35 Ill. Adm. Code 724.297
Closure and Post-Closure Care
Section 724
Section 724.297Â Closure and
Post-Closure Care
a)Â Â Â Â Â Â Â Â At closure of a tank system, the owner or operator must remove
or decontaminate all waste residues, contaminated containment system components
(liners, etc.), contaminated soils and structures and equipment contaminated
with waste, and manage them as hazardous waste, unless 35 Ill. Adm. Code
721.103(d) applies. The closure plan, closure activities, cost estimates for
closure and financial responsibility for tank systems must meet all of the
requirements specified in Subparts G and H.
b)Â Â Â Â Â Â Â Â If the owner or operator demonstrates to the Agency by way of
permit application that not all contaminated soils can be practicably removed
or decontaminated, as required in subsection (a), then the owner or operator must
close the tank system and perform post-closure care in accordance with the
closure and post-closure care requirements that apply to landfills (Section
724.410). In addition, for the purposes of closure, post-closure and financial
responsibility, such a tank system is then considered to be a landfill, and the
owner or operator must meet all of the requirements for landfills specified in
Subparts G and H.
c)Â Â Â Â Â Â Â Â If an owner or operator has a tank system that does not have
secondary containment which meets the requirements of Section 724.193(b)
through (f), and the owner and operator has not been granted alternative design
and operating practices for secondary containment requirements in accordance
with Section 724.293(g), then the following apply:
1)Â Â Â Â Â Â Â Â The closure plan for the tank system must include both a plan
for complying with subsection (a) and a contingent plan for complying with
subsection (b).
2)Â Â Â Â Â Â Â Â A contingent post-closure plan for complying with subsection
(b) must be prepared and submitted as part of the permit application.
3)Â Â Â Â Â Â Â Â The cost estimates calculated for closure and post-closure
care must reflect the costs of complying with the contingent closure plan and
the contingent post-closure plan if those costs are greater than the costs of
complying with the closure plan prepared for the expected closure under
subsection (a).
4)Â Â Â Â Â Â Â Â Financial assurance must be based on the cost estimates in
subsection (c)(3).
5)Â Â Â Â Â Â Â Â For the purposes of the contingent closure and post-closure
plans, such a tank system is considered to be a landfill, and the contingent
plans must meet all of the closure, post-closure, and financial responsibility
requirements for landfills under Subparts G and H.