35 Ill. Adm. Code 704.183
Construction Requirements
Section 704
Section 704.183 Construction
Requirements
Existing wells must achieve
compliance with construction requirements as set forth in 35 Ill. Adm. Code 730
according to a compliance schedule established as a permit condition. The
owner or operator of a proposed new injection well must submit plans for
testing, drilling, and construction as part of the permit application. Except
as authorized by an area permit, no construction may commence until a permit
has been issued containing construction requirements (see Section 704.121). New
wells must be in compliance with these requirements prior to commencing
injection operations. Changes in construction plans during construction may be
approved by the Agency as minor modifications. (See 35 Ill. Adm. Code
702.187.) No such changes may be physically incorporated into construction of
the well prior to approval of the modification by the Agency.
BOARD NOTE: Derived from 40 CFR
144.52(a)(1) (2005).