35 Ill. Adm. Code 742.1100
Engineered Barriers
Section 742
Section 742.1100Â Engineered
Barriers
a)Â Â Â Â Â Â Â Â Any person who develops remediation objectives under this Part
based on engineered barriers shall meet the requirements of this Subpart and
the requirements of Subpart J relative to institutional controls.
b)Â Â Â Â Â Â Â Â The Agency shall not approve any remediation objective under
this Part that is based on the use of engineered barriers unless the person has
proposed engineered barriers meeting the requirements of this Subpart.
c)Â Â Â Â Â Â Â Â The use of engineered barriers can be recognized in
calculating remediation objectives only if the engineered barriers are intended
for use as part of the final corrective action.
d)Â Â Â Â Â Â Â Â Any no further remediation determination based upon the use of
engineered barriers shall require effective maintenance of the engineered
barrier. The maintenance requirements shall be included in an institutional
control under Subpart J. This institutional control shall address provisions
for temporary breaches of the barrier by requiring the following if intrusive
construction work is to be performed in which the engineered barrier is to be
temporarily breached:
1)Â Â Â Â Â Â Â Â The construction workers shall be notified by the site
owner/operator in advance of intrusive activities. Such notification shall
enumerate the contaminant of concern known to be present; and
2)Â Â Â Â Â Â Â Â The site owner/operator shall require construction workers to
implement protective measures consistent with good industrial hygiene practice.
e)Â Â Â Â Â Â Â Â Failure to maintain an engineered barrier in accordance with
that no further remediation determination shall be grounds for voidance of the
determination and the instrument memorializing the Agency's no further
remediation determination.