35 Ill. Adm. Code 730.133
Operating, Monitoring, and Reporting Requirements
Section 730
Section 730.133 Operating,
Monitoring, and Reporting Requirements
a) Operating Requirements. Operating requirements prescribed
must, at a minimum, specify each of the following:
1) That, except during well stimulation, the injection pressure
at the wellhead must be calculated so as to assure that the pressure in the
injection zone during injection does not initiate new fractures or propagate
existing fractures in the injection zone. In no case must injection pressure
initiate fractures in the confining zone or cause the migration of injection or
formation fluids into an underground source of drinking water; and
2) That injection between the outermost casing protecting
underground sources of drinking water and the well bore is prohibited.
b) Monitoring Requirements
1) Monitoring requirements must, at a minimum, specify the following
information:
A) Monitoring of the nature of injected fluids with sufficient
frequency to yield representative data on its characteristics. Whenever the
injection fluid is modified to the extent that the analysis required by Section
730.134 (a)(7)(C) is incorrect or incomplete, the owner or operator must
provide the Agency with a new analysis as required by Section 730.134
(a)(7)(C);
B) Monitoring of injection pressure and either flow rate or volume
semimonthly, or metering and daily recording of injected and produced fluid
volumes, as appropriate;
C) Demonstration of mechanical integrity pursuant to Section
730.108 at least once every five years during the life of the well for salt
solution mining;
D) Monitoring of the fluid level in the injection zone
semi-monthly, where appropriate, and monitoring of the parameters chosen to
measure water quality in the monitoring wells required by Section 730.132(e)
semi-monthly; and
E) Quarterly
monitoring of wells required by Section 730.132(g).
2) A Class III injection well may be monitored on a field or
project basis, rather than on an individual well basis, by manifold
monitoring. Manifold monitoring may be used in cases of facilities consisting
of more than one injection well operating with a common manifold. Separate
monitoring systems for each well are not required provided the owner or
operator demonstrates that manifold monitoring is comparable to individual well
monitoring.
c) Reporting Requirements
1) Reporting requirements must, at a minimum, include the following
information set forth in subsections (c)(1) and (c)(2):
A) Quarterly
reporting to the Agency on required monitoring; and
B) Results of mechanical integrity and any other periodic test
required by the Agency reported with the first regular quarterly report after
the completion of the test.
2) Monitoring may be reported on a project or field basis rather
than individual well basis where manifold monitoring is used.