35 Ill. Adm. Code 724.960
Standards: Closed-Vent Systems and Control Devices
Section 724
Section 724.960Â Standards:Â Closed-Vent
Systems and Control Devices
a)Â Â Â Â Â Â Â Â An owner or operator of a closed-vent system or control device
subject to this Subpart BB must comply with the provisions of Section 724.933.
b)Â Â Â Â Â Â Â Â Implementation Schedule
1)Â Â Â Â Â Â Â Â The owner or operator of an existing facility that cannot
install a closed-vent system and control device to comply with the provisions
of this Subpart BB on the effective date that the facility becomes subject to
the provisions of this Subpart BB must prepare an implementation schedule that
includes dates by which the closed-vent system and control device will be
installed and in operation. The controls must be installed as soon as
possible, but the implementation schedule may allow up to 30 months after the
effective date that the facility becomes subject to this Subpart BB for
installation and startup.
2)Â Â Â Â Â Â Â Â Any unit that is subject to the provisions of this Subpart BB
when operation begins, must comply with the rules immediately (i.e., the unit
must have control devices installed and operating on startup of the affected
unit); the 30-month implementation schedule does not apply.
3)Â Â Â Â Â Â Â Â The owner or operator of any facility in existence on the
effective date of a statutory or regulatory amendment that renders the facility
subject to this Subpart BB must comply with all requirements of this Subpart BB
as soon as practicable but no later than 30 months after the effective date of the
amendment. When control equipment required by this Subpart BB cannot be
installed and begin operation by the effective date of the amendment, the
facility owner or operator must prepare an implementation schedule that
includes the following information:Â specific calendar dates for award of
contracts or issuance of purchase orders for the control equipment, initiation
of on-site installation of the control equipment, completion of the control
equipment installation, and performance of any testing to demonstrate that the
installed equipment meets the applicable standards of this Subpart BB. The
owner or operator must enter the implementation schedule in the operating
record or in a permanent, readily available file located at the facility.
4)Â Â Â Â Â Â Â Â An owner or operator of a facility or unit that becomes newly
subject to the requirements of this Subpart BB due to an action other than
those described in subsection (b)(3) must comply with all applicable
requirements immediately (i.e., the facility or unit must have control devices
installed and operating on the date the facility or unit becomes subject to
this Subpart BB; the 30-month implementation schedule does not apply).