35 Ill. Adm. Code 702.126
Signatories to Permit Applications and Reports
Section 702
Section 702.126 Signatories
to Permit Applications and Reports
a) Applications. A permit application must be signed as follows:
1) For a corporation: a permit application must be signed by a
responsible corporate officer. For the purpose of this Section, a responsible
corporate officer means either of the following persons:
A) A president, secretary, treasurer, or vice president of the
corporation in charge of a principal business function, or any other person
that performs similar policy or decision-making functions for the corporation; or
B) The manager of one or more manufacturing, production, or
operating facilities employing more than 250 persons or having gross annual
sales or expenditures exceeding $25 million (in second-quarter 1980 dollars),
if authority to sign documents has been assigned or delegated to the manager in
accordance with corporate procedures;
BOARD NOTE: The Board does not require specific assignments
or delegations of authority to responsible corporate officers identified in
subsection (a)(l)(A). The Agency will presume that these responsible corporate
officers have the requisite authority to sign permit applications unless the
corporation has notified the Agency to the contrary. Corporate procedures
governing authority to sign permit applications may provide for assignment or
delegation to applicable corporate positions pursuant to subsection (a)(l)(B),
rather than to specific individuals.
2) For a partnership or sole proprietorship: a permit
application must be signed by a general partner or the proprietor,
respectively; or
3) For a municipality, State, federal, or other public agency: a
permit application must be signed by either a principal executive officer or
ranking elected official. For purposes of this Section, a principal executive
officer of a federal agency includes either of the following persons:
A) The chief executive officer of the agency, or
B) A senior executive officer having responsibility for the
overall operations of a principal geographic unit of the agency (e.g., Regional
Administrators of USEPA).
b) Reports. All reports required by permits or other information
requested by the Agency must be signed by a person described in subsection (a),
or by a duly authorized representative of that person. A person is a duly
authorized representative only if each of the following conditions are
fulfilled:
1) The authorization is made in writing by a person described in
subsection (a);
2) The authorization specifies either an individual or a position
having responsibility for the overall operation of the regulated facility or
activity, such as the position of plant manager, operator of a well or a well
field, superintendent, or position of equivalent responsibility. (A duly
authorized representative may thus be either a named individual or any
individual occupying a named position); and
3) The written authorization is submitted to the Agency.
c) Changes to Authorization. If an authorization pursuant to subsection
(b) is no longer accurate because a different individual or position has
responsibility for the overall operation of the facility, a new authorization
satisfying the requirements of subsection (b) must be submitted to the Agency
prior to or together with any reports, information, or applications to be
signed by an authorized representative.
d) Certification
1) Any person signing a document pursuant to subsection (a) or
(b) must make the following certification:
I certify under penalty of law that this document and all
attachments were prepared under my direction or supervision in accordance with
a system designed to assure that qualified personnel properly gather and
evaluate the information submitted. Based on my inquiry of the person or
persons that manage the system, or those persons directly responsible for
gathering the information, the information submitted is, to the best of my
knowledge and belief, true, accurate, and complete. I am aware that there are
significant penalties for submitting false information, including the
possibility of fine and imprisonment for knowing violations.
2) Alternative Owner Certification. For remedial action plans
(RAPs) pursuant to Subpart H, if the operator certifies according to
subsection (d)(1), then the owner may choose to make the following
certification instead of the certification in subsection (d)(1):
Based on my knowledge of the conditions of the property
described in the RAP and my inquiry of the person or persons that manage the
system referenced in the operator's certification, or those persons directly
responsible for gathering the information, the information submitted is, upon
information and belief, true, accurate, and complete. I am aware that there
are significant penalties for submitting false information, including the
possibility of fine and imprisonment for knowing violations.
BOARD NOTE:
Derived from 40 CFR 144.32 and 270.11 (2017).