35 Ill. Adm. Code 731.162
Initial Abatement Measures and Site Check
Section 731
Section 731.162 Initial
Abatement Measures and Site Check
a) Owners and operators must perform the following abatement
measures:
1) Remove as much of the regulated substance from the UST system
as is necessary to prevent further release to the environment;
2) Visually inspect any aboveground releases or exposed
belowground releases and prevent further migration of the released substance
into surrounding soils and groundwater;
3) Continue to monitor and mitigate any additional fire and
safety hazards posed by vapors or free product that have migrated from the UST
excavation zone and entered into substance structures (such as sewers or
basements);
4) Remedy hazards posed by contaminated soils that are excavated
or exposed as a result of release confirmation, site investigation, abatement
or corrective action activities. If these remedies include treatment or
disposal of soils, the owner and operator must comply with 35 Ill. Adm. Code
722, 724, 725 and 807 through 815.
5) Measure for the presence of a release where contamination is
most likely to be present at the UST site, unless the presence and source of
the release have been confirmed in accordance with the site check or the
closure site assessment. In selecting sample types, sample locations and
measurement methods, the owner and operator must consider the nature of the
stored substance, the type of backfill, depth to groundwater and other factors
as appropriate for identifying the presence and source of the release; and
6) Investigate to determine the possible presence of free
product, and begin free product removal as soon as practicable and in
accordance with Section 731.164.
b) Within 20 days after release confirmation, owners and
operators must submit a report to the Agency, summarizing the initial abatement
steps taken under subsection (a) and any resulting information or data.