35 Ill. Adm. Code 6020.602.245
Source Construction Applications
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE F: PUBLIC WATER SUPPLIES
CHAPTER I: POLLUTION CONTROL BOARD
PART 602 PERMITS
SECTION 602.245 SOURCE CONSTRUCTION APPLICATIONS
Section 602.245
Source Construction Applications
a) Construction permit
applications for the construction of a new, or the modification of an existing,
well or surface water intake or the construction of a water main to transport
water purchased from another community water supply must include the following:
1) Existing and proposed finished water
quality, including:
A) Hardness;
B) Calcium;
C) Alkalinity;
D) pH;
E) Orthophosphate;
F) Silicate;
G) Total Dissolved Solids;
H) Oxidation-reduction
potential (ORP);
I) Temperature;
J) Chloride;
K) Sulfate;
L) Iron;
M) Manganese;
N) Chlorine residual
(total); and
O) Chlorine residual (free).
2) A recommendation of the
treatment necessary to reduce corrosion in household plumbing.
b) Well construction permit
applications must specify the following:
1) the latitude and
longitude of the well location;
2) the location and nature
of all potential routes, potential primary sources, and potential secondary
sources of contamination within 2,500 feet of the well location;
3) for sites subject to
flooding, the well casing heights and the maximum flood level based upon the
highest flood level specified in the best available information, such as the
flood of record, the 100-year flood projection, or the 500-year flood
projection;
4) a general aquifer
description;
5) the total well depth;
6) the well casing
diameter, material, depth, weight, height above ground, and thickness;
7) the grout type,
thickness, and depth;
8) the screen diameter,
material, slot size, and length, if applicable;
9) temporary capping and
security measures during well construction;
10) proposed
pump test procedures;
11) sampling
procedures, if necessary under 35 Ill. Adm. Code 611.212, for wells that may be
subject to surface water influences;
12) the type, design
capacity, head rating, and depth of pump setting;
13) the
column pipe diameter, length, material, and joint;
14) the
discharge pipe diameter, depth of cover, material, and valving;
15) the
casing vent diameter;
16) the
airline length;
17) the
location of the raw water sample tap;
18) a
description of how the top of the well casing is sealed;
19) a
description of access to the well site; and
20) well
hydraulics and aquifer property data.
c) The following
information must be submitted on plans for well construction permit
applications:
1) the well location with the
following information:
A) a 2,500-foot radius
showing the location of potential routes,
potential primary sources, and potential
secondary sources of contamination;
B) cleanup sites within
2,500 feet of the proposed well site with any of the following:
i) No Further Remediation
(NFR) letter;
ii) Groundwater Management
Zone (GMZ);
iii) Environmental Land Use
Covenant (ELUC); or
iv) an ordinance that restricts
the use of groundwater; and
C) a 400-foot radius showing
the location of the sources of pollution listed in 35 Ill. Adm. Code 604.150(a);
2) a cross-section of the
well showing finished grade, natural ground surface, vent, casing, column pipe,
screen, well depth, pump depth, grout, gravel pack, and discharge piping;
3) all discharge piping,
including pressure gauge, meter, sample tap, check valve, shut-off valve, and
vacuum/air release valve, if applicable;
4) well house construction,
if provided;
5) the locations of all
electrical junction boxes;
6) the locations of all observation
wells; and
7) piping showing the
ability to pump to waste.
d) The following
information must be submitted on plans for surface water intake construction
permit applications:
1) plan and profile views
of the intake structure showing the location, elevation of intake ports, fish
screens, valves, piping, and pumps, if applicable;
2) for sites subject to
flooding, the maximum flood level based upon the highest flood level specified
in the best available information, such as the flood of record, the 100-year flood
projection, or the 500-year flood projection;
3) location of inspection
manholes, if applicable; and
4) location of chemical
treatment, if applicable.