35 Ill. Adm. Code 663.420
Post-Loan Issuance Construction Contract Requirements
Section 663.420 Post
-
Loan Issuance Construction
Contract Requirements
a) The
loan recipient shall provide construction engineering and project monitoring to
assure that the construction substantially conforms to the approved plans and
specifications.
b) The
following procedures shall apply to construction contracts awarded by loan
recipients for the construction phase only. They shall not apply to personal
and professional service contracts.
1) Executed
Contract. For each construction contract awarded, the loan recipient shall
submit an executed contract, performance, and payment bond for the bid amount,
certificate of insurance with the loan recipient added as additional insured,
and the notice to proceed.
2) Change
Orders
A) When
the loan recipient authorizes the contractor to add, delete, or revise the work
within the general scope of the contract documents, or authorizes an adjustment
in the contract price or contract time, the loan recipient shall submit a
change order to the Agency.
B) For
each change order, the loan recipient shall submit to the Agency for approval the
following documentation:
i) one
copy of the fully executed change order signed by the loan recipient,
construction engineer, and the contractor; and
ii) a
description of any changes, with justification for the changes.
C) Prior
approval by the Agency of a change order is required when a change order
results in an increase in the amount of loan funds needed to complete the
project.
D) Failure
to give timely notice of proposed project changes or action by the loan
recipient that is not consistent with the Agency's determination on those
changes may result in disallowance of loan participation for costs incurred
that are attributable to the change.