35 Ill. Adm. Code 6020.602.320
Partial Operating Permits
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE F: PUBLIC WATER SUPPLIES
CHAPTER I: POLLUTION CONTROL BOARD
PART 602 PERMITS
SECTION 602.320 PARTIAL OPERATING PERMITS
Section 602.320 Partial Operating
Permits
a) If all phases of a construction
project will not be completed at one time, the Agency must issue a partial
operating permit under Section 602.105 upon receipt of:
1) a cover letter describing which
sections of the project are completed;
2) a general layout plan sheet of
the project indicating the location of water mains, treatment processes, or
storage facilities to be operated;
3) a
completed and signed operating permit application; and
4) bacteriological analysis
results from water samples collected from the completed section of the project
verifying satisfactory disinfection in accordance with Section 602.310.
b) Additional operating
permits may be obtained in accordance with this Section as other portions of
the project are completed.