35 Ill. Adm. Code 725.353
Containment
Section 725
Section 725.353Â Containment
If leachate or run-off from a
pile is a hazardous waste, then control of the leachate or run-off must be
accomplished by either of the following means:
a)Â Â Â Â Â Â Â Â Control by Pile Design, Construction, and Operation
1)Â Â Â Â Â Â Â Â The pile must be placed on an impermeable base that is
compatible with the waste under the conditions of treatment or storage;
2)Â Â Â Â Â Â Â Â The owner or operator must design, construct, operate and
maintain a run-on control system capable of preventing flow onto the active
portion of the pile during peak discharge from at least a 25-year storm;
3)Â Â Â Â Â Â Â Â The owner or operator must design, construct, operate and
maintain a run-off management system to collect and control at least the water
volume resulting from a 24-hour, 25-year storm; and
4)Â Â Â Â Â Â Â Â Collection and holding facilities (e.g., tanks or basins)
associated with run-on and run-off control systems must be emptied or otherwise
managed expeditiously to maintain design capacity of the system; or
b)Â Â Â Â Â Â Â Â Alternative Control
1)Â Â Â Â Â Â Â Â The pile must be protected from precipitation and run-on by
some other means; and
2)Â Â Â Â Â Â Â Â No liquids or wastes containing free liquids may be placed in
the pile.
BOARD NOTE:Â
If collected leachate or run-off is discharged through a point source to waters
of the United States, it is subject to the requirements of Section 12 of the
Act.