35 Ill. Adm. Code 731.163
Initial Site Characterization
Section 731
Section 731.163 Initial Site
Characterization
a) Owners and operators must assemble information about the site
and the nature of the release, including information gained while confirming
the release or completing the initial abatement measures in Section 731.160 and
Section 731.161. This information must include, but is not necessarily limited
to the following:
1) Data on the nature and estimated quantity of release;
2) Data from available sources or site investigations concerning
the following factors: surrounding populations, water quality, use and
approximate locations of wells potentially affected by the release, subsurface
soil conditions, locations of subsurface sewers, climatological conditions and
land use;
3) Results of the site check required under Section
731.162(a)(5); and
4) Results of the free product investigations required under
Section 731.162(a)(6), to be used by owners and operators to determine whether
free product must be recovered under Section 731.164.
b) Within 45 days after confirmation of the release, owners and
operators must submit the information collected in compliance with subsection
(a) to the Agency, in a manner that demonstrates its applicability and
technical adequacy.