35 Ill. Adm. Code 602.220
Alterations
Section 602.220
Alterations
a) Before any deviations
from plans and specifications approved by the Agency are made, the owner or
official custodian, or an authorized delegate, must make a written request for
a supplemental permit. The written request must document all of the changes made
to the previously approved plans and specifications. Only those changes
identified will be considered for a supplemental permit.
b) Revised plans or
specifications must be submitted to and approved by the Agency with the
supplemental permit request.
c) The Agency must approve
supplemental permit requests if those requests comply with Section 602.105 and
this Subpart.
d) A supplemental permit is
not required for minor changes that will not affect the location, capacity,
hydraulic conditions, water treatment processes or sanitary or mineral quality
of the water to be delivered.
e) A supplemental permit
will not be granted to add water main after construction has begun, except for
additional water main necessary due to a change in the connection point to the
existing water distribution system or due to a change in
route or
alignment. A new application for construction permit must be submitted for
water main to serve additional users.