35 Ill. Adm. Code 6020.602.325
Operating Permit-by-Rule
TITLE 35: ENVIRONMENTAL PROTECTION
SUBTITLE F: PUBLIC WATER SUPPLIES
CHAPTER I: POLLUTION CONTROL BOARD
PART 602 PERMITS
SECTION 602.325 OPERATING PERMIT-BY-RULE
Section 602.325 Operating Permit-by-Rule
a) This
Section implements the permit-by-rule program provided for in Section 39.12 of
the Act for classes of community water supply operating permits. By fulfilling
all of the requirements of this Section, a community water supply is considered
to have met the requirements for obtaining an operating permit under Section
18(a)(3) of the Act and Section 602.300.
b) A
community water supply is eligible to obtain an operating permit-by-rule if the
construction project for which the Agency granted a construction permit is for
any of the following projects:
1) Water main extensions;
or
2) Projects
not requiring disinfection specified in Section 602.315.
c) A
community water supply is not eligible to obtain an operating permit-by-rule if
the construction project involves a water main that connects two or more
community water supplies.
d) Upon
issuance of a construction permit, the Agency may notify an eligible community
water supply that it may not seek a permit-by-rule if the community water
supply has failed to submit the information required by Agency or Board rules
in the two years preceding the Agency's notification.
e) For
construction projects that contain both permit-by-rule eligible and
non-eligible components, a community water supply may obtain a partial
operating permit-by-rule for the eligible portions of the project.
f) A
community water supply eligible for a permit-by-rule under subsection (b) that does
not elect to obtain a permit-by-rule, must obtain an operating permit issued by
the Agency before commencing operations.
g) Permit-by-Rule
Certification. Any community water supply seeking to obtain an operating
permit-by-rule must submit a certification, on Agency forms, specifying the
following:
1) the
community water supply's name, address, identification number and project name;
2) the
construction permit number, type of construction permit, and date the
construction permit was issued;
3) an
explanation of the status of the construction project and, if the project is
only partially completed, the information set forth in Section 602.320;
4) a
statement attesting to compliance with Section 602.310, if disinfection is
required; and
5) the
submission of the water sample results required by Section 602.310.
h) The
community water supply may begin operation of a permit-by-rule eligible
construction project immediately after it files the certification required by
subsection (g).