35 Ill. Adm. Code 604.1405
Installation of Water Mains
Section 604.1405 Installation of Water Mains
a) Except
as provided in 35 Ill. Adm. Code 602.200, a permit from the Agency is required
before the installation of a water main.
b) Bedding
1) A
continuous and uniform bedding must be provided in the trench for all buried
pipe.
2) Backfill
material must be tamped in layers around the pipe and to a sufficient height
above the pipe to adequately support and protect the pipe.
3) Stones
found in the trench must be removed for a depth of at least six inches below
the bottom of the pipe.
c) Water
mains must be placed at a sufficient depth, or covered with sufficient earth or
other insulation, to prevent freezing.
d) All
tees, bends, plugs and hydrants must be provided with reaction blocking (thrust
blocks), tie rods or joints designed to prevent pipe failure.
e) Installed
pipe must be pressure and leak tested.
f) New,
cleaned and repaired water mains must be disinfected in accordance with 35 Ill.
Adm. Code 602.310 and AWWA C651, incorporated by reference in 35 Ill. Adm. Code
601.115.
g) External Corrosion
1) In
areas where aggressive soil conditions are suspected, the community water
supply must perform analyses to determine the actual aggressiveness of the soil
unless protections in subsection (g)(2) are provided.
2) If
soils are found or known to be aggressive, the community water supply must
protect the water main, by methods including encasement of the water main in
polyethylene, provision of cathodic protection (in very severe instances), or
using corrosion resistant water main materials.