35 Ill. Adm. Code 663.430
Loan Eligible Costs
Section 663.430 Loan Eligible Costs
The loan recipient shall be paid, upon request, in
accordance with Section 663.440, for all costs within the scope of the approved
project, not to exceed the total amount of the loan, and that are determined to
be eligible in accordance with the following criteria:
a) Eligible
project costs include all reasonable and necessary costs directly attributable
to the project's planning, design, or construction that are not otherwise
excluded by this Part. Categories of necessary costs include, but are not
limited to, the following:
1) The
direct purchase of materials, equipment, and personal services not under the
approved construction contract necessary for the completion of a loan funded
project;
2) Professional
and consultant services contracts necessary for planning, design, bidding, and
construction of a loan funded project, except as elsewhere limited by this
Part;
3) Costs
under approved construction contracts;
4) Costs
under a construction contract executed prior to the award of the loan agreement
only when the loan applicant has received written approval from the Agency
prior to the award of the construction contract; and
5) Costs
associated with activities described in Appendix A.
b) Ineligible project costs
include, but are not limited to, the following:
1) Laboratory
fees for routine compliance monitoring;
2) Operation
and maintenance expenses;
3) Costs
outside the scope of the approved Project Plan;
4) Construction
of any facilities that do not fall within the definition of a community water
supply facility as contained in the SDWA or do not qualify in meeting the
federal green project reserve requirements;
5) Costs
of projects whose main purpose is fire protection or servicing future growth;
6) Corrosion
control studies and corrosion control infrastructure;
7) Water
meters;
8) Bottled
water; and
9) Premise
plumbing.