35 Ill. Adm. Code 742.320
Groundwater Ingestion Exposure Route
Section 742
Section 742.320 Groundwater
Ingestion Exposure Route
The groundwater ingestion
exposure route may be excluded from consideration if:
a) The requirements of Sections 742.300 and 742.305 are met;
b) The corrective action measures have been completed to remove
any free product to the maximum extent practicable;
c) The source of the release is not located within the minimum or
designated maximum setback zone or within a regulated recharge area of a
potable water supply well;
d) As demonstrated in accordance with Section 742.1015, for any
area within the measured and modeled extent of groundwater contamination above
what would otherwise be the applicable Tier 1 groundwater remediation
objectives, an ordinance adopted by a unit of local government is in place that
effectively prohibits the installation of potable water supply wells (and the
use of such wells);
e) As demonstrated using Equation R26, in Appendix C, Table C, in
accordance with Section 742.810, the concentration of any contaminant of
concern in groundwater within the minimum or designated maximum setback zone of
an existing potable water supply well will meet the applicable Tier 1
groundwater remediation objective; and
f) As demonstrated using Equation R26, in Appendix C, Table C, in
accordance with Section 742.810, the concentration of any contaminant of
concern in groundwater discharging into a surface water will meet the applicable
surface water quality standard under 35 Ill. Adm. Code 302.