Rates
The pumps and controls of main pumping stations, and
especially pumping stations operated as part of treatment works, should be
selected to operate at varying delivery rates. The stations shall be designed
to deliver as uniform flow as practicable in order to minimize hydraulic
surges. The peak design flow of the station shall be determined in accordance
with Sections 370.300(c), 370.310(b) and 370.520(c) and should be adequate to
maintain a minimum velocity of 2 feet per second in the force main. Refer to
Section 370.470(f).
d) Controls
Control float tubes and bubbler lines should be so located as
not to be unduly affected by turbulent flows entering the well or by the
turbulent suction of the pumps. Provision shall be made to automatically
alternate the pumps in use.
e) Valves
Shutoff valves shall be placed on suction and discharge lines
of each pump. A check valve shall be placed on each discharge line, between
the shutoff valve and the pump. Check valves shall not be located on a
vertical rise unless they are specifically designed for such usage.
f) Wet Wells
1) Divided Wells
Where continuity of pumping station operation is critical,
consideration should be given to dividing the wet well into two sections,
properly interconnected, to facilitate repairs and cleaning.
2) Size
The design fill time and minimum pump cycle time shall be
taken into account in sizing the wet well. The effective volume of the wet
well shall be based on design average flow and a filling time not to exceed 30
minutes unless the facility is designed to provide flow equalization. The pump
manufacturer's duty cycle recommendations shall be used in selecting the
minimum cycle time. When the anticipated initial flow tributary to the pumping
station is less than the ultimate average design flow, provisions should be
made so that the holding time indicated is not exceeded for initial flows. When
the wet well is designed for flow equalization as part of a treatment plant,
provisions should be made to prevent septicity.
3) Floor Slope
The wet well floor shall have a minimum slope of 1 to 1 to
the hopper bottom. The horizontal area of the hopper bottom shall be no
greater than necessary for proper installation and function of the inlet.
4) Air Displacement
Covered wet walls shall provide for air displacement open to
the atmosphere, such as by an inverted "j" tube or similar means.
g) Ventilation
1) General
Adequate ventilation shall be provided for all pump
stations. Where the dry well is below the ground surface, mechanical
ventilation is required. If screens or mechanical equipment requiring
maintenance or inspection is located in the wet well, permanently installed
ventiliation is required. There shall be no interconnection between the wet
well and dry well ventilation systems.
2) Air Inlets and Outlets
In dry wells over 15 feet deep, multiple inlets and outlets
should be used. Dampers should not be used on exhaust or fresh air ducts and
fine screens or other obstructions in air ducts should be avoided to prevent
clogging.
3) Electrical Controls
Switches for operation of ventilation equipment should be
marked and located conveniently. All intermittently operated ventilation
equipment shall be interconnected with the respective pit lighting system.
Consideration should be given also to automatic controls where intermittent
operation is used. The manual lighting ventilation switch shall override the
automatic controls.
4) Fans, Heating and Dehumidification
The fan wheel shall be fabricated from non-sparking
material. Automatic heating and dehumidification equipment shall be provided
in all dry wells. The electrical equipment and components shall meet the
requirements of subsection (c)(5) above.
5) Wet Wells
Wet well ventilation may be either continuous or
intermittent. Ventilation, if continuous, should provide at least 12 complete
air changes per hour; if intermittent, at least 30 complete air changes per
hour. Air shall be forced into the wet well by mechanical means rather than
exhausted from the wet well. Portable ventilation equipment shall be provided
for use at submersible pump stations and at wet wells with no permanently
installed ventilation equipment.
6) Dry Wells
Dry well ventilation may be either continuous or
intermittent. Ventilation, if continuous, should provide at least 6 complete
air changes per hour; if intermittent, at least 30 complete air changes per
hour. A system of two-speed ventilation with an initial ventilation rate of 30
changes per hour for 10 minutes and an automatic switch-over to 6 changes per
hour may be used to conserve heat.
h) Flow Measurement
Suitable devices for measuring sewage flow shall be provided
at all pumping stations. Indicating, totalizing and recording flow
measurement shall be provided at pumping stations with a 1200 gpm or greater
design peak flow. Elapsed time meters used in conjunction with pumping rate
tests may be used for pump stations with a design peak flow of up to 1200 gpm.
i) Water Supply
There shall be no physical connection between any potable
water supply and a sewage pumping station which under any conditions might
cause contamination of the potable water supply. If a potable water supply is
brought to the station, it should comply with conditions stipulated under
Section 370.146(b)(3). In-line backflow preventors shall not be used.